Barshi, Solapur
Deedo IDDL-SOL-BARSHI-310 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects26
Registrations26
Completion still due422 past their date
Median extension18 months42% of registrations extended
Regulatory cases0none on MahaRERA's lists
10 in 10 registrations run late here
26 MahaRERA registrations in Barshi
4 extended, not yet due22 past even the latest date
Extended registrations moved their completion date by a median of 18 months.
Projects in Barshi
26 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Samruddhi ApartmentAshwa Vishwa Builders Private Limited | 5 mo late | — | — |
| Royal Residency Building No 2Shubhankar Developers | Completed | — | 39% |
| Mangal ResidencyPradnya Abhijit Patil | 11 mo late | — | — |
| Tower A , Group Housing At Gat No. 637/1/4Marval Construction And Developers | Due Apr 2027, extended 4 mo | — | — |
| Varad NagariShriram Builders & Developers | Completed | — | — |
Nearby: other villages in Barshi
Most active promoters
- Rajendra Sukhadev Mirgane3 projects
- Satish Malanbai Andhare3 projects
- Rsm Nest Developers2 projects
- Sahayog Developers2 projects
- Satyabhamavitthal Construction And Land Developers Private Limited Barshi2 projects
- Ashwa Vishwa Builders Private Limited1 project
- Barshi Nagar Parishad1 project
- Idhant Construction And Developers1 project
- Mahaveer Developers And Builders1 project
- Marval Construction And Developers1 project
Barshi, in questions
How many projects in Barshi run late?
10 in 10 MahaRERA registrations (26 of 26): their completion date was extended or has passed, data through 24 Oct 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Barshi by Deedo. Medians on fewer than 3 deeds are not shown.
Data through24 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology