RERA projects in Dhule

71 projects under 71 MahaRERA registrations across 8 localities, registered 2017–2025. 15% have a completion date extended beyond the one promised.

71RERA projectsin 8 localities
71Registrations
13Completion still due49 past their completion date, 30 marked completed
28 monthsMedian extension beyond promised date15% of registrations extended
3Regulatory caseson 3 projects
164Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
201713
20183
20196
20206
20216
20228
20238
20244
20258

Localities in Dhule

By number of registered projects. Talukas and localities as MahaRERA names them.

Projects in Dhule

71 projects registered with MahaRERA in this district and the places within it.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Maruti Nandan Business HubSanjay Nandkishor AgrawalPC10900025006791 Sep 202531 Dec 2031—Not yet due0
Narmada HeightsAPS DevelopersPR109000250056213 Aug 202531 Dec 2028—Not yet due0
Dream's GTPNew Dream House Builders and DevelopersPR10900025001873 Jul 202531 Mar 2028—Not yet due0
Bhalchandra RegencyOm Shiv InfraP498000804334 Jun 202531 Dec 2028—Not yet due0
Narayani ApartmentChaudhari and Badgujar AssociatesP498000802219 May 202530 Dec 2026—Not yet due0
Nakshatram AthashriDivine InfrastructureP498000802016 May 202531 Dec 2027—Not yet due0
BhalchandraHarvish DeveloperP4980007998911 Apr 202530 Dec 2026—Not yet due0
Samata TowerSamata PropertiesP4980007921417 Feb 202530 Aug 2027—Not yet due0
AnandvanRaka Agrawal BuildersP4980007861727 Dec 202431 Mar 2030—Not yet due0
Radha Krishna Nagri Phase 1Smyle Housing Development Pvt. Ltd.P498000778567 Nov 202431 Dec 2027—Not yet due0
Shivam PlazaAlka Vasantrao WankhedeP4980007750720 Aug 202431 Dec 2028—Not yet due0
PremlataBhandari Realty And Infrastructure CompanyP4980007719029 Jul 202430 Jun 2026—Promised date passed0
Radha NagarAshok Ramniwas AgrawalP4980005156827 Jun 202331 Mar 2027—Completed0
Padmashree Residency VIIParag Subhash AhireP4980005043112 Apr 202330 Nov 2027—Not yet due0
G K ArcadeGopal Kashinath Kele HufP498000503081 Apr 202330 Nov 2025—Promised date passed0
Indramangal ApartmentM/S Navjeevan Developers And Infrastructure ServicesP4980005010115 Mar 202330 Sep 2024—Promised date passed0
NakshatramDivine InfrastructureP5210004956615 Feb 202331 Jul 2025—Promised date passed0
Krishna KunjaChetan Vidyadhar PathakP4980004944614 Feb 202331 Dec 2025—Promised date passed0
Krushna Kunj HeightsJai Shreekrishna Dream Homes Builders And DevelopersP4980004881419 Jan 202321 Sep 2025—Promised date passed0
Somvijay PrideRajendra Vasantrao KhankariP4980004864310 Jan 202331 Jan 2025—Promised date passed0
Nakshatra AvenueDharmniti Construction Private LimitedP4980004821515 Dec 202231 Mar 2026—Promised date passed0
The HorizonNilcon Infrabuilders Private LimitedP4980004617620 Jun 202215 Jun 2024—Completed0
G K Market Phase 1Gopal Kashinath KeleP4980004581415 Jun 202215 Jun 2023—Completed0
Suman ApartmentSiddhivinayak Engineer and ContractorsP4980003496428 Apr 20221 Jun 2023—Promised date passed0
Dreams AnuramDream House Builders And DevelopersP4980003461920 Apr 202231 Dec 2024—Promised date passed0
Shree Gajanan HeightsSachin Developers - -P4980003450211 Apr 202231 Dec 2024—Completed0
Ramkrishna ApartmentRajendra Vasantrao KhankariP4980003390814 Mar 202231 Mar 2023—Completed0
Shri Krishna VrindavanSoham ConstructionP4980003326710 Feb 202231 Dec 2023—Promised date passed0
SwapnashilpHarvish DeveopersP498000320986 Dec 202131 Mar 2024—Completed0
Venkatesh Dream HubSaisiddhi DeveloperP498000320333 Dec 202130 Jun 2023—Completed0
JaaiPiyush Lifespaces Pvt Ltd DhuleP4980003195329 Nov 202131 Mar 2025—Completed0
Sri Sri Balaji PalaceDinesh Bhatu FulpagareP4980003158231 Oct 202130 Sep 2022—Completed0
Uma DevalayamBorse Brothers Engineers & Contractors Private LimitedP498000305621 Sep 202131 Dec 2023—Promised date passed1
Nirmal HeightsVarsha Vasant PatilP4980002937329 May 202125 Jul 2022—Completed0
Gururaj ApartmentNilesh Prakash JadhavP4980002769931 Dec 202030 Jun 2023—Completed0
Surya ResidencyM/s Concept Builder And DevelopersP498000273576 Dec 202028 Feb 2022—Promised date passed0
Pooja AppartmetsIshwar Dnyandeo LadeP4980002720724 Nov 20209 Feb 2023—Promised date passed0
Padmashree Residency VIParag Subhash AhireP498000242863 Feb 202030 Jan 2024—Promised date passed0
Padmashree Residency VParag Subhash AhireP4980002425929 Jan 202030 Dec 2023—Promised date passed0
Tirth PushpamPiyush Lifespaces Private LimitedP498000238567 Jan 202030 Dec 2024—Completed0
Padmashree Residency IVParag Subhash AhireP4980002243924 Sep 201928 Aug 2023—Promised date passed0
Mangalmurti ResidencySumit Sanjay KorakeP4980002236416 Sep 20191 Oct 20205 Apr 2021Extended 6 mo0
BrahmakamalPiyush Lifespaces Private LimitedP498000222005 Sep 201930 Dec 2023—Completed0
Govardhan HeightsJai Shreekrishna Dream Homes Builders And DevelopersP498000215255 Jul 20191 Jul 2022—Completed0
Vivan CasitaBorse Brothers Engineers And Contractors Private LimitedP4980002119614 Jun 201931 Dec 202231 Dec 2023Completed0
COnstruction of 256EWS T/s and 64 Shops under PMAY scheme no S.No.471,477,478 Chalisgaon Road,DhuleNashik Housing & Area Development BoardP498000197555 Mar 201930 Mar 2025—Completed0
Hiradeep ApartmentParag Subhash AhireP4980001850912 Nov 201830 Dec 2022—Promised date passed0
Ashtavinayak NagarAshtavinayak Land DevelopersP4980001566716 Mar 20188 Mar 2019—Completed0
Pratikraj AprtmentAvinash Pundlik ThoratP4980001494015 Jan 201831 Dec 20199 Aug 2022Extended 32 mo0
Eknath HeightsLifestyle RealtiesP498000140147 Nov 201730 Dec 2021—Completed0
Vasudha ViharRajendra Vasantrao KhankariP498000135209 Oct 201715 Jan 202130 Jun 2023Completed0
Hasti TowerKumar DevelopersP498000134857 Oct 201731 Mar 2018—Completed0
Gokul ApartmentPundlik Gokul SutarP498000119691 Sep 201731 Mar 201831 Mar 2019Completed0
Rohini ApertmentYogiraj Shivajirao MaratheP498000119831 Sep 201731 Mar 201910 Mar 2023Completed0
Vedant ResidencyVedant BuildconP498000123021 Sep 201731 Aug 202031 Aug 2023Completed0
Santkrupa SankulChandrakant Kashinath KeleP4980001170131 Aug 201731 Dec 201930 Dec 2021Completed0
Vrundavan PlazaVrundavan BuildconP4980001128531 Aug 201731 Aug 2020—Completed0
Shri Krishna ApartmentPrashant DevelopersP4980001030024 Aug 201731 Aug 2020—Completed0
Raka ParkAdinath InfrastructureP4980000934222 Aug 201726 Aug 201830 Dec 2020Completed0
Shri Chatrapati Shivaji Maharaj Vyapari SankoolBorse Brothers Engineers And Contractors Private LimitedP4980000915919 Aug 201731 May 2018—Completed0
Kai. Abasaheb R R Patil Vyapari SankulBorse Brothers Engineers And Contractors Pvt LtdP4980000754417 Aug 201731 May 2018—Completed0
Chandravel3Piyush Lifespaces Private LimitedP4980000107426 Jul 201731 Dec 2019—Completed0
Aai Hinglaj ResidencyP49800021515————0
Ajinkyatara ResidencyKrushna Aavishkar RealtiesP49800033990————1
H K Villha ApartmentP49800017275————0
Jai Kishan ParkP49800015070————0
Kalindi ApartmentP49800011074————0
Padmashree Residency IIIP49800018489————0
Revised To Proposed 400 Ews And 288 Mig Housing At Site No.1a Survey No.60 Maujja.warwadeShirpur Warwade Municiple CouncilP49800052133————1
Shiv Prerna ApartmentP49800023981————0
Vrundavan ResidencyP49800017493————0

Other districts

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Parag Subhash Ahire5 projects
  2. Piyush Lifespaces Private Limited3 projects
  3. Rajendra Vasantrao Khankari3 projects
  4. Borse Brothers Engineers And Contractors Private Limited2 projects
  5. Divine Infrastructure2 projects
  6. Jai Shreekrishna Dream Homes Builders And Developers2 projects
  7. Adinath Infrastructure1 project
  8. Alka Vasantrao Wankhede1 project
  9. APS Developers1 project
  10. Ashok Ramniwas Agrawal1 project
Data through8 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology