Kale Residency
Deedo IDDP-PUN-7392Its promised completion date, Mar 2024, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 0% of its units are booked.
Aalandi, Pune 412105 · by Pride Construction
Buying a flat here?
See every deed registered on it.
Its promised completion date, Mar 2024, has passed and MahaRERA does not show it completed
- This projectRegistered 23 Apr 2021, completion promised 31 Mar 2024, and still not shown completed today.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100029014
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100029014 | 23 Apr 2021 | 31 Mar 2024 | 31 Mar 2024 | Pride Construction | Project page |
Documents34
1 document held by Deedo, 33 filings listed on MahaRERA's project page
Finance
- PAN CardPAN CARD.pdf · uploaded 8 Apr 2021Source
Legal
- Legal Title reportSEARCHREPORTRERA.pdf · uploaded 8 Apr 2021Source
- Legal Title reportSEARCH REPORT_compressed.pdf · uploaded 8 Apr 2021Source
- Declaration Form BANNEX B ALL.pdf · uploaded 8 Apr 2021Source
- Declaration Form BANNEX B LANDOWNER.pdf · uploaded 12 Apr 2021Source
- Otherapproval_compressed.pdf · uploaded 26 Oct 2021Source
Migrated
- 1 PAN CardPAN CARD.pdf · uploaded 8 Apr 2021Source
Show all 34 documentsShow fewer documents
Migrated
- 1 Copy of the legal title reportSEARCHREPORTRERA.pdf · uploaded 8 Apr 2021Source
- 2 Copy of the legal title reportSEARCH REPORT_compressed.pdf · uploaded 8 Apr 2021Source
- 1 Details of encumbrancesDECLRATION.pdf · uploaded 8 Apr 2021Source
- 1 Copy of Layout Approval (in case of layout)layout.pdf · uploaded 8 Apr 2021Source
- 1 Building Plan Approval / NA Order for plotted developmentbuilding.pdf · uploaded 8 Apr 2021Source
- 1 Commencement Certificates / NA Order for plotted developmentCOMMENCEMENT.pdf · uploaded 8 Apr 2021Source
- 1 Declaration in FORM BANNEX B ALL.pdf · uploaded 8 Apr 2021Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)1.pdf · uploaded 8 Apr 2021Source
- 1 Proforma of Allotment letterAGREEMENT Format.pdf · uploaded 8 Apr 2021Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM2.pdf · uploaded 9 Apr 2021Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FINAL FORM 3_compressed.pdf · uploaded 9 Apr 2021Source
- 2 Declaration in FORM BANNEX B LANDOWNER.pdf · uploaded 12 Apr 2021Source
- 2 Copy of Layout Approval (in case of layout)revisedplan_compressed.pdf · uploaded 26 Oct 2021Source
- 2 Building Plan Approval / NA Order for plotted developmentrevisedpplan_compressed.pdf · uploaded 26 Oct 2021Source
- 3 Building Plan Approval / NA Order for plotted developmentrevisedplan_compressed.pdf · uploaded 26 Oct 2021Source
- 2 Commencement Certificates / NA Order for plotted developmentcommencement_compressed.pdf · uploaded 26 Oct 2021Source
- 1 Otherapproval_compressed.pdf · uploaded 26 Oct 2021Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Pride firm-form 5.pdf · uploaded 24 Jan 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)FORM 5 2223 pride.pdf · uploaded 2 Nov 2023Source
Technical
Technical (Architect)
- Document1.pdf · uploaded 8 Apr 2021Source
Technical (Engineer)
- DocumentFORM2.pdf · uploaded 9 Apr 2021Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel S NO 141/1/1/1 CHOVISAWADI ALANDI DEVACHI PUNE
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK36 units in all
- Address
- S No 141 1 1 1 Chovisawadi Alandi Devachi Pune 412105, Chovisawadi, Chovisawadi Alandi DevachiPIN 412105
- Village
- Aalandi
- Land area for this project
- 1,501 sq m (16,162 sq ft)
- Permissible built-up area
- 2,118 sq m (22,797 sq ft)
- Sanctioned built-up area
- 1,324 sq m (14,248 sq ft)
- Designated bank account
- 212
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
S NO 141 1 1 1 CHOVISAWADI ALANDI DEVACHI PUNE 412105
Boundaries
- North
- Vishwashwar Nagar Society
- South
- Property Of Dnyansheshwar Kale
- East
- Property Ofmr Nanvate
- West
- Property Of Mr Sopan Kale
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking36 units
0 of 36 units booked (0%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 41.16 sq m · 443 sq ft | 12 | 0 |
| 1BHK | 41.16 sq m · 443 sq ft | 12 | 0 |
| 1BHK | 42.46 sq m · 457 sq ft | 6 | 0 |
| 1BHK | 42.46 sq m · 457 sq ft | 6 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Techno Arrch | — |
| Chartered accountant | prakash suneja | — |
| Engineer | Bhushan Rathod | — |
Source: MahaRERA project page. Contact details are not shown.