Dhule (M Corp.), Dhule 424002 |Promoter: Parag Subhash Ahire

Residential / Group HousingRERAP49800018509
12 Nov 2018Registered with MahaRERA
30 Dec 2022Promised completion
1Building
26Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Lapsed
Buildings
1
Unit types
1 BHKS, Basement, Shop26 units in all
Land area for this project
488 sq m (5,248 sq ft)
Permissible built-up area
683 sq m (7,348 sq ft)
Sanctioned built-up area
681 sq m (7,329 sq ft)
Address
Sr No 8/14/2 Part Plot No 12, Jay Hind College Road, Jay Hind ColonyPIN 424002
Designated bank account
Hdfc Bank
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 20.91094, 74.77068
Hiradeep Apartment is at latitude 20.91094, longitude 74.77068.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 30 Dec 2022

The latest completion date on record passed 3 years and 10 months ago.

Registered
12 Nov 2018
Promised
30 Dec 2022

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P4980001850912 Nov 201830 Dec 2022—Parag Subhash AhireProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Hiraseep Apartment726

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

26 units registered

1 BHKS · 16 unitsBasement · 5 unitsShop · 5 units
TypeCarpet areaUnits
1 BHKS28.9 sq m · 311 sq ft4
1 BHKS29.14 sq m · 314 sq ft4
1 BHKS29.51 sq m · 318 sq ft4
1 BHKS29.6 sq m · 319 sq ft4
Basement9.39 sq m · 101 sq ft5
Shop9.95 sq m · 107 sq ft5

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered00001
Open Space00000

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Hiraseep Apartment

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water SupplyCORPORATION WATER SUPPLY100%
  • Sewerage (Chamber, Lines, Septic Tank , STP)COMPLETED100%
  • Storm Water DrainsNot applicable
  • Landscaping & Tree Planting5 TREE PLANTATION100%
  • Street LightingNot applicable
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingCOMPLETED100%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Electrical meter room, sub-station, receiving stationWOODEN METER BOX PROVIDED100%
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingNot applicable
  • LIFTCOMPLETED100%

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

19 documents held by Deedo, 23 filings listed on MahaRERA's project page

Title

Encumbrance

Commencement certificate

Form b

Registration certificate

Completion

Others

Layout plan

Building plan

Allotment letter

Document library

  • Declaration in FORM BHiradeep Apt Form B Promoter.pdf · uploaded 28 Oct 2018View
  • Details of encumbrancesHiradeep Apt Encumbrance Promoter.pdf · uploaded 28 Oct 2018View
  • Commencement Certificates / NA Order for plotted developmentHiradeep Apt Commencement Certificate.pdf · uploaded 28 Oct 2018View
  • Copy of the legal title reportHiradeep Apt Title Report.pdf · uploaded 28 Oct 2018View
  • Building Plan Approval (IOD)Hiradeep IOD 3.pdf · uploaded 28 Oct 2018View
  • Copy of Layout Approval (in case of layout)Hiradeep Lay Out.pdf · uploaded 28 Oct 2018View
  • Proforma of Allotment letterHiradeep Apt Corrected Agreement To Sell.pdf · uploaded 28 Oct 2018View
  • Status of ConveyancePadmashri Residency IV Declaration of Apt R to 14.pdf · uploaded 22 Jan 2025View
  • Status of ConveyancePadmashri Residency IV Declaration of Apt 15 to 25.pdf · uploaded 22 Jan 2025View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentPadmashri Residency IV Declaration of Apt R to 14.pdf · uploaded 22 Jan 2025View
  • Status of Formation of Legal Entity (Society/Co Op etc.)Hiradeep Apartment Declaration of Apt R to 11.pdf · uploaded 22 Jan 2025View
  • Status of Formation of Legal Entity (Society/Co Op etc.)Hiradeep Apartment Declaration of Apt 12 to 24.pdf · uploaded 22 Jan 2025View
  • Status of Formation of Legal Entity (Society/Co Op etc.)Hiradeep Apartment Declaration of Apt 25 to 35.pdf · uploaded 22 Jan 2025View
  • Status of ConveyanceHiradeep Apartment Declaration of Apt R to 11.pdf · uploaded 22 Jan 2025View
  • Status of Formation of Legal Entity (Society/Co Op etc.)Hiradeep Apartment Declaration of Apt 36 to 50 end.pdf · uploaded 22 Jan 2025View
  • Status of ConveyanceHiradeep Apartment Declaration of Apt 12 to 24.pdf · uploaded 22 Jan 2025View
  • Status of ConveyanceHiradeep Apartment Declaration of Apt 25 to 35.pdf · uploaded 22 Jan 2025View
  • Status of ConveyanceHiradeep Apartment Declaration of Apt 36 to 50 end.pdf · uploaded 22 Jan 2025View

Promoter documents

  • Declaration Form BHiradeep Apt Form B Promoter.pdf · uploaded 28 Oct 2018View
  • Legal Title reportHiradeep Apt Title Report.pdf · uploaded 28 Oct 2018View

Technical documents

  • Building Plan ApprovalHiradeep IOD 3.pdfView
  • Layout ApprovalHiradeep Lay Out.pdfView

Proforma allotment letter

  • Proforma allotment letterHiradeep Apt Corrected Agreement To Sell.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Dhule (M Corp.), Dhule taluka

Survey, CTS, gat or plot numbers

12SR NO 8/14/2 PART PLOT NO 12

As published on MahaRERA's project page

SR NO 8/14/2 PART PLOT NO 12

Boundaries

North
12 Mtr Road
South
Colony Road
East
Plot No 5
West
Plot No 15

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectParag Ahire—

Source: MahaRERA project page. Contact details are not shown.