Skip to content
Deedo home
Menu

Dongari, Raigarh

5 in 10 MahaRERA registrations here have pushed their completion date back.

RERA projects18
Registrations19some projects hold several
Completion still due613 past their date
Median extension12 months47% of registrations extended
Regulatory cases0none on MahaRERA's lists

Projects in Dongari

18 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Sai SwamiAai InfrastructuresP5200007983927 Mar 202511 Oct 202711 Feb 2028Extended 4 mo0
Prathmesh ParkIchhapurti DevelopersP5200007799419 Nov 202431 Dec 202730 Apr 2028Extended 4 mo0
Shiv EmpireB N DevelopersP5200005460731 Jan 202431 Dec 202731 Dec 2027Not yet due0
Pramukh DharmaPramukh AssociatesP5200005200313 Jul 202330 Sep 202630 Jan 2027Extended 4 mo0
Jupiter BlissArjun Ashok TarachandaniP520000508599 May 202315 Sep 202615 Jan 2027Extended 4 mo0
Malik SolitaireAfzal Husain MalikP5200005065321 Apr 202331 Dec 202531 Dec 2025Promised date passed0
KingstonSushant Sudhakar PolP5200004531812 May 202231 Aug 202231 Dec 2025Extended 40 mo0
Dhanashree ApartmentShree Ekvira Developers LLPP520000265412 Oct 202030 Apr 202830 Apr 2028Not yet due0
Shreepad DevelopersMangesh Ramling TatodeP520000256521 Jul 202011 Jan 202511 Jan 2025Promised date passed0
Vishwa NathVishwa Developers And InfrastructuresP520000243215 Feb 202030 Dec 202230 Dec 2022Promised date passed0
Aarsh AppartmentAnaahat EnterpriseP5200002125214 Jun 20191 Jun 20241 Jun 2024Promised date passed0
Sai SanjeevaniSuresh Basawanappa FatateP5200002112810 Jun 201930 Jun 202331 Mar 2025Extended 21 mo0
Anil ResidencyR Y ConstructionP5200002099027 May 201930 Dec 202230 Dec 2022Promised date passed0
GalaxyRnd Builders & DevelopersP520000191084 Jan 201930 Jun 202330 Jun 2023Promised date passed0
ElementsMap Earthscapes LLPP5200001645311 May 201830 Jun 202131 Dec 2024Extended 42 mo0
Eden GardenM C BabuP52000005932, P5200000871414 Aug 201731 Dec 201930 Dec 2020Extended 12 mo0
PlatinumRnd Builders & DevelopersP520000045909 Aug 201730 Dec 202020 Jan 2022Extended 13 mo0
SkylineRnd Builders & DevelopersP520000037746 Aug 201730 Dec 202330 Dec 2023Promised date passed0

Most active promoters

  1. Rnd Builders & Developers3 projects
  2. Aai Infrastructures1 project
  3. Afzal Husain Malik1 project
  4. Anaahat Enterprise1 project
  5. Arjun Ashok Tarachandani1 project
  6. B N Developers1 project
  7. Ichhapurti Developers1 project
  8. Mangesh Ramling Tatode1 project
  9. Map Earthscapes LLP1 project
  10. M C Babu1 project
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology