RERA projects in Mugaon

2 projects under 3 MahaRERA registrations, registered 2017–2017. None has an extended completion date on record.

Locality
2RERA projects
3Registrationssome projects hold several
0Completion still due3 past their completion date
—Median extension beyond promised date0% of registrations extended
3Regulatory caseson 2 projects
0Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20173

Projects in Mugaon

2 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Hillshore 1,2,3,4,5,6,7,8,9,10,11 LCL - 0012Lavasa Corporation LtdP5210001382527 Oct 201730 Dec 2025—Promised date passed1
BelshoreLavasa Corporation LtdP52100013623, P5210001363716 Oct 201730 Dec 2025—Promised date passed2

Other localities in Mulshi

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Lavasa Corporation Ltd2 projects
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology