Grace Residency B
Completion was pushed back 6 months to Aug 2022, and that date has passed too; no MahaRERA orders on record; 89% of its units are booked.
Sus, Pune 411021 · Promoter: Nimhan Developers
Completion was pushed back 6 months to Aug 2022, and that date has passed too
- This projectRegistered 11 Sep 2018, completion promised 28 Feb 2022, revised to 28 Aug 2022, and still not shown completed today.
1 extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100017741
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100017741 | 11 Sep 2018 | 28 Feb 2022 | 28 Aug 2022 | Nimhan Developers | Project page |
Documents46
2 documents held by Deedo, 44 filings listed on MahaRERA's project page
Finance
- PAN CardNimhan_Developers_PAN.PDF · uploaded 23 Aug 2018Source
Legal
Show all 46 documentsShow fewer documents
Migrated
- 1 Certificates of CA (Form 3)Grace 2 - CA Certificate.pdf · uploaded 23 Aug 2018Source
- 1 Details of encumbrancesDeclaration of Encumbrances - Grace B.pdf · uploaded 24 Aug 2018Source
- 1 Copy of Layout Approval (in case of layout)Sanction Plan (2-3).pdf · uploaded 24 Aug 2018Source
- 2 Copy of Layout Approval (in case of layout)Sanction Plan (1-3).pdf · uploaded 24 Aug 2018Source
- 3 Copy of Layout Approval (in case of layout)Sanction Plan (3-3).pdf · uploaded 24 Aug 2018Source
- 1 Building Plan Approval (IOD)Sanction Plan (1-3) B P Layout.pdf · uploaded 31 Aug 2018Source
- 2 Building Plan Approval (IOD)Sanction Plan (2-3).pdf · uploaded 31 Aug 2018Source
- 3 Building Plan Approval (IOD)Sanction Plan (3-3).pdf · uploaded 31 Aug 2018Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Grace 2 - Engineer Certificate.pdf · uploaded 31 Aug 2018Source
- 1 Proforma of Allotment letterAgreement Draft.pdf · uploaded 31 Aug 2018Source
- 1 Copy of the legal title reportSearch and Title Report - Grace B.pdf · uploaded 1 Sep 2018Source
- 1 Declaration in FORM BForm B - Grace B.pdf · uploaded 1 Sep 2018Source
- 1 OtherRERA Declaration - Nimhan Developers-compressed.pdf · uploaded 18 May 2022Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Architect Certificate - Apr 2019.pdf · uploaded 15 Apr 2023Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Architect Certificate - Mar 2020.pdf · uploaded 15 Apr 2023Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Architect Certificate - Mar 2021.pdf · uploaded 15 Apr 2023Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Architect Certificate - Oct 21.pdf · uploaded 15 Apr 2023Source
- 1 Disclosure of sold/ booked inventoryOccupancy Certificate - Grace Residency B.pdf · uploaded 15 Apr 2023Source
- 1 Status of Formation of Legal Entity (Society/Co Op etc.)Grace B - Society Registration Certificate.pdf · uploaded 15 Feb 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)New Form 2A - Engineers Certificate - Mar 2022.pdf · uploaded 7 Oct 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)New Form 2A - Engineers Certificate - Mar 2021.pdf · uploaded 7 Oct 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)New Form 2A - Engineers Certificate - Mar 2022.pdf · uploaded 7 Oct 2024Source
- 2 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)New Form 2A - Engineers Certificate - Mar 2022.pdf · uploaded 7 Oct 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)New Form 2A - Engineers Certificate - Mar 2021.pdf · uploaded 7 Oct 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)New Form 2A - Engineers Certificate - Mar 2022.pdf · uploaded 7 Oct 2024Source
- 1 Certificates of CA (Form 3)Revised Grace B - Form 3 - CA Certificate.pdf · uploaded 12 Dec 2024Source
- 2 Certificates of CA (Form 3)CA Certifcate - Form 3 - 2018-19_compressed.pdf · uploaded 21 Dec 2024Source
- 3 Certificates of CA (Form 3)CA Certificate - Form 3 - 2019-20_compressed.pdf · uploaded 21 Dec 2024Source
- 4 Certificates of CA (Form 3)CA Certificate - Form 3 - 2020-21_compressed.pdf · uploaded 21 Dec 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)New Form 2A - Engineers Certificate - Mar 2019.pdf · uploaded 6 Jan 2025Source
Technical
- DocumentSanction Plan (2-3).pdf · uploaded 24 Aug 2018Source
- DocumentSanction Plan (1-3).pdf · uploaded 24 Aug 2018Source
- DocumentSanction Plan (3-3).pdf · uploaded 24 Aug 2018Source
- DocumentSanction Plan (1-3) B P Layout.pdf · uploaded 31 Aug 2018Source
- DocumentSanction Plan (2-3).pdf · uploaded 31 Aug 2018Source
- DocumentSanction Plan (3-3).pdf · uploaded 31 Aug 2018Source
Technical (Architect)
- DocumentForm 1 - Architect Certificate - Oct 21.pdf · uploaded 15 Apr 2023Source
Technical (Engineer)
- DocumentGrace 2 - Engineer Certificate.pdf · uploaded 31 Aug 2018Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvals39, S NO 133/134 PLOT NO 30
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- Residential19 units in all
- Address
- S No 133/134 Plot No 30 And 39, Sus Road, Sairang Society SusPIN 411021
- Village
- Sus, Mulshi taluka
- Designated bank account
- 85
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Boundaries
- North
- Plot No 31 And 38
- South
- Plot No 29 And 40
- East
- 9 Mtr Road
- West
- 12 Mtr Road
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking19 units
17 of 19 units booked (89%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| Residential | 829.09 sq m · 8,924 sq ft | 19 | 17 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals1
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Pramod Chavan | — |
Source: MahaRERA project page. Contact details are not shown.