RERA projects in Peth
48 projects under 48 MahaRERA registrations, registered 2017–2026. 23% have a completion date extended beyond the one promised.
Locality
48RERA projects
48Registrations
21Completion still due27 past their completion date
14 monthsMedian extension beyond promised date23% of registrations extended
1Regulatory caseson 1 project
4Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 8 |
| 2018 | 5 |
| 2019 | 4 |
| 2020 | 5 |
| 2021 | 4 |
| 2022 | 7 |
| 2023 | 7 |
| 2024 | 3 |
| 2025 | 4 |
| 2026 | 1 |
Projects in Peth
48 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Fab IconM/s Iconstruct Fab Landmarks LLP | PC1260002601257 | 20 Jul 2026 | 31 Dec 2030 | — | Not yet due | 0 |
| Tanish Moti ArcadeM/S Tanish Developers | PC1260002501207 | 13 Oct 2025 | 31 Dec 2028 | — | Not yet due | 0 |
| The PantheonUnitee Realtors LLP | PR1260002500496 | 6 Aug 2025 | 31 Mar 2027 | — | Not yet due | 0 |
| Chaandrai IconChaandrai Construction SS LLP | PM1260002500139 | 26 Jun 2025 | 30 Jun 2028 | — | Not yet due | 0 |
| PakharNestcon | P52100080564 | 16 Jun 2025 | 30 Apr 2028 | — | Not yet due | 0 |
| Square OneA Square Developer | P52100066518 | 11 Jun 2024 | 31 Dec 2028 | — | Not yet due | 0 |
| EshaanNaman Realty | P52100056154 | 16 May 2024 | 31 Dec 2026 | — | Not yet due | 0 |
| Parichay Co-Op Housing Society LtdBelvalkar Realtors LLP | P52100055315 | 14 Mar 2024 | 31 Mar 2027 | — | Not yet due | 0 |
| Jagannath HeritageAscent Landmarks | P52100052896 | 5 Oct 2023 | 31 Mar 2027 | — | Not yet due | 0 |
| B. T. SquareAjay Jayawant Bhosle | P52100052316 | 9 Aug 2023 | 31 Dec 2027 | — | Not yet due | 0 |
| Apex HeadquartersOneapex Realty | P52100051519 | 23 Jun 2023 | 30 Dec 2027 | — | Not yet due | 0 |
| ShikharVardhaman Landmarks | P52100051120 | 29 May 2023 | 31 Dec 2026 | — | Not yet due | 1 |
| Shankeshwar MarketOm Buildcon And Reality | P52100049978 | 6 Mar 2023 | 31 Jan 2028 | — | Not yet due | 0 |
| Shree ComplexAGR Realtors LLP | P52100049918 | 6 Mar 2023 | 31 Dec 2025 | — | Promised date passed | 0 |
| Dhanalaxmi SanskritiShubh Realty | P52100048793 | 17 Jan 2023 | 31 Dec 2026 | — | Not yet due | 0 |
| Gund PalaceVedant Construction | P52100047360 | 27 Oct 2022 | 31 Mar 2026 | — | Promised date passed | 0 |
| Sheetalkunj Sahakari Gruharachana Sansatha MaryaditIcon Properties | P52100034994 | 28 Apr 2022 | 31 Dec 2025 | — | Promised date passed | 0 |
| Kulkarni wadaJagdish Universal Superbiz Developers and Construction | P52100034429 | 5 Apr 2022 | 31 Dec 2024 | 31 Dec 2026 | Extended 24 mo | 0 |
| Kanakmangala - GajananKanakmangala Properties | P52100034371 | 4 Apr 2022 | 31 Mar 2024 | — | Promised date passed | 0 |
| BhardwajMotive Associates | P52100034098 | 24 Mar 2022 | 31 Mar 2026 | — | Promised date passed | 0 |
| 100 PrabhatRavetkar Crystal Developers LLP | P52100033089 | 3 Feb 2022 | 23 Nov 2026 | — | Not yet due | 0 |
| DharmeshPandit Javdekar Associates | P52100033046 | 3 Feb 2022 | 28 Nov 2026 | — | Not yet due | 0 |
| Quba ResidencyQuba Group | P52100032265 | 22 Dec 2021 | 31 Dec 2028 | — | Not yet due | 0 |
| NidishKalashree Properties | P52100032146 | 14 Dec 2021 | 25 Sep 2024 | 25 Sep 2025 | Extended 12 mo | 0 |
| Dhanlaxmi MarketDhanlaxmi Infra | P52100029973 | 18 Jul 2021 | 31 Dec 2024 | 30 Dec 2026 | Extended 24 mo | 0 |
Other localities in Haveli
Most active promoters
By projects registered here, as named on MahaRERA.
- Buttepatil Properties4 projects
- Eiffel Landmarks Private Limited2 projects
- AGR Realtors LLP1 project
- Ajay Jayawant Bhosle1 project
- Ascent Landmarks1 project
- Asha Arun Sane1 project
- A Square Developer1 project
- Avadhoot Constructions1 project
- Belvalkar Realtors LLP1 project
- B K Pate Enterprises1 project
Data through11 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology