RERA projects in Dronagiri

7 projects under 7 MahaRERA registrations, registered 2026–2026. 57% have a completion date extended beyond the one promised.

Locality
7RERA projects
7Registrations
7Completion still due0 past their completion date
4 monthsMedian extension beyond promised date57% of registrations extended
0Regulatory casesnone on MahaRERA's lists
8Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20267

Projects in Dronagiri

7 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
AnantaAstell Apex Developers LLPPM127000260228214 Oct 202631 Dec 2029—Not yet due0
Sagar SangamS D BuildconPR127000260228014 Oct 202631 Dec 2033—Not yet due0
Sunrise TowersMal And Mal Construction LLPPR127000260200623 Sep 202631 May 202931 May 2029Not yet due0
Suvidha VillaSuvidha EnterprisesPR127000260094729 Jun 202631 Dec 203230 Apr 2033Extended 4 mo0
VaikunthAvani EnterprisesPM127000260021218 Apr 202631 Dec 202830 Apr 2029Extended 4 mo0
Hari NiwasGlobe Infra Developers 1PR127000260014817 Apr 202631 Dec 203030 Apr 2031Extended 4 mo0
Shree Narayan ResidencyShree Ganesh Builders And DevelopersPM127000250270511 Mar 202631 Dec 202830 Apr 2029Extended 4 mo0

Other localities in Uran

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Astell Apex Developers LLP1 project
  2. Avani Enterprises1 project
  3. Globe Infra Developers 11 project
  4. Mal And Mal Construction LLP1 project
  5. S D Buildcon1 project
  6. Shree Ganesh Builders And Developers1 project
  7. Suvidha Enterprises1 project
Data through14 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology