2 in 10 MahaRERA registrations here have pushed their completion date back.
RERA projects65
Registrations65
Completion still due1247 past their date
Median extension24 months19% of registrations extended
Regulatory cases1on 1 project
3 in 10 registrations run late here
65 MahaRERA registrations in Dhule and the places within it
29 completed9 not yet due2 extended, not yet due19 past even the latest date6 no date on record
Extended registrations moved their completion date by a median of 24 months.
Projects in Dhule
65 projects registered with MahaRERA in this taluka and the places within it.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Maruti Nandan Business HubSanjay Nandkishor Agrawal | Due Dec 2031 | — | — |
| Narmada HeightsAPS Developers | Due Apr 2029, extended 4 mo | — | — |
| Dream's GTPNew Dream House Builders and Developers | Due Jul 2028, extended 4 mo | — | — |
| Bhalchandra RegencyOm Shiv Infra | Due Dec 2028 | — | — |
| Narayani ApartmentChaudhari and Badgujar Associates | Due Dec 2026 | — | — |
| Nakshatram AthashriDivine Infrastructure | Due Dec 2027 | — | — |
| BhalchandraHarvish Developer | Due Dec 2026 | — | — |
| Samata TowerSamata Properties | Due Aug 2027 | — | — |
| AnandvanRaka Agrawal Builders | Due Mar 2030 | — | — |
| Shivam PlazaAlka Vasantrao Wankhede | Due Dec 2028 | — | — |
| PremlataBhandari Realty And Infrastructure Company | 4 mo late | — | — |
| Radha NagarAshok Ramniwas Agrawal | Completed | — | — |
| Padmashree Residency VIIParag Subhash Ahire | Due Nov 2027 | — | — |
| G K ArcadeGopal Kashinath Kele Huf | 11 mo late | — | — |
| NakshatramDivine Infrastructure | 1 yr 3 mo late | — | 54% |
| Krishna KunjaChetan Vidyadhar Pathak | 10 mo late | — | — |
| Krushna Kunj HeightsJai Shreekrishna Dream Homes Builders And Developers | 1 yr 1 mo late | — | — |
| Somvijay PrideRajendra Vasantrao Khankari | 1 yr 9 mo late | — | — |
| Nakshatra AvenueDharmniti Construction Private Limited | 7 mo late | — | — |
| The HorizonNilcon Infrabuilders Private Limited | Completed | — | — |
| G K Market Phase 1Gopal Kashinath Kele | Completed | — | — |
| Suman ApartmentSiddhivinayak Engineer and Contractors | 3 yrs 4 mo late | — | — |
| Dreams AnuramDream House Builders And Developers | 1 yr 10 mo late | — | — |
| Shree Gajanan HeightsSachin Developers - - | Completed | — | — |
| Ramkrishna ApartmentRajendra Vasantrao Khankari | Completed | — | — |
Nearby: other talukas in Dhule
Most active promoters
- Parag Subhash Ahire5 projects
- Piyush Lifespaces Private Limited3 projects
- Rajendra Vasantrao Khankari3 projects
- Borse Brothers Engineers And Contractors Private Limited2 projects
- Divine Infrastructure2 projects
- Jai Shreekrishna Dream Homes Builders And Developers2 projects
- Adinath Infrastructure1 project
- Alka Vasantrao Wankhede1 project
- APS Developers1 project
- Ashok Ramniwas Agrawal1 project
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology