Delayed projects in Maharashtra
8,413 MahaRERA projects in 36 districts are past their promised completion date, and MahaRERA shows no completion for them.
Most overdue first
Late: the latest completion date MahaRERA records (promised, or revised by an extension) has passed. Months late count from the first promised date. Page 37 of 169.
| Project | Locality | Promised | Revised | Delivery |
|---|---|---|---|---|
| Siddhivinayak SankulShivsai Developers | Malkapur (Np)Satara | Jan 2022 | Jan 2022 | 4 yrs 10 mo late |
| Seawoods HeightScarlet Builders & Developer | NerulThane | Jan 2022 | Jan 2026 | 4 yrs 10 mo late |
| Simran LuxuriaJay Sunil Daryanani | Ulhasnagar (M Corp.)Thane | Jan 2022 | Jan 2022 | 4 yrs 10 mo late |
| Ujwal ArcadUjwal Associates | Nagpur (M Corp.)Nagpur | Jan 2022 | Jan 2022 | 4 yrs 10 mo late |
| Adora Enclave Residency / CommercialHemant Vinaykant Parikh | KurlaMumbai Suburban | Jan 2022 | Jan 2022 | 4 yrs 10 mo late |
| Mahira ConstructionMahira Construction | ChunchaleNashik | Jan 2022 | Jan 2022 | 4 yrs 10 mo late |
| Sai CornerMauli Developers | Vadghar (Ct)Raigarh | Jan 2022 | Jan 2022 | 4 yrs 10 mo late |
| Samarth AvenueAtul Tukaram Wagh | AdgaonNashik | Jan 2022 | Jan 2022 | 4 yrs 10 mo late |
| arnavvhillaBabaso Nivritti Choudhar | RuiPune | Jan 2022 | Jan 2022 | 4 yrs 10 mo late |
| Shri Vallabh ResidencySwadhinta Builders LLP | BorivaliMumbai Suburban | Jan 2022 | Jan 2022 | 4 yrs 10 mo late |
| AmrutyogPrerna Group Baramati | MorgaonPune | Jan 2022 | Dec 2022 | 4 yrs 10 mo late |
| Casa FelizAujaswi Associates | MahalungePune | Jan 2022 | Dec 2025 | 4 yrs 10 mo late |
| Galaxy RoyalDinesh Pyarelal Tiwari | Palghar | Jan 2022 | Jan 2022 | 4 yrs 10 mo late |
| HrishaYadav Bro''s Constructions | Ambarnath (R)Thane | Jan 2022 | Jan 2022 | 4 yrs 10 mo late |
| Kuber VillaMahadev Kanha Mohite | UlaweRaigarh | Jan 2022 | Jan 2022 | 4 yrs 10 mo late |
| Laxmi Narayan MansionAtharva Developers | BorivaliMumbai Suburban | Jan 2022 | Jan 2022 | 4 yrs 10 mo late |
| Lucky ResidencyAshtavinayak Developers | PomanPalghar | Jan 2022 | Jan 2024 | 4 yrs 10 mo late |
| Om Sai Sankul COm Sai United | MandaThane | Jan 2022 | Jan 2023 | 4 yrs 10 mo late |
| Sai Samarth ResidencySamarth Builders & Developers | Godoli (Ct)Satara | Jan 2022 | Jan 2022 | 4 yrs 10 mo late |
| Swan ParadiseYogita Sanjay Gosavi | JalgaonRatnagiri | Jan 2022 | Jan 2022 | 4 yrs 10 mo late |
| Vaibhav ApartmentShree Vinayak Enterprises And Dalvi Premises Private Limited Jv | Talegaon Dabhade (M Cl)Pune | Jan 2022 | Jan 2022 | 4 yrs 10 mo late |
| Arzoo NagarArzoo Swabhiman Nagarik Sahkari Gruhrachana Sanstha Maryadit | DabewadiSatara | Jan 2022 | Jan 2022 | 4 yrs 10 mo late |
| Shree Mahadev ApartmentOm Ganesha Builders & Developers | Palghar | Jan 2022 | Jun 2022 | 4 yrs 10 mo late |
| Viraj SequoiaSequoia Realty LLP | AundhPune | Jan 2022 | Dec 2023 | 4 yrs 10 mo late |
| Radha HomeShree Mauli Krupa Developers | KaranjadeRaigarh | Feb 2022 | Feb 2022 | 4 yrs 9 mo late |
| Unicon Avasa Part 1Sachin Ishwarchand Goyal | ShiraswadiPune | Feb 2022 | Feb 2022 | 4 yrs 9 mo late |
| Unicon Nivasa Part 1Mahalaxmi Spaces | PeranePune | Feb 2022 | Feb 2022 | 4 yrs 9 mo late |
| Patil Parbat PlazaVijaysinh Krishnarao Parbat | PalusSangli | Feb 2022 | Aug 2024 | 4 yrs 9 mo late |
| Lakshmi Narayan SankulINDRA Construction | KhedRatnagiri | Feb 2022 | Feb 2022 | 4 yrs 9 mo late |
| Lilium ClassicSketch Art Builders And Developers LLP | RahataniPune | Feb 2022 | Feb 2022 | 4 yrs 9 mo late |
| Akshad Super City Phase 1Vansh Infrastructure | Gangapur JahagirAurangabad | Feb 2022 | — | 4 yrs 9 mo late |
| Sai Vitthal ResidencySai Builders And Developers | SinnarNashik | Feb 2022 | Feb 2022 | 4 yrs 9 mo late |
| JubilationAakankssha Properties | YawalewadiPune | Feb 2022 | Feb 2022 | 4 yrs 9 mo late |
| Grace Residency BNimhan Developers | SusPune | Feb 2022 | Aug 2022 | 4 yrs 9 mo late |
| Globe ApartmentV. Kumar Infratech | UranRaigarh | Feb 2022 | Feb 2022 | 4 yrs 9 mo late |
| Hari Om ShivamAyush Dashrath Koli | WahalRaigarh | Feb 2022 | Dec 2023 | 4 yrs 9 mo late |
| Shree PrastShree Prast | PaliThane | Feb 2022 | Feb 2023 | 4 yrs 9 mo late |
| Surya ResidencyConcept Builder And Developers | Walwadi (Ct)Dhule | Feb 2022 | — | 4 yrs 9 mo late |
| Swapnalok- Building BGandhi Bafna Construction Private Limited | BopodiPune | Feb 2022 | Mar 2023 | 4 yrs 9 mo late |
| Shivalik AuraMukesh Shrinath Sharma | PushapakRaigarh | Feb 2022 | Dec 2023 | 4 yrs 9 mo late |
| Shree Bhavani HeightShree Bhavani Developers | Pune (M Corp.)Pune | Feb 2022 | Feb 2022 | 4 yrs 9 mo late |
| AnandAjit Anant Barve | Ward GnorthMumbai City | Mar 2022 | Mar 2022 | 4 yrs 8 mo late |
| Prachiti ResidencyDeepak Developers | Wadgaon BkPune | Mar 2022 | Mar 2022 | 4 yrs 8 mo late |
| Sai Datta ResidencySai Datta Enterprises | Pune (Cb)Pune | Mar 2022 | Sep 2023 | 4 yrs 8 mo late |
| Unitech HeightsNew Unitech Constructions | Aurangabad (M Corp.)Aurangabad | Mar 2022 | — | 4 yrs 8 mo late |
| Niwas AppartmentNiwas Developers | Shramik NagarNashik | Mar 2022 | Mar 2022 | 4 yrs 8 mo late |
| Gandhakosh ApartmentsMaheshkumar Pralhad Khilare | Vita (M Cl)Sangli | Mar 2022 | Mar 2022 | 4 yrs 8 mo late |
| Vandan HeightsGovinda Ghanshyam Nagori | Jalgaon | Mar 2022 | — | 4 yrs 8 mo late |
| Sky HeavenGunavant Supadu Patil | KalambRaigarh | Mar 2022 | Mar 2022 | 4 yrs 8 mo late |
| Shree Ambe Varad VinayakShree Ambe Homes | Vadghar (Ct)Raigarh | Mar 2022 | Mar 2022 | 4 yrs 8 mo late |
Delayed projects by district
Pune · 2,214Thane · 1,157Raigarh · 1,041Mumbai Suburban · 994Nashik · 481Palghar · 362Nagpur · 323Aurangabad · 243Mumbai City · 242Satara · 228Ratnagiri · 192Sangli · 176Solapur · 155Kolhapur · 131Amravati · 72Sindhudurg · 72Ahmednagar · 69Chandrapur · 39Jalgaon · 39Latur · 27Akola · 23Beed · 21Nanded · 18Dhule · 17Wardha · 16Buldana · 14Jalna · 12Parbhani · 9Bhandara · 8Yavatmal · 6
SourcesMahaRERA registrations, extension certificates, project pages and document listsA project counts as completed when MahaRERA shows it so: its status, or a completion or occupancy certificate in its documents. Dates are MahaRERA's; Deedo does not know the day a project was handed over.Report a problemMethodology