Perane, Pune

Deedo IDDL-PUN-PERANE

9 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects8
Registrations8
Completion still due35 past their date
Median extension11 months25% of registrations extended
Regulatory cases0none on MahaRERA's lists

9 in 10 registrations run late here

8 MahaRERA registrations in Perane

1 not yet due2 extended, not yet due5 past even the latest date

Extended registrations moved their completion date by a median of 11 months.

Projects in Perane

8 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Tulsi VillaPrnav Rohidas Choudhari1 yr 5 mo late——
Tulsi VillaMr Rajendra Narayan Kand (Yashoda Properties E)Completed——
Sparkle ResidenceKale DeveloperDue Apr 2028, extended 4 mo—7%
Pristine Purvrang Part 2Padmavati Homes2 yrs 11 mo late——
Unicon AksharMahalaxmi CreationsCompleted, extended 1 yr 6 mo—49%
All 8 projects →
Perane market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Mahalaxmi Spaces2 projects
  2. Padmavati Homes2 projects
  3. Kale Developer1 project
  4. Mahalaxmi Creations1 project
  5. Mr Rajendra Narayan Kand (Yashoda Properties E)1 project
  6. Padmavati Homes1 project
  7. Prnav Rohidas Choudhari1 project

Perane, in questions

How many projects in Perane run late?

9 in 10 MahaRERA registrations (7 of 8): their completion date was extended or has passed, data through 21 Oct 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Perane by Deedo. Medians on fewer than 3 deeds are not shown.

Latest deal · Resale · Jun 2026

Under ₹25 L

Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology