Skip to content
Deedo home
Menu

Eden Garden

Completion date passed

Dongari, Raigarh 400702 |Promoter: M C Babu

14 Aug 2017Registered with MahaRERAFirst of 2 registrations
31 Dec 2019Promised completionLatest across registrations
30 Dec 2020Revised completion1 of 2 registrations pushed back, by up to 1 year
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA

RERA registrations
2
Phases
2

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 18.89254, 72.98362
Eden Garden is at latitude 18.89254, longitude 72.98362.

Also registered as

Eden Garden II
MahaRERA's project page hasn't been imported for this project yet.

Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 1 year

P52000005932

The latest completion date on record passed 5 years and 10 months ago.

Registered
14 Aug 2017
Promised
31 Dec 2019
Revised
30 Dec 2020

Completion promised for 31 Dec 2019

P52000008714

The latest completion date on record passed 6 years and 10 months ago.

Registered
19 Aug 2017
Promised
31 Dec 2019

2 RERA registrations

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5200000593214 Aug 201731 Dec 201930 Dec 2020M C BabuProject page
P5200000871419 Aug 201731 Dec 2019—M C BabuProject page

Documents

3 documents held by Deedo

Registration certificates

  • Registration certificateP52000005932 · 14 Aug 2017ViewSource
  • Registration certificateP52000008714 · 19 Aug 2017ViewSource

Extension certificate

  • Extension certificateP52000005932 · 18 May 2020ViewSource

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Dongari

Survey, CTS, gat or plot numbers

35 Sector 5436

Source: registration certificates, as stated there.

SourcesMahaRERA project search · registration certificatesMethodology