3 in 10 MahaRERA registrations here have pushed their completion date back.

RERA projects1,472in 81 localities
Registrations1,499some projects hold several
Completion still due422782 past their date
Median extension4 months31% of registrations extended
Regulatory cases122on 114 projects
Aurangabad market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

6 in 10 registrations run late here

1,499 MahaRERA registrations in Aurangabad and the places within it

181 completed140 not yet due269 extended, not yet due614 past even the latest date295 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Aurangabad

1,472 projects registered with MahaRERA in this district and the places within it.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Oberoi Manali ComfortManali VenturesPM10400026011169 Jul 202631 Oct 202928 Feb 2030Extended 4 mo0
Madhura Angan Phase 2Madhura Ventures LLPPM10400026010688 Jul 202631 Dec 203230 Apr 2033Extended 4 mo0
Morya Residency 2Morya BuildersPR10400026010243 Jul 202631 Mar 202831 Jul 2028Extended 4 mo0
Aarav EnclaveRajendra Laxminarayan JaiswalPR104000260095329 Jun 202631 Mar 202831 Jul 2028Extended 4 mo0
MORYA PARK Ph-IIIMh Builders And DevelopersPR104000260097529 Jun 202631 Dec 203130 Apr 2032Extended 4 mo0
Sawangi City Phase-2Aryaman InfraPR104000260092724 Jun 202631 Mar 203131 Jul 2031Extended 4 mo0
Sai NakshatraEverest Bajaj CombinesPR104000260089923 Jun 202631 Dec 203030 Apr 2031Extended 4 mo0
Leela-3Leela RealityPM10400026006725 Jun 202630 Apr 202930 Aug 2029Extended 4 mo0
Prisha Square Phase-IINandkishor Bhimrao ChavanPR10400026005991 Jun 202631 Dec 203030 Apr 2031Extended 4 mo0
Tirupati HillsSSBD Builders and Developers LLPPR10400026005951 Jun 202630 Jun 202830 Oct 2028Extended 4 mo0
Om Sai ResidencyDattatray Gangadhar RautPR104000260049621 May 202631 Dec 203030 Apr 2031Extended 4 mo0
Ssbd TowerSSBD Builders and Developers LLPPR10400026003748 May 202631 Dec 202730 Apr 2028Extended 4 mo0
Shanta Apartment Swanand RealtiesSwanand RealtiesPR10400026003566 May 202630 Nov 202830 Mar 2029Extended 4 mo0
T ThreeTayal Business Park LLPPC10400026003506 May 202631 Dec 202930 Apr 2030Extended 4 mo0
Bhumija TejasBhumija Infra & DevelopersPM104000260024823 Apr 202631 Dec 202930 Apr 2030Extended 4 mo0
Omkar ResidencyOmkar DevelopersPM104000260022321 Apr 202614 Nov 202914 Mar 2030Extended 4 mo0
Radha Nagari BVision InfraPR104000260020518 Apr 202617 Jan 203117 May 2031Extended 4 mo0
Palm Leaves Phase 2Shakti Lifespaces Pvt LtdPR104101260012917 Apr 202630 Jun 202730 Oct 2027Extended 4 mo0
Khinvasara August HighStreet MarketChampalal Kanhaiyalal KhinvasaraPC10410126000569 Apr 202631 Dec 203130 Apr 2032Extended 4 mo0
Shubhlabh HeritageBhaishree Realtors LLPPM10400026000176 Apr 202615 Jan 203015 May 2030Extended 4 mo0
Jadhav HeightsSantosh Uttamrao JadhavP5150008111018 Mar 202615 Dec 202715 Apr 2028Extended 4 mo0
Mahalaxmi Saubhagya 3Moreshwar Ramchandra KulkarniPR104000250293118 Mar 202631 Dec 203230 Apr 2033Extended 4 mo0
Param HeightsParam HeightsPC104000250287317 Mar 202631 Dec 203030 Apr 2031Extended 4 mo0
Radha Nagari AVision InfraPR104000250281516 Mar 20264 Feb 20314 Jun 2031Extended 4 mo0
The AltusShakti Lifespaces Pvt LtdPM104000250282016 Mar 202631 Dec 203030 Apr 2031Extended 4 mo0

Most active promoters

  1. Vikas Laxman Chaudhary13 projects
  2. Sajansing Motilal Jarwal11 projects
  3. Simar Pride Ventures LLP10 projects
  4. Bhuvi Landmarks LLP8 projects
  5. Sara Properties8 projects
  6. Sara Infrastructures7 projects
  7. Abad Estate Aop6 projects
  8. Arch Developers6 projects
  9. Ashok Baheti6 projects
  10. Jagrut Sara Associates6 projects
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology