Uran, Raigarh

Deedo IDDL-RAI-URAN-2

9 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects60
Registrations60
Completion still due1644 past their date
Median extension12 months47% of registrations extended
Regulatory cases0none on MahaRERA's lists

9 in 10 registrations run late here

60 MahaRERA registrations in Uran

5 not yet due11 extended, not yet due44 past even the latest date

Extended registrations moved their completion date by a median of 12 months.

Projects in Uran

60 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Surana VistaS D BuildconDue Apr 2033, extended 4 mo——
Shiv EnclaveCielo HeightsDue Apr 2030, extended 4 mo——
Shalom EnclaveShali JacobDue Sep 2030, extended 4 mo——
Balaji PlanetPlanetnova Developments LLPDue Apr 2030, extended 4 mo——
Siddhivinayak ApartmentsBaldev Diwan SinghDue Mar 2027, extended 4 mo——
All 60 projects →
Uran market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Cielo Heights2 projects
  2. Devkrupa Enterprises2 projects
  3. Jacob George2 projects
  4. Murudeshwar Developers2 projects
  5. A A Thaiup Ali Abdul Madina1 project
  6. Aaum Constructions1 project
  7. Abm Omcon Land Developers1 project
  8. Apex Realty1 project
  9. Baldev Diwan Singh1 project
  10. Furqan Shafi Navrange1 project

Uran, in questions

How many projects in Uran run late?

9 in 10 MahaRERA registrations (55 of 60): their completion date was extended or has passed, data through 22 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Uran by Deedo. Medians on fewer than 3 deeds are not shown.

Data through22 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology