Skip to content

Ghorpadi, Pune

Deedo IDDL-PUN-GHORPADI

6 in 10 MahaRERA registrations here have pushed their completion date back.

RERA projects36
Registrations36
Completion still due2610 past their date
Median extension4 months64% of registrations extended
Regulatory cases4on 1 project
Ghorpadi market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

8 in 10 registrations run late here

36 MahaRERA registrations in Ghorpadi

7 not yet due19 extended, not yet due10 past even the latest date

Extended registrations moved their completion date by a median of 4 months.

Projects in Ghorpadi

36 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
F5 SkyraAnand Construction CompanyDue Sep 2030——
LuxoraMr. Mukesh Kishanchand Khaitan Mrs. Usha Mukesh KhaitanDue Apr 2029, extended 4 mo——
One Place-Bund Garden RoadTopspace Landmarks LLPDue Apr 2033, extended 4 mo——
Magnar OneRyse Landmarks LLPDue Apr 2031, extended 4 mo——
9 Tara CrestSrichaitanya Space Private LimitedDue Jul 2030, extended 4 mo——
Clover AmanoClover Buildcon Private LimitedDue Oct 2029, extended 4 mo—0%
K P OneShri Laxmi Narayan Properties LLPDue Dec 2028, extended 4 mo——
Casa Verde - A WingSkyboat Infrastructure Unit-1 LLPDue Apr 2028, extended 4 mo——
Sky Suites By BramhacorpBramhacorp LimitedDue Apr 2030, extended 4 mo——
AmairaPridecraft DevelopersDue Oct 2028, extended 4 mo——
Surobhi EliteSSRPL Pune LLPDue Nov 2027, extended 4 mo—0%
Surobhi RegencySSRPL Pune LLPDue Jul 2027—0%
65 OrravitaGagan Galaxy Housing LLPDue Dec 2029——
Bird Nest Cooperative Housing Society LimitedViraj PropertiesDue May 2028, extended 4 mo—56%
Boulevard Wing B 1Bramhacorp LimitedDue Apr 2029, extended 4 mo—20%
Boulevard Tower A2Bramhacorp LimitedDue Apr 2027, extended 4 mo——
Hues Of SkyBramhacorp LimitedDue Apr 2030, extended 4 mo——
Bund Garden ProjectLodha Developers LimitedDue Aug 2028, extended 4 mo——
Ratna PandhariM/S Vijay Developers3 yrs 7 mo late—25%
TruSpace PremieraAtharva Enterprises1 yr 1 mo late——
CasaverdeSkyboat Infrastructure Unit 1 LLPDue Apr 2027, extended 4 mo—14%
Sky OneA K DevelopersDue Dec 2026—12%
Ivy By Vistaara HomesVistaarahomes Realty LLPDue Apr 2027, extended 4 mo—38%
Pinnacle Northern GatesGajendra Dattatraya PawarDue Dec 2027, extended 3 yrs—7%
Opulent StarlitOpulent DevelopersDue Oct 2027, extended 4 mo—56%

Most active promoters

  1. Bramhacorp Limited6 projects
  2. Ranade Realtors LLP2 projects
  3. Skyboat Infrastructure Unit 1 LLP2 projects
  4. SSRPL Pune LLP2 projects
  5. Abil Propcon LLP1 project
  6. A K Developers1 project
  7. Anand Construction Company1 project
  8. Arun Sheth Properties1 project
  9. Atharva Enterprises1 project
  10. Cedrus Assets1 project
Data through28 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology