Deedo IDDP-RAI-GZPDCompletion was pushed back 1 year and 10 months to Dec 2023, and that date has passed too; no MahaRERA orders on record; 80% of its units are booked.
Pushapak, Raigarh 410206 · by Mukesh Shrinath Sharma
Buying a flat here?
See every deed registered on it.
Completion was pushed back 1 year and 10 months to Dec 2023, and that date has passed too
- This projectRegistered 29 Aug 2020, completion promised 28 Feb 2022, revised to 31 Dec 2023, and still not shown completed today.
1 extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
2 buildings
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52000026197
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52000026197 | 29 Aug 2020 | 28 Feb 2022 | 31 Dec 2023 | Mukesh Shrinath Sharma | Project page |
Documents31
3 documents held by Deedo, 28 filings listed on MahaRERA's project page
Other
- OtherDate not statedView
Finance
- PAN CardPan Card Mukesh.pdf · uploaded 24 Aug 2020Source
Legal
Migrated
- 1 PAN CardPan Card Mukesh.pdf · uploaded 24 Aug 2020Source
Show all 31 documentsShow fewer documents
Migrated
- 1 Copy of the legal title reportTitle -295_compressed.pdf · uploaded 24 Aug 2020Source
- 1 Details of encumbrancesEncumberence - Shivalik Aura.pdf · uploaded 24 Aug 2020Source
- 1 Copy of Layout Approval (in case of layout)Cidco Plan.pdf · uploaded 24 Aug 2020Source
- 1 Building Plan Approval / NA Order for plotted developmentCidco Plan.pdf · uploaded 24 Aug 2020Source
- 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 24 Aug 2020Source
- 1 Declaration in FORM BForm B - Shivalik Aura.pdf · uploaded 24 Aug 2020Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Shivalik Aura.pdf · uploaded 24 Aug 2020Source
- 1 Proforma of Allotment letterAgreement for Sale.pdf · uploaded 24 Aug 2020Source
- 2 Proforma of Allotment letterAllotment Letter.pdf · uploaded 24 Aug 2020Source
- 2 Declaration in FORM BFORM B_compressed.pdf · uploaded 3 Jul 2023Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 3 Jul 2023Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 3 Jul 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)FORM 2A_compressed.pdf · uploaded 3 Jul 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)FORM 2A_compressed.pdf · uploaded 3 Jul 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)FORM 2A_compressed.pdf · uploaded 3 Jul 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)FORM 2A_compressed.pdf · uploaded 3 Jul 2023Source
- 1 Disclosure of sold/ booked inventorySOLD UNSOLD.pdf · uploaded 3 Jul 2023View
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)FORM 5 FY 2021-22.pdf · uploaded 3 Jul 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)FORM 5 FY 2022-23.pdf · uploaded 3 Jul 2023Source
Technical
Technical (Architect)
- DocumentFORM 1.pdf · uploaded 3 Jul 2023Source
Technical (Engineer)
- DocumentFORM 2.pdf · uploaded 3 Jul 2023Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel Plot No. 295
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 1RK, Shop10 units in all
- Address
- Plot No. 295, Sector - R3, Pushpak (New)PIN 410206
- Village
- Vadghar (CT), Panvel taluka
- Land area for this project
- 360 sq m (3,873 sq ft)
- Permissible built-up area
- 539 sq m (5,804 sq ft)
- Sanctioned built-up area
- 539 sq m (5,804 sq ft)
- Designated bank account
- 109
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
Plot No. 295
Boundaries
- North
- Plot No 284 and Plot No 285
- South
- 9 M wide Road
- East
- Plot No 296
- West
- Plot No 294
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking10 units
8 of 10 units booked (80%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 25.54 sq m · 275 sq ft | 2 | 2 |
| 1BHK | 26 sq m · 280 sq ft | 2 | 2 |
| 1RK | 15.52 sq m · 167 sq ft | 1 | 1 |
| 1RK | 16.07 sq m · 173 sq ft | 1 | 1 |
| 1RK | 16.7 sq m · 180 sq ft | 1 | 1 |
| 1RK | 19.08 sq m · 205 sq ft | 1 | 1 |
| Shop | 9.22 sq m · 99 sq ft | 1 | 0 |
| Shop | 12 sq m · 129 sq ft | 1 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals4
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Atul Patel Architects | — |
| Chartered accountant | STP & Associates | — |
| Engineer | B S Sukhtankar | — |
| Other | Baleshwar Mahato | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Pushapak
- Aaiji Lks HeightsRERA PM1270002602692
- Datta VillaRERA PM1270002602510
- Infinity SpireRERA PR1270002602327
- Mukta ResidencyRERA PM1270002602110
- Pandurang HeightsRERA PM1270002602051
- Shreepati Kalash 1RERA PM1270002601951
- Surya Nath NiwasRERA PR1270002601611
- Shreesha HeightsRERA PM1270002601543
All 84 projects in Pushapak · Compare Shivalik Aura with another project