ProjectLocalityPromisedRevisedDelivery
Gagan Commerce CentreGagan I-Land Township Private limitedPune (M Corp.)Mar 2024Mar 20242 yrs 8 mo late
Gagan KlaraGagan Housing And Landmarks LLPBalewadiMar 2024Mar 20262 yrs 8 mo late
Hermes Paras 3Abhilasha DevelopersYerawadaMar 2024Mar 20242 yrs 8 mo late
Ivory TowersDSL Reality LLPHaveliMar 2024Mar 20242 yrs 8 mo late
Nirmiti 25 EastNirmiti Vastu Creation LLPKharadiMar 2024Mar 20262 yrs 8 mo late
Natures Blessings Phase IINagarkar DevelopersGorhe Bk.Mar 2024Mar 20242 yrs 8 mo late
Parkland - I C buildingYashvastu DevelopersGhorpadiMar 2024Mar 20242 yrs 8 mo late
Rajgad 5S R K RealtyPimpri Chinchawad (M Corp.)Mar 2024Mar 20242 yrs 8 mo late
Sai Kunj ResidencyS K Builders And DevelopersDighiMar 2024Mar 20242 yrs 8 mo late
Samarth NabhanganSamarth ConstructionWadagaon (Ct)Mar 2024Mar 20242 yrs 8 mo late
Shree GaneshaS K AssociatesPimpri Chinchawad (M Corp.)Mar 2024Mar 20242 yrs 8 mo late
Shreeram TradeconShreeram TradeconChakan (Ct)Mar 2024Oct 20252 yrs 8 mo late
Shreyas CrestShreyas SheltersBanerMar 2024Mar 20242 yrs 8 mo late
Vision SquareUnity LandmarksCharholiMar 2024Mar 20242 yrs 8 mo late
Va.Na.Oak Trust SankulSanjay Vasantlal GundechaPethMar 2024Mar 20242 yrs 8 mo late
7 Apte RoadLokmanya Multipurpose Co Operative Society LtdPune (M Corp.)Mar 2024Mar 20242 yrs 8 mo late
Aman HeightsInamdar PropertiesPune CityMar 2024Mar 20242 yrs 8 mo late
Ashoka Commercial HubAshoka DevelopersTathwadeMar 2024Mar 20252 yrs 8 mo late
Blue Dice Phase IIIShwetali Jitendra SonigaraChikhaliMar 2024Mar 20262 yrs 8 mo late
Dream VistaT T BladesLonavala (M Cl)Mar 2024Mar 20242 yrs 8 mo late
EkdantVaastu Vishwa DevelopersBaramatiMar 2024Mar 20242 yrs 8 mo late
Fortune HeightsAjaz Iqbal HavaldarKothrudMar 2024Dec 20252 yrs 8 mo late
Gaatha Nagar Phase 1Kalbhor Realtors And Services LLPChikhaliMar 2024Mar 20242 yrs 8 mo late
Gagan SouthcodeAkash DevelopersKondhwa BkMar 2024Mar 20242 yrs 8 mo late
Golden HeightsGolden Hills BuildconDhayariMar 2024Mar 20242 yrs 8 mo late
Ganesh ResidencyTrimurti Promotors And DevelopersPimpale GuravMar 2024Mar 20242 yrs 8 mo late
Happy Home ResidencyPhoenix AssociatesShirurMar 2024Mar 20242 yrs 8 mo late
Kale ResidencyPride ConstructionAalandiMar 2024Mar 20242 yrs 8 mo late
Moti MandirMoti MandirPune (M Corp.)Mar 2024Mar 20252 yrs 8 mo late
One AvanteAvante Spaces LimitedKothrudMar 2024Jun 20242 yrs 8 mo late
Padmalaya PearlPadmalaya PropertiesBanerMar 2024Sep 20252 yrs 8 mo late
R K HeightsNadeem Abdulrazak BagwanPune (M Corp.)Mar 2024Sep 20252 yrs 8 mo late
Royal VillaRoyal Properties BaramatiJalochiMar 2024Mar 20242 yrs 8 mo late
Sahyadri TowersMahesh Sambhaji PawarVaraleMar 2024Mar 20242 yrs 8 mo late
Sai AnandShree Ashtavinayak DevelopersCharholiMar 2024Mar 20242 yrs 8 mo late
Shree Ganesh ApartmentS.s. Construction And DevelopersDhankawadiMar 2024Mar 20242 yrs 8 mo late
Shubh Ganesh IconShubh Ganesh AssociatesVadgaonsheriMar 2024Mar 20242 yrs 8 mo late
Siddhi AnandVinayak DevelopersTalegaon Dabhade (M Cl)Mar 2024Mar 20242 yrs 8 mo late
SiddhivinayakShree Ashtavinayak DevelopersWadmukhwadiMar 2024Mar 20242 yrs 8 mo late
Stellar Homes - Phase IShyam Hanumant WakadkarHinjavadi (Ct)Mar 2024Mar 20252 yrs 8 mo late
Sun CrestJindal Mittal InfrastructureDhayari (Part)Mar 2024Sep 20252 yrs 8 mo late
The MelangeCosmos Skyline Homes Private LimitedBhosariMar 2024Aug 20252 yrs 8 mo late
United AthashriTen Corner Developers LLPLohgaonMar 2024Aug 20242 yrs 8 mo late
Vastushree ResidencySandeep Chandrakant KakadeTalegaon Dabhade (M Cl)Mar 2024Mar 20242 yrs 8 mo late
You57 Amenity BuildingSanas Developers Private LimitedManMar 2024Mar 20252 yrs 8 mo late
AnandsagarMoraya Construction & DevelopersDehuApr 2024Apr 20242 yrs 7 mo late
Kanhaiya Business CentreSanjay Vasantlal GundechaPune (M Corp.)Apr 2024Dec 20252 yrs 7 mo late
Mandai ComplexNew Manikraj DevelopersShirur GraminApr 2024Apr 20242 yrs 7 mo late
Tanish Dreams BTanish PropertiesWadmukhwadiApr 2024Mar 20252 yrs 7 mo late
Tanish Dreams ETanish PropertiesWadmukhwadiApr 2024Feb 20252 yrs 7 mo late

Delayed projects by district

SourcesMahaRERA registrations, extension certificates, project pages and document listsA project counts as completed when MahaRERA shows it so: its status, or a completion or occupancy certificate in its documents. Dates are MahaRERA's; Deedo does not know the day a project was handed over.Report a problemMethodology