RERA projects in Sangamner (Mcl)
13 projects under 13 MahaRERA registrations, registered 2017–2026. 54% have a completion date extended beyond the one promised.
Locality
13RERA projects
13Registrations
4Completion still due9 past their completion date
4 monthsMedian extension beyond promised date54% of registrations extended
0Regulatory casesnone on MahaRERA's lists
13Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 3 |
| 2018 | 2 |
| 2019 | 0 |
| 2020 | 1 |
| 2021 | 2 |
| 2022 | 1 |
| 2023 | 0 |
| 2024 | 3 |
| 2025 | 0 |
| 2026 | 1 |
Projects in Sangamner (Mcl)
13 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Pr1010002502162Navrang Corporation | PR1010002502162 | 23 Jan 2026 | 31 May 2028 | 30 Sep 2028 | Extended 4 mo | 0 |
| Samartha PlazaYashashri Buildcon | P52200055941 | 2 May 2024 | 31 Dec 2027 | 30 Apr 2028 | Extended 4 mo | 0 |
| Sangamner CentralFortune Developers | P52200055965 | 2 May 2024 | 31 Dec 2027 | 30 Apr 2028 | Extended 4 mo | 0 |
| Building at CTS No 2454Nirvana Life Realty | P52200054363 | 17 Jan 2024 | 31 Mar 2026 | 31 Jul 2026 | Extended 4 mo | 0 |
| Morya GangaiMorya Construction | P52200046982 | 26 Sep 2022 | 31 Dec 2026 | 30 Apr 2027 | Extended 4 mo | 0 |
| Krushna Pride 21Krushna Properties | P52200031826 | 12 Nov 2021 | 31 Dec 2025 | 31 Dec 2025 | Promised date passed | 0 |
| Nayantara apartmentPrafulla Nandanmal Bafna | P52200028887 | 5 Apr 2021 | 30 Jun 2024 | 30 Jun 2024 | Promised date passed | 0 |
| Krushna PropertiesKrushna Properties | P52200024657 | 26 Feb 2020 | 30 May 2023 | 30 May 2023 | Promised date passed | 0 |
| Morya ResidencyMorya Construction | P52200015475 | 28 Feb 2018 | 9 May 2019 | 9 May 2019 | Promised date passed | 0 |
| City CenterCity Center | P52200015178 | 2 Feb 2018 | 30 Dec 2021 | 30 Dec 2021 | Promised date passed | 0 |
| Aman PlazaAman Constructions | P52200014104 | 7 Nov 2017 | 30 Dec 2023 | 29 Dec 2024 | Extended 12 mo | 0 |
| shreeram sankulVishal Vishwas Kale | P52200013813 | 25 Oct 2017 | 21 Sep 2022 | 21 Sep 2022 | Promised date passed | 0 |
| Top Ten ImperialTop Ten Developers | P52200011619 | 31 Aug 2017 | 31 Dec 2019 | 30 Dec 2021 | Extended 24 mo | 0 |
Other localities in Sangamner
Most active promoters
By projects registered here, as named on MahaRERA.
- Krushna Properties2 projects
- Morya Construction2 projects
- Aman Constructions1 project
- City Center1 project
- Fortune Developers1 project
- Navrang Corporation1 project
- Nirvana Life Realty1 project
- Prafulla Nandanmal Bafna1 project
- Top Ten Developers1 project
- Vishal Vishwas Kale1 project
Data through11 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology