Vivan Casita

Completed

Dhule (M Corp.), Dhule 424002 |Promoter: Borse Brothers Engineers And Contractors Private Limited

Residential / Group HousingRERAP49800021196
14 Jun 2019Registered with MahaRERA
31 Dec 2022Promised completion
31 Dec 2023Revised completionPushed back 1 year
1Building
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Completed
Buildings
1
Land area for this project
670 sq m (7,208 sq ft)
Permissible built-up area
933 sq m (10,043 sq ft)
Sanctioned built-up area
933 sq m (10,043 sq ft)
Address
Plot No 34 Survey No 08 and 14/2, Deopur, DeopurPIN 424002
Designated bank account
State Bank Of India
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 20.91146, 74.77127
Vivan Casita is at latitude 20.91146, longitude 74.77127.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 1 year

The latest completion date on record passed 2 years and 10 months ago.

Registered
14 Jun 2019
Promised
31 Dec 2022
Revised
31 Dec 2023

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P4980002119614 Jun 201931 Dec 202231 Dec 2023Borse Brothers Engineers And Contractors Private LimitedProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Vivan Casita5—

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

0 units registered

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered00006
Open Space00006

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Vivan Casita

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water SupplyCompleted100%
  • Sewerage (Chamber, Lines, Septic Tank , STP)work in progress100%
  • Storm Water DrainsNot applicable
  • Landscaping & Tree PlantingNot applicable
  • Street LightingNot applicable
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingRain Water Pipe Installation completed100%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Electrical meter room, sub-station, receiving stationElectrical Meter Room100%
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingCompleted100%

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

26 documents held by Deedo, 26 filings listed on MahaRERA's project page

Title

Commencement certificates

Form b

Encumbrance

Allotment letters

Form 5s

Form 2a

Others

Extension certificate

Registration certificate

Completion

Form 1

Form 2

Layout plan

Document library

  • Declaration in FORM BForm_B_Affidavit.pdf · uploaded 10 May 2019View
  • Copy of the legal title reportLegal Title Search Report.pdf · uploaded 10 May 2019View
  • Copy of Layout Approval (in case of layout)SANCTION DRAWING PLAN A3 SIZE.pdf · uploaded 10 May 2019View
  • Building Plan Approval (IOD)SANCTION DRAWING PLAN A3 SIZE.pdf · uploaded 10 May 2019View
  • Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 10 May 2019View
  • Details of encumbrancesNo Encumbrances.pdf · uploaded 14 May 2019View
  • Proforma of Allotment letterArgeement for Sale.pdf · uploaded 15 May 2019View
  • Proforma of Allotment letterAllotment Letter.pdf · uploaded 7 Jun 2019View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Form 5_Vivan Casita.pdf · uploaded 25 Jun 2022View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Audit Report-20-21 Vivaan Casita.pdf · uploaded 19 Jul 2022View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Audit report_Vivaan Casita_21 22.pdf · uploaded 28 Nov 2022View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Audit Report-20-21 Vivaan Casita.pdf · uploaded 28 Nov 2022View
  • Declaration about Commencement CertificateForm D.pdf · uploaded 28 Nov 2022View
  • Disclosure of sold/ booked inventorySold Booked.pdf · uploaded 28 Nov 2022View
  • CERSAI detailsCERSAI Report.pdf · uploaded 28 Nov 2022View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentVC_OCCUPENCEY CERTIFICATE DT 04012023 COL_250131_164305.pdf · uploaded 27 Mar 2025View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)RERA Audit report 22-23.pdf · uploaded 22 Apr 2025View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)RERA Audit report 22-23.pdf · uploaded 22 Apr 2025View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHICT'S CERTIFICATE_0001.pdf · uploaded 23 Apr 2025View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers's Certificate_.pdf · uploaded 23 Apr 2025View
  • Disclosure of sold/ booked inventoryDISCLOSURE OF SOLD-BOOKED INVENTRY VIVAAN CASITA.pdf · uploaded 28 Apr 2025View

Promoter documents

  • Declaration Form BForm_B_Affidavit.pdf · uploaded 10 May 2019View
  • Legal Title reportLegal Title Search Report.pdf · uploaded 10 May 2019View

Technical documents

  • Building Plan ApprovalSANCTION DRAWING PLAN A3 SIZE.pdfView
  • Layout ApprovalSANCTION DRAWING PLAN A3 SIZE.pdfView

Proforma allotment letter

  • Proforma allotment letterArgeement for Sale.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Dhule (M Corp.), Dhule taluka

Survey, CTS, gat or plot numbers

0814/214/234Plot No 34 Survey No 08

As published on MahaRERA's project page

Plot No 34 Survey No 08 and 14/2

Boundaries

North
Survey No 6
South
Road
East
Plot No 33
West
Plot No 35

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAvinash Devchand Bhavsar—

Source: MahaRERA project page. Contact details are not shown.

Data through8 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology