Completion was pushed back 4 months, to Apr 2027; no MahaRERA orders on record; 14% of its units are booked.

Ghorpadi, Pune 411001 · Promoter: Skyboat Infrastructure Unit 1 LLP

DeliveryExtended 4 moPromised Dec 2026 · now due Apr 2027RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales14% booked4 of 28 units · as the promoter reported to MahaRERA
Casaverde project report cardPDF: delivery, regulatory orders, people on record, every tower and the registered deals — for your bank or lawyerSee what's inside · from ₹1,499

Completion was pushed back 4 months, to Apr 2027

  • This projectRegistered 7 Nov 2022, completion promised 31 Dec 2026, revised to 30 Apr 2027.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100047518
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P521000475187 Nov 202231 Dec 202630 Apr 2027Skyboat Infrastructure Unit 1 LLPProject page
Documents139

1 document held by Deedo, 138 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardSkyboat Unit 1 - PAN.pdf · uploaded 23 Sep 2022Source

Legal

  • Legal Title reportFormat A (2)_compressed.pdf · uploaded 23 Sep 2022Source
  • Legal Title reportLegal Search Title Report.pdf · uploaded 23 Sep 2022Source
  • Declaration Form BForm B - Promoter.pdf · uploaded 23 Sep 2022Source
  • Other – Legal109 a_compressed-1-50.pdf · uploaded 27 Nov 2023Source
  • Other – Legal109 a_compressed-51-100.pdf · uploaded 27 Nov 2023Source
  • Other – Legal109 a_compressed-101-145.pdf · uploaded 27 Nov 2023Source
Show all 139 documentsShow fewer documents

Migrated

  • 1 PAN CardSkyboat Unit 1 - PAN.pdf · uploaded 23 Sep 2022Source
  • 1 Copy of the legal title reportFormat A (2)_compressed.pdf · uploaded 23 Sep 2022Source
  • 2 Copy of the legal title reportLegal Search Title Report.pdf · uploaded 23 Sep 2022Source
  • 1 a Details of encumbrances concerned to FinanceEncumbrances.pdf · uploaded 23 Sep 2022Source
  • 1 b Details of encumbrances concerned to LegalEncumbrances.pdf · uploaded 23 Sep 2022Source
  • 1 Copy of Layout Approval (in case of layout)scan 260243531011 (1).pdf · uploaded 23 Sep 2022Source
  • 1 Building Plan Approval / NA Order for plotted developmentscan 260243531012 (1).pdf · uploaded 23 Sep 2022Source
  • 1 Commencement Certificates / NA Order for plotted developmentSKMBT_C36022091903530_0001.pdf · uploaded 23 Sep 2022Source
  • 1 Declaration about Commencement CertificateDeclaration Form (1).pdf · uploaded 23 Sep 2022Source
  • 1 Declaration in FORM BForm B - Promoter.pdf · uploaded 23 Sep 2022Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architects Certificate (1).pdf · uploaded 23 Sep 2022Source
  • 1 CERSAI detailsCERSAI_Search_Report_200248201982_For_Asset_Based_Search_27_09_2022_12_39_16_690.pdf · uploaded 23 Sep 2022Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Final Form 3 27 09 2022.pdf · uploaded 23 Sep 2022Source
  • 1 Proforma of Allotment letterModel Copy of Allotment letter_compressed (1).pdf · uploaded 23 Sep 2022Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the samebank Declaration.pdf · uploaded 23 Sep 2022Source
  • 1 Deviation Report with respect to Allotment letterDeviation report allotment letter.pdf · uploaded 23 Sep 2022Source
  • 1 Deviation Report with respect to model copy of AgreementRevise Deviation Report - 01 11 2022_compressed.pdf · uploaded 23 Sep 2022Source
  • 1 Proforma of Agreement for saleAgreement to sale -02 11 2022.pdf · uploaded 28 Sep 2022Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 18 Feb 2023Source
  • 1 Disclosure of sold/ booked inventoryCasa verde (3).pdf · uploaded 18 Feb 2023Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 23 Feb 2023Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Casaverde form 2.pdf · uploaded 2 Mar 2023Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 4 Mar 2023Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate - Casa Verde (2).pdf · uploaded 23 Jun 2023Source
  • 2 Disclosure of sold/ booked inventorySold Unsold - Casa Verde.pdf · uploaded 23 Jun 2023Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)f1.pdf · uploaded 14 Oct 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)casaverde october 23 qu (1).pdf · uploaded 14 Oct 2023Source
  • 3 Disclosure of sold/ booked inventorysold unsold.pdf · uploaded 14 Oct 2023Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Casa Verde - Statment (2).pdf · uploaded 27 Nov 2023Source
  • 1 Other – Legal109 a_compressed-1-50.pdf · uploaded 27 Nov 2023Source
  • 2 Other – Legal109 a_compressed-51-100.pdf · uploaded 27 Nov 2023Source
  • 3 Other – Legal109 a_compressed-101-145.pdf · uploaded 27 Nov 2023Source
  • 2 a Details of encumbrances concerned to Financerera encumbrance.pdf · uploaded 28 Nov 2023Source
  • 2 b Details of encumbrances concerned to Legalrera encumbrance.pdf · uploaded 28 Nov 2023Source
  • 3 a Details of encumbrances concerned to Financeencumbrance letter.pdf · uploaded 4 Dec 2023Source
  • 3 b Details of encumbrances concerned to Legalencumbrance letter.pdf · uploaded 4 Dec 2023Source
  • 2 Proforma of Agreement for saleRERA Agreement.pdf · uploaded 11 Dec 2023Source
  • 3 Proforma of Agreement for saleFinal Agreement - Draft - 22-11-2023 - Finance_ Reviewed by Piramal legal (1).pdf · uploaded 14 Dec 2023Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate - Skyboat 1 - DEC 23.pdf · uploaded 24 Jan 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate - Jun 23.pdf · uploaded 27 Jan 2024Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate - Sep 23.pdf · uploaded 27 Jan 2024Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Sky ENGG CER MAR 23.pdf · uploaded 27 Jan 2024Source
  • 4 Disclosure of sold/ booked inventorySkyboat unit 1 - Sold unsold.pdf · uploaded 27 Jan 2024Source
  • 5 Disclosure of sold/ booked inventorySkyboat - sold - unsold - 31 Dec 2023.pdf · uploaded 27 Jan 2024Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3 March 2023 (2).pdf · uploaded 27 Jan 2024Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Skyboat From 3 - 30-06-2023.pdf · uploaded 27 Jan 2024Source
  • 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)Skyboat From 3 - 30-09-2023.pdf · uploaded 27 Jan 2024Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate - DEC 23.pdf · uploaded 31 Jan 2024Source
  • 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Dec 2023.pdf · uploaded 31 Jan 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Skyboat unit 1 - Statement (1).pdf · uploaded 31 Jan 2024Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate - MAR 24.pdf · uploaded 30 Apr 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Dec 24 - Skyboat Unit 1.pdf · uploaded 30 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate Dec 24 - Skyboat Unit 1.pdf · uploaded 30 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate - MAR 25 -SKYBOAT (1).pdf · uploaded 8 Apr 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)casa Verde form 2.pdf · uploaded 8 Apr 2025Source
  • 1 Disclosure of sold/ booked inventorySold Unsold - Skyboat Unit 1 - MAR 25 (1).pdf · uploaded 8 Apr 2025Source
  • Form 1form 1.pdf · uploaded 9 Aug 2025Source
  • Form 2form 2.pdf · uploaded 9 Aug 2025Source
  • Form 3form 3.pdf · uploaded 9 Aug 2025Source
  • Disclosure of Sold and Booked Inventorysold unsold.pdf · uploaded 9 Aug 2025Source
  • Form 1form 1.pdf · uploaded 9 Aug 2025Source
  • Form 2form 2.pdf · uploaded 9 Aug 2025Source
  • Form 3form 3.pdf · uploaded 9 Aug 2025Source
  • Disclosure of Sold and Booked Inventorysold unsold.pdf · uploaded 9 Aug 2025Source
  • Form 1form 1.pdf · uploaded 9 Aug 2025Source
  • Form 2form 2.pdf · uploaded 9 Aug 2025Source
  • Form 3form 3.pdf · uploaded 9 Aug 2025Source
  • Disclosure of Sold and Booked Inventorysold unsold.pdf · uploaded 9 Aug 2025Source
  • Form 1form 1.pdf · uploaded 12 Aug 2025Source
  • Form 2form 2.pdf · uploaded 12 Aug 2025Source
  • Form 3form 3.pdf · uploaded 12 Aug 2025Source
  • Disclosure of Sold and Booked Inventorysold unsold.pdf · uploaded 12 Aug 2025Source
  • Form 1form 1.pdf · uploaded 12 Aug 2025Source
  • Form 2form 2.pdf · uploaded 12 Aug 2025Source
  • Form 3form 3.pdf · uploaded 12 Aug 2025Source
  • Disclosure of Sold and Booked Inventorysold unsold.pdf · uploaded 12 Aug 2025Source
  • Form 1form 1.pdf · uploaded 12 Aug 2025Source
  • Form 2form 2.pdf · uploaded 12 Aug 2025Source
  • Form 3form 3.pdf · uploaded 12 Aug 2025Source
  • Disclosure of Sold and Booked Inventorysold unsold.pdf · uploaded 12 Aug 2025Source
  • Form 1form 1.pdf · uploaded 14 Aug 2025Source
  • Form 2form 2.pdf · uploaded 14 Aug 2025Source
  • Form 3form 3.pdf · uploaded 14 Aug 2025Source
  • Disclosure of Sold and Booked InventorySold unsold.pdf · uploaded 14 Aug 2025Source
  • Form 1form 1.pdf · uploaded 14 Aug 2025Source
  • Form 2form 2.pdf · uploaded 14 Aug 2025Source
  • Form 3Form 3.pdf · uploaded 14 Aug 2025Source
  • Disclosure of Sold and Booked InventorySold unsold.pdf · uploaded 14 Aug 2025Source
  • Form 1form 1.pdf · uploaded 14 Aug 2025Source
  • Form 2FORM 2.pdf · uploaded 14 Aug 2025Source
  • Form 3Form 3.pdf · uploaded 14 Aug 2025Source
  • Disclosure of Sold and Booked Inventorysold unsold.pdf · uploaded 14 Aug 2025Source
  • Form 2A (FY 2022-2023)2022-2023.pdf · uploaded 14 Aug 2025Source
  • Form 2A (FY 2023-2024)2023-2024.pdf · uploaded 14 Aug 2025Source
  • Form 2A (FY 2024-2025)2024-2025.pdf · uploaded 14 Aug 2025Source
  • Form 5 (FY 2022-2023)2022-2023.pdf · uploaded 14 Aug 2025Source
  • Form 5 (FY 2023-2024)2023-2024.pdf · uploaded 14 Aug 2025Source
  • Form 5 (FY 2024-2025)SKYBAOT -2024-25 FORM 5 (1) (1).pdf · uploaded 31 Oct 2025Source
  • Form 1form 1.pdf · uploaded 3 Nov 2025Source
  • Form 2Engineer Certificate - Jun 23 s.pdf · uploaded 3 Nov 2025Source
  • Form 3FORM 3 s.pdf · uploaded 3 Nov 2025Source
  • Disclosure of Sold and Booked Inventorysold unsold.pdf · uploaded 3 Nov 2025Source
  • Form 1Form 1 s.pdf · uploaded 3 Nov 2025Source
  • Form 2Form 2 s.pdf · uploaded 3 Nov 2025Source
  • Form 3Form 3 s.pdf · uploaded 3 Nov 2025Source
  • Disclosure of Sold and Booked InventorySold Unsold.pdf · uploaded 3 Nov 2025Source
  • Withdrawal Update Form 1Form 1 Sep 2025.pdf · uploaded 4 Dec 2025Source
  • Withdrawal Update Form 1Form 1 Sep 2025.pdf · uploaded 4 Dec 2025Source
  • Withdrawal Update Form 2Engineering certificate.pdf · uploaded 4 Dec 2025Source
  • Withdrawal Update Form 2Engineering certificate.pdf · uploaded 4 Dec 2025Source
  • Withdrawal Update Form 3Form 3 (1) (1).pdf · uploaded 4 Dec 2025Source
  • Withdrawal Update Form 3Form 3 (1) (1).pdf · uploaded 4 Dec 2025Source
  • Withdrawal Update Form 1Updated - AR - Dec 25 .pdf · uploaded 26 May 2026Source
  • Withdrawal Update Form 1AR - March 26 .pdf · uploaded 26 May 2026Source
  • Withdrawal Update Form 2ER - Dec 25 .pdf · uploaded 26 May 2026Source
  • Withdrawal Update Form 2ER - March 26 .pdf · uploaded 26 May 2026Source
  • Withdrawal Update Form 3CA - Dec 25Final.pdf · uploaded 26 May 2026Source
  • Withdrawal Update Form 3CA - March 26 ..pdf · uploaded 26 May 2026Source

Technical

  • Documentscan 260243531011 (1).pdf · uploaded 23 Sep 2022Source
  • Documentscan 260243531012 (1).pdf · uploaded 23 Sep 2022Source
  • DocumentCC_0001.pdf · uploaded 15 Sep 2025Source
  • Documentmain layout_compressed (4).pdf · uploaded 15 Sep 2025Source
  • Documentmain layout_compressed (6).pdf · uploaded 18 Sep 2025Source
  • Documentplan 1_compressed.pdf · uploaded 18 Sep 2025Source
  • Documentplan 2_compressed.pdf · uploaded 18 Sep 2025Source
  • Documentplan 3_compressed.pdf · uploaded 18 Sep 2025Source

Technical (Architect)

  • DocumentArchitect Certificate - MAR 25 -SKYBOAT (1).pdf · uploaded 8 Apr 2025Source
  • DocumentAR - March 26 .pdf · uploaded 26 May 2026Source

Technical (Engineer)

  • DocumentEngineer Certificate Dec 24 - Skyboat Unit 1.pdf · uploaded 30 Jan 2025Source
  • Documentcasa Verde form 2.pdf · uploaded 8 Apr 2025Source
  • DocumentER - March 26 .pdf · uploaded 26 May 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsCTS No 807/2, Sr No 70B/1A

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
2BHK28 units in all
Address
CTS No 807/2, Sr No 70B/1A, Ghorpadi, GhorpadiPIN 411001
Village
Ghorpadi, Haveli taluka
Designated bank account
76
Developed in phases
No

Survey, CTS, gat or plot numbers

CTS No 807/2Sr No 70B/1A

Boundaries

North
By S no 70 1
South
By S no 70 1
East
By DP Road
West
By Canal

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking28 units

4 of 28 units booked (14%), as the promoter reported to MahaRERA

2BHK · 28 units
TypeCarpet areaUnitsBooked
2BHK72.64 sq m · 782 sq ft70
2BHK73.29 sq m · 789 sq ft71
2BHK77.64 sq m · 836 sq ft70
2BHK83.56 sq m · 899 sq ft73

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals7

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAr Atit Admulwar—
ArchitectHarshvardhan Kunjir—
Chartered accountantCA Yogesh Mali—
Chartered accountantRitesh Shah—
EngineerMr Kailas Sarode—
EngineerRohinee Badgujar—
EngineerRupesh Pawar—

Source: MahaRERA project page. Contact details are not shown.