RERA projects in Mhatvali
2 projects under 2 MahaRERA registrations, registered 2018–2022. None has an extended completion date on record.
Locality
2RERA projects
2Registrations
1Completion still due1 past their completion date
—Median extension beyond promised date0% of registrations extended
0Regulatory casesnone on MahaRERA's lists
5Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2018 | 1 |
| 2019 | 0 |
| 2020 | 0 |
| 2021 | 0 |
| 2022 | 1 |
Projects in Mhatvali
2 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Mahaavir Labdhi Phase 1Mahaavir Buildcon LLP | P52000045246 | 10 May 2022 | 31 Dec 2030 | 31 Dec 2030 | Not yet due | 0 |
| Ram VillaShree Rudra Enterprises | P52000014853 | 8 Jan 2018 | 30 Dec 2021 | 30 Dec 2021 | Promised date passed | 0 |
Other localities in Uran
Most active promoters
By projects registered here, as named on MahaRERA.
- Mahaavir Buildcon LLP1 project
- Shree Rudra Enterprises1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology