Dongari, Raigarh
5 in 10 MahaRERA registrations here have pushed their completion date back.
RERA projects18
Registrations19some projects hold several
Completion still due613 past their date
Median extension12 months47% of registrations extended
Regulatory cases0none on MahaRERA's lists
Projects in Dongari
18 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Sai SwamiAai Infrastructures | P52000079839 | 27 Mar 2025 | 11 Oct 2027 | 11 Feb 2028 | Extended 4 mo | 0 |
| Prathmesh ParkIchhapurti Developers | P52000077994 | 19 Nov 2024 | 31 Dec 2027 | 30 Apr 2028 | Extended 4 mo | 0 |
| Shiv EmpireB N Developers | P52000054607 | 31 Jan 2024 | 31 Dec 2027 | 31 Dec 2027 | Not yet due | 0 |
| Pramukh DharmaPramukh Associates | P52000052003 | 13 Jul 2023 | 30 Sep 2026 | 30 Jan 2027 | Extended 4 mo | 0 |
| Jupiter BlissArjun Ashok Tarachandani | P52000050859 | 9 May 2023 | 15 Sep 2026 | 15 Jan 2027 | Extended 4 mo | 0 |
| Malik SolitaireAfzal Husain Malik | P52000050653 | 21 Apr 2023 | 31 Dec 2025 | 31 Dec 2025 | Promised date passed | 0 |
| KingstonSushant Sudhakar Pol | P52000045318 | 12 May 2022 | 31 Aug 2022 | 31 Dec 2025 | Extended 40 mo | 0 |
| Dhanashree ApartmentShree Ekvira Developers LLP | P52000026541 | 2 Oct 2020 | 30 Apr 2028 | 30 Apr 2028 | Not yet due | 0 |
| Shreepad DevelopersMangesh Ramling Tatode | P52000025652 | 1 Jul 2020 | 11 Jan 2025 | 11 Jan 2025 | Promised date passed | 0 |
| Vishwa NathVishwa Developers And Infrastructures | P52000024321 | 5 Feb 2020 | 30 Dec 2022 | 30 Dec 2022 | Promised date passed | 0 |
| Aarsh AppartmentAnaahat Enterprise | P52000021252 | 14 Jun 2019 | 1 Jun 2024 | 1 Jun 2024 | Promised date passed | 0 |
| Sai SanjeevaniSuresh Basawanappa Fatate | P52000021128 | 10 Jun 2019 | 30 Jun 2023 | 31 Mar 2025 | Extended 21 mo | 0 |
| Anil ResidencyR Y Construction | P52000020990 | 27 May 2019 | 30 Dec 2022 | 30 Dec 2022 | Promised date passed | 0 |
| GalaxyRnd Builders & Developers | P52000019108 | 4 Jan 2019 | 30 Jun 2023 | 30 Jun 2023 | Promised date passed | 0 |
| ElementsMap Earthscapes LLP | P52000016453 | 11 May 2018 | 30 Jun 2021 | 31 Dec 2024 | Extended 42 mo | 0 |
| Eden GardenM C Babu | P52000005932, P52000008714 | 14 Aug 2017 | 31 Dec 2019 | 30 Dec 2020 | Extended 12 mo | 0 |
| PlatinumRnd Builders & Developers | P52000004590 | 9 Aug 2017 | 30 Dec 2020 | 20 Jan 2022 | Extended 13 mo | 0 |
| SkylineRnd Builders & Developers | P52000003774 | 6 Aug 2017 | 30 Dec 2023 | 30 Dec 2023 | Promised date passed | 0 |
Nearby: other localities in Uran
Most active promoters
- Rnd Builders & Developers3 projects
- Aai Infrastructures1 project
- Afzal Husain Malik1 project
- Anaahat Enterprise1 project
- Arjun Ashok Tarachandani1 project
- B N Developers1 project
- Ichhapurti Developers1 project
- Mangesh Ramling Tatode1 project
- Map Earthscapes LLP1 project
- M C Babu1 project
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology