Delayed projects in Maharashtra
8,413 MahaRERA projects in 36 districts are past their promised completion date, and MahaRERA shows no completion for them.
Most overdue first
Late: the latest completion date MahaRERA records (promised, or revised by an extension) has passed. Months late count from the first promised date. Page 45 of 169.
| Project | Locality | Promised | Revised | Delivery |
|---|---|---|---|---|
| Tsp HeightsAshwamegh Assoicates | DombivliThane | Jul 2022 | Dec 2022 | 4 yrs 4 mo late |
| VivantaKshitij Realtors And Developers | KurlaMumbai Suburban | Jul 2022 | Jul 2022 | 4 yrs 4 mo late |
| Wollywood Gold INirvana Lifestyle Homes LLP | AmboliPalghar | Jul 2022 | Jul 2022 | 4 yrs 4 mo late |
| Chirag Construction | Adivali DhokaliThane | Aug 2022 | Aug 2022 | 4 yrs 3 mo late |
| HillcrestSwapnashilp Buildcon | VaralePune | Aug 2022 | Oct 2026 | 4 yrs 3 mo late |
| Sai Laxmi SahniwasOm Sai Datta Construction | Sangli Miraj Kupwad (M Corp.)Sangli | Aug 2022 | Aug 2022 | 4 yrs 3 mo late |
| Triaa PrincetownTriaa Infracon LLP | ShikrapurPune | Aug 2022 | Aug 2022 | 4 yrs 3 mo late |
| Trijal Enterprises | Adivali DhokaliThane | Aug 2022 | Aug 2022 | 4 yrs 3 mo late |
| Vikram Villa Co-Op Housing SocietyChaturthi Developers | DombivliThane | Aug 2022 | Jan 2024 | 4 yrs 3 mo late |
| Shree Pandurang Gore ComplexJain Builders & Developers | GoregaonRaigarh | Aug 2022 | Aug 2022 | 4 yrs 3 mo late |
| Riya NiwasCharan Pandurang Patil | PushapakRaigarh | Aug 2022 | Aug 2024 | 4 yrs 3 mo late |
| Krishna Raj ComplexAmit Govindrao Bhosale | Vita (M Cl)Sangli | Aug 2022 | Aug 2022 | 4 yrs 3 mo late |
| Oxy Gold DM M Developers | Shirur GraminPune | Aug 2022 | Aug 2022 | 4 yrs 3 mo late |
| Chintamani Hill ViewVrushabh Builders & Developers | DevlaiAurangabad | Aug 2022 | Aug 2022 | 4 yrs 3 mo late |
| Janak Jambha NagariPprom Constructions LLP | ShirshingeRatnagiri | Aug 2022 | Aug 2022 | 4 yrs 3 mo late |
| Prishita ParadiseVirendra Pandurang More | GimhavaneRatnagiri | Aug 2022 | Aug 2022 | 4 yrs 3 mo late |
| ABHANG Phase IKale and Dhankawade Associates | Ambegaon BkPune | Aug 2022 | Aug 2024 | 4 yrs 3 mo late |
| RSM Heights E PhaseRajendra Sukhadev Mirgane | BarshiSolapur | Aug 2022 | Aug 2022 | 4 yrs 3 mo late |
| Chandak SnehShruti Kishor Chandak | Solapur (M Corp.)Solapur | Aug 2022 | Dec 2025 | 4 yrs 3 mo late |
| Sai PlatinumPrakash Aburao Tate | Pimpri Chinchawad (M Corp.)Pune | Aug 2022 | Aug 2022 | 4 yrs 3 mo late |
| Apex Business Court Phase IMohnish Ramesh Chordia | Pune CityPune | Aug 2022 | Aug 2022 | 4 yrs 3 mo late |
| Ashirwad ResidencyPrakalpa Builders And Developers LLP | WahalRaigarh | Aug 2022 | Aug 2022 | 4 yrs 3 mo late |
| AvaniKamal Promoters & Builders. | MohammadwadiPune | Aug 2022 | Aug 2023 | 4 yrs 3 mo late |
| Elite Estate Building B And C Phase IMulik Assocaites | Koregaon Bhima (Ct)Pune | Aug 2022 | Aug 2022 | 4 yrs 3 mo late |
| Gagan AvivaGagan Landmarks LLP | KesnandPune | Aug 2022 | Aug 2025 | 4 yrs 3 mo late |
| Hari Om Shiv KrupaYashwant Nagesh Waghe | WahalRaigarh | Aug 2022 | Aug 2022 | 4 yrs 3 mo late |
| Lifestyle City Kalyan RivieraNirmal Lifestyle (Kalyan) Private Limited | Vadavali Kh.Thane | Aug 2022 | Oct 2024 | 4 yrs 3 mo late |
| Lifestyle City Kalyan-Magnolia ANirmal Lifestyle (Kalyan) Private Limited | Vadavali Kh.Thane | Aug 2022 | Aug 2022 | 4 yrs 3 mo late |
| Mahadev ResidencyRajkumar Tuljaram Aswani | Asangaon (Ct)Thane | Aug 2022 | Aug 2022 | 4 yrs 3 mo late |
| Md TownShailendra Manohar Pulliwar | BesaNagpur | Aug 2022 | Aug 2023 | 4 yrs 3 mo late |
| Neha GalaxyNeha Construction | DevlaiAurangabad | Aug 2022 | Aug 2023 | 4 yrs 3 mo late |
| Parshuram ComplexSanjay Ambu Patil | PushapakRaigarh | Aug 2022 | Aug 2022 | 4 yrs 3 mo late |
| Parth Estate Building DSandeep Construction Company | DehuPune | Aug 2022 | Aug 2022 | 4 yrs 3 mo late |
| Sai Dham Building No. 03Shree Sai Developers | UmroliPalghar | Aug 2022 | Dec 2024 | 4 yrs 3 mo late |
| Shreejis OrionVN Developers | SomatanePune | Aug 2022 | May 2026 | 4 yrs 3 mo late |
| Soham RiveriaSoham Builders | Wadgaon BkPune | Aug 2022 | Aug 2022 | 4 yrs 3 mo late |
| AashrayDurvankur Associates Realtors And Developers | SinnarNashik | Aug 2022 | Aug 2022 | 4 yrs 3 mo late |
| KingstonSushant Sudhakar Pol | DongariRaigarh | Aug 2022 | Dec 2025 | 4 yrs 3 mo late |
| Nirmala NiwasSRS Developers | WahalRaigarh | Aug 2022 | Aug 2022 | 4 yrs 3 mo late |
| Sai Harsh AvenueA Cube B Buildcon | Nashik (M Corp.)Nashik | Aug 2022 | Aug 2022 | 4 yrs 3 mo late |
| Shivpriya ResidencyOm Gurudev Promoters Builders And Contractors | Shukrawar PethPune | Sep 2022 | Dec 2024 | 4 yrs 2 mo late |
| Shree Swami Samarth ApartmentSudhir Shankar Dhadve | BharaneRatnagiri | Sep 2022 | Sep 2022 | 4 yrs 2 mo late |
| Sai PlazaShree Developers | Ambegaon BkPune | Sep 2022 | Sep 2022 | 4 yrs 2 mo late |
| VenusresidencyGem Promoters Builders And Developers | Sangli Miraj Kupwad (M Corp.)Sangli | Sep 2022 | Sep 2022 | 4 yrs 2 mo late |
| Vastushree BuildingM/s.Shiv Developers through its Prop.Shri. Shankar Laxman Gaikwad | BhigvanPune | Sep 2022 | Sep 2022 | 4 yrs 2 mo late |
| Namdev ResidencyOm Sai Enterprises | Vadghar (Ct)Raigarh | Sep 2022 | Sep 2022 | 4 yrs 2 mo late |
| shreeram sankulVishal Vishwas Kale | Sangamner (Mcl)Ahmednagar | Sep 2022 | Sep 2022 | 4 yrs 2 mo late |
| Ekdant ResidencyGajraj Constructions | ParvatiPune | Sep 2022 | Sep 2023 | 4 yrs 2 mo late |
| Aakash HeightsKalpataru Promoters Developers Pvt Ltd | PimpriPune | Sep 2022 | Sep 2023 | 4 yrs 2 mo late |
| Akshara HillsK N K Builders | KatrajPune | Sep 2022 | Sep 2022 | 4 yrs 2 mo late |
Delayed projects by district
Pune · 2,214Thane · 1,157Raigarh · 1,041Mumbai Suburban · 994Nashik · 481Palghar · 362Nagpur · 323Aurangabad · 243Mumbai City · 242Satara · 228Ratnagiri · 192Sangli · 176Solapur · 155Kolhapur · 131Amravati · 72Sindhudurg · 72Ahmednagar · 69Chandrapur · 39Jalgaon · 39Latur · 27Akola · 23Beed · 21Nanded · 18Dhule · 17Wardha · 16Buldana · 14Jalna · 12Parbhani · 9Bhandara · 8Yavatmal · 6
SourcesMahaRERA registrations, extension certificates, project pages and document listsA project counts as completed when MahaRERA shows it so: its status, or a completion or occupancy certificate in its documents. Dates are MahaRERA's; Deedo does not know the day a project was handed over.Report a problemMethodology