Skip to content
Residential / Group Housing · 1 buildingRERA P49800051568

Radha Nagar

MahaRERA shows it completed; no MahaRERA orders on record.

Dhule (M Corp.), Dhule 424001 · Promoter: Ashok Ramniwas Agrawal

DeliveryCompletedAs MahaRERA showsRegulatoryNo ordersNot in any MahaRERA list or order Deedo has read
Radha Nagar project report cardPDF: delivery, regulatory orders, people on record, every tower and the registered deals — for your bank or lawyerSee what's inside · from ₹1,499

MahaRERA shows it completed

  • This projectRegistered 27 Jun 2023, completion promised 31 Mar 2027.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page. Construction % is the average of the developer's own declared activity progress to MahaRERA, not an inspection.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP49800051568
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P4980005156827 Jun 202331 Mar 2027—Ashok Ramniwas AgrawalProject page
Documents87

33 documents held by Deedo, 54 filings listed on MahaRERA's project page

Commencement certificate (2)

Form B

Encumbrance details (3)

Other (8)

Show all 87 documentsShow fewer documents

Other (8)

Allotment letter (2)

Title report

Registration certificate

Form 1 (4)

Form 2 (4)

Form 4 (3)

Form 5

Form 2A

Occupancy / completion certificate

  • Occupancy / completion certificate3 Dec 2024ViewSource

Layout plan

Document library

  • Copy of Layout Approval (in case of layout)sanction map.pdf · uploaded 1 Jun 2023View
  • Building Plan Approval / NA Order for plotted developmentsanction map.pdf · uploaded 1 Jun 2023View
  • Commencement Certificates / NA Order for plotted developmentBUILDING PERMIT.pdf · uploaded 1 Jun 2023View
  • Declaration in FORM BFORM B.pdf · uploaded 2 Jun 2023View
  • a Details of encumbrances concerned to FinanceFINANCIAL ENCUMBRANCE.pdf · uploaded 3 Jun 2023View
  • b Details of encumbrances concerned to LegalFINANCIAL ENCUMBRANCE.pdf · uploaded 3 Jun 2023View
  • a Details of encumbrances concerned to FinanceLEGAL ENCUMBRANCE.pdf · uploaded 3 Jun 2023View
  • b Details of encumbrances concerned to LegalLEGAL ENCUMBRANCE.pdf · uploaded 3 Jun 2023View
  • Declaration about Commencement CertificateFORM D.pdf · uploaded 3 Jun 2023View
  • Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameRevised Declaration about separate bank account.pdf · uploaded 3 Jun 2023View
  • Deviation Report with respect to Allotment letterDEVIATION IN ALLOTMENT.pdf · uploaded 3 Jun 2023View
  • Deviation Report with respect to model copy of AgreementDEVIATION IN AFS.pdf · uploaded 3 Jun 2023View
  • CERSAI detailsCersai Format Radha Nagar.pdf · uploaded 3 Jun 2023View
  • Copy of the legal title reportTITLE REPORT.pdf · uploaded 4 Jun 2023View
  • Disclosure of Interest in Other Real Estate OrganizationsANNEXURE A.pdf · uploaded 4 Jun 2023View
  • Proforma of Agreement for saleAGREEMENT TO SELL -RERA - AGRAWAL - DHULIYA.pdf · uploaded 4 Jun 2023View
  • Proforma of Allotment letterALLOTMENT LETTER.pdf · uploaded 4 Jun 2023View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect_Certificate.pdf · uploaded 5 Jan 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers_Certificate.pdf · uploaded 5 Jan 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)1 Form 1 - Radha Nagar - Sept 23.pdf · uploaded 28 Mar 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)2 Form 2 - Radha Nagar - Sept 23.pdf · uploaded 28 Mar 2024View
  • Disclosure of sold/ booked inventory5 Sold Booked Inv - Radha Nagar - Sept 23.pdf · uploaded 28 Mar 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1.pdf · uploaded 2 Jun 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2 (1).pdf · uploaded 2 Jun 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 (1).pdf · uploaded 2 Jun 2024View
  • Disclosure of sold/ booked inventorysold booked.pdf · uploaded 2 Jun 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2.pdf · uploaded 2 Jun 2024View
  • Disclosure of sold/ booked inventorysold booked.pdf · uploaded 2 Jun 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 29 Jul 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 29 Jul 2024View
  • Disclosure of sold/ booked inventorySOLD BOOKED.pdf · uploaded 29 Jul 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1.pdf · uploaded 18 Nov 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2.pdf · uploaded 18 Nov 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1.pdf · uploaded 18 Nov 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2.pdf · uploaded 18 Nov 2024View
  • Disclosure of sold/ booked inventorysold booked.pdf · uploaded 18 Nov 2024View
  • Architect’s Certificate on Completion of Project (Form 4)form 4.pdf · uploaded 18 Nov 2024View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)form 5.pdf · uploaded 18 Nov 2024View
  • Architect’s Certificate on Completion of Project (Form 4)form 4.pdf · uploaded 18 Nov 2024View
  • Disclosure of sold/ booked inventorysold booked.pdf · uploaded 18 Nov 2024View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)form 5.pdf · uploaded 18 Nov 2024View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentoc.pdf · uploaded 18 Nov 2024View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentoc.pdf · uploaded 18 Nov 2024View
  • Architect’s Certificate on Completion of Project (Form 4)Certificates ARA - Radha Nagar-1.pdf · uploaded 19 Nov 2024View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)document1_241118_170644.pdf · uploaded 19 Nov 2024View
  • Architect’s Certificate on Completion of Project (Form 4)Certificates ARA - Radha Nagar-1.pdf · uploaded 19 Nov 2024View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)document1_241118_170644.pdf · uploaded 19 Nov 2024View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentoc.pdf · uploaded 3 Dec 2024View
  • Architect’s Certificate on Completion of Project (Form 4)Radha Nagar - Form 4.pdf · uploaded 5 Dec 2024View

Promoter documents

  • Declaration Form BFORM B.pdf · uploaded 2 Jun 2023View
  • Legal Title reportTITLE REPORT.pdf · uploaded 4 Jun 2023View

Technical documents

  • Layout Approvalsanction map.pdfView
  • Building Plan Approvalsanction map.pdfView

Proforma allotment letter

  • Proforma allotment letterALLOTMENT LETTER.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvals41 42 43

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Completed
Address
41 42 43, Kh No 16/6, Mouza- Walwadi, Dhule, Mouza- WalwadiPIN 424001
Village
Dhule (M Corp.), Dhule taluka
Land area for this project
1,172 sq m (12,612 sq ft)
Permissible built-up area
1,289 sq m (13,873 sq ft)
Sanctioned built-up area
1,140 sq m (12,267 sq ft)
Designated bank account
Axis Bank
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Survey, CTS, gat or plot numbers

41 42 43

Land as published on MahaRERA's project page

41 42 43

Boundaries

North
Plot No 38 39 40
South
Plot No 44
East
12 Mtr Road
West
Plot No 34 35 36

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking0 parking spaces

0 units registered

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered00000
Open Space00000

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress2 buildings and areas

Work completed, as the promoter reported it to MahaRERA (Form 1)

Radha Nagar

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water SupplyAS PER PLAN100%
  • Sewerage (Chamber, Lines, Septic Tank , STP)AS PER PLAN100%
  • Storm Water DrainsNot applicable
  • Landscaping & Tree PlantingAS PER PLAN100%
  • Street LightingAS PER PLAN100%
Show all 15 activitiesShow fewer activities
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalAS PER PLAN100%
  • Water conservation /Rain water harvestingAS PER PLAN100%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Electrical meter room, sub-station, receiving stationAS PER PLAN100%
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingNot applicable

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Professionals4

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectVastushri Associate—
Chartered accountantAmit A Agrawal—
EngineerVastushri Associate—
OtherSatish More—

Source: MahaRERA project page. Contact details are not shown.

Data through9 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology