Deedo IDDL-DHU-WALWADI4 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects11
Registrations11
Completion still due38 past their date
Median extension16 months18% of registrations extended
Regulatory cases0none on MahaRERA's lists
4 in 10 registrations run late here
11 MahaRERA registrations in Walwadi (Ct)
5 completed2 not yet due1 extended, not yet due3 past even the latest date
Extended registrations moved their completion date by a median of 16 months.
Projects in Walwadi (Ct)
11 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Dream's GTPNew Dream House Builders and Developers | Due Jul 2028, extended 4 mo | — | — |
| Bhalchandra RegencyOm Shiv Infra | Due Dec 2028 | — | — |
| BhalchandraHarvish Developer | Due Dec 2026 | — | — |
| G K ArcadeGopal Kashinath Kele HUF | 1 yr late | — | — |
| NakshatramDivine Infrastructure | Completed | — | 54% |
Nearby: other municipal areas in Dhule
Most active promoters
- Adinath Infrastructure1 project
- Concept Builder And Developers1 project
- Divine Infrastructure1 project
- Gopal Kashinath Kele1 project
- Gopal Kashinath Kele Huf1 project
- Harvish Developer1 project
- Harvish Deveopers1 project
- New Dream House Builders and Developers1 project
- Om Shiv Infra1 project
- Piyush Lifespaces Private Limited1 project
Walwadi (Ct), in questions
How many projects in Walwadi (Ct) run late?
4 in 10 MahaRERA registrations (4 of 11): their completion date was extended or has passed, data through 21 Oct 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Walwadi (Ct) by Deedo. Medians on fewer than 3 deeds are not shown.
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology