Skip to content
Residential / Group Housing · 1 building · 16 unitsRERA P52600080239

Samruddhi Apartment

Deedo IDDP-SOL-XP7Z

Completion was pushed back 4 months to Oct 2026, and that date has passed too; no MahaRERA orders on record; 0% of its units are booked.

Barshi, Solapur 413401 · by Ashwa Vishwa Builders Private Limited

Delivery5 mo latePromised Jun 2026 · revised Oct 2026 · that date has passed tooRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 16 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months to Oct 2026, and that date has passed too

  • This projectRegistered 13 May 2025, completion promised 30 Jun 2026, revised to 30 Oct 2026, and still not shown completed today.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52600080239
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5260008023913 May 202530 Jun 202630 Oct 2026Ashwa Vishwa Builders Private LimitedProject page
Documents45

1 document held by Deedo, 44 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPan Card.pdf · uploaded 31 Dec 2024Source

Legal

  • Legal Title reportSearch Report for RERA.pdf · uploaded 25 Dec 2024Source
  • Other – Legalorganized (35).pdf · uploaded 31 Jan 2025Source
  • Declaration Form BAshwa Vishwa Builders PVT.pdf · uploaded 3 Mar 2025Source

Migrated

  • 1 Copy of Layout Approval (in case of layout)Plan_RBP_ Ashwa Vishwa Builders_240702_155329.pdf · uploaded 2 Jul 2024Source
  • 2 Commencement Certificates / NA Order for plotted developmentCert_RBP_ Ashwa Vishwa Builders.pdf · uploaded 2 Jul 2024Source
  • 1 Building Plan Approval / NA Order for plotted developmentPlan_RBP_ Ashwa Vishwa Builders_240702_155329.pdf · uploaded 2 Jul 2024Source
Show all 45 documentsShow fewer documents

Migrated

  • 1 Copy of the legal title reportSearch Report for RERA.pdf · uploaded 25 Dec 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Architect.pdf · uploaded 25 Dec 2024Source
  • 1 Declaration about all RERA Designated Bank Accounts (Format A)Format A - Promoter Letterhead.pdf · uploaded 25 Dec 2024Source
  • 1 Deviation Report with respect to Allotment letterDeviation Allotment Flat Own Land.pdf · uploaded 25 Dec 2024Source
  • 1 Deviation Report with respect to model copy of AgreementDeviation ATS Apartment Own Land.pdf · uploaded 25 Dec 2024Source
  • 1 PAN CardPan Card.pdf · uploaded 31 Dec 2024Source
  • 1 a Details of encumbrances concerned to FinanceNo Encumbrance Financial.pdf · uploaded 31 Dec 2024Source
  • 2 a Details of encumbrances concerned to FinanceNo Encumbrance Legal.pdf · uploaded 31 Dec 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 31 Dec 2024Source
  • 1 Declaration about Commencement CertificateDeclaration About CC.pdf · uploaded 31 Dec 2024Source
  • 2 CERSAI detailsCersai.pdf · uploaded 31 Dec 2024Source
  • 1 b Details of encumbrances concerned to LegalNo Encumbrance Financial.pdf · uploaded 31 Dec 2024Source
  • 2 b Details of encumbrances concerned to LegalNo Encumbrance Legal.pdf · uploaded 31 Dec 2024Source
  • 1 Proforma of Allotment letterAllotment Letter Flat Own Land.pdf · uploaded 8 Jan 2025Source
  • 1 Other – TechnicalDeclaration of Non Registration Standalone Project.pdf · uploaded 8 Jan 2025Source
  • 1 Proforma of Agreement for saleAgreement to sale Flat Own Land.pdf · uploaded 8 Jan 2025Source
  • 1 Disclosure for secured/unsecured finance availed for the projectDisclosure of Finance Secured.pdf · uploaded 8 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Engineer.pdf · uploaded 9 Jan 2025Source
  • 1 CERSAI detailsCERSAI Declaration.pdf · uploaded 9 Jan 2025Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsInterest in Other Projects - Promoter Letterhead.pdf · uploaded 9 Jan 2025Source
  • 1 Other – Legalorganized (35).pdf · uploaded 31 Jan 2025Source
  • 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)PDFGallery_20250131_165731 (1).pdf · uploaded 1 Feb 2025Source
  • 1 Declaration in FORM BAshwa Vishwa Builders PVT.pdf · uploaded 3 Mar 2025Source
  • 1 Commencement Certificates / NA Order for plotted developmentilovepdf_merged (78).pdf · uploaded 29 Apr 2025Source
  • 2 Other – TechnicalClarification on email from authority.pdf · uploaded 29 Apr 2025Source
  • 3 Other – Technicalrera patra.pdf · uploaded 29 Apr 2025Source
  • 4 Other – TechnicalRERA PATRA EMAIL.pdf · uploaded 29 Apr 2025Source
  • 5 Other – TechnicalCC Email.pdf · uploaded 29 Apr 2025Source

Technical

  • DocumentPlan_RBP_ Ashwa Vishwa Builders_240702_155329.pdf · uploaded 2 Jul 2024Source
  • DocumentPlan_RBP_ Ashwa Vishwa Builders_240702_155329.pdf · uploaded 2 Jul 2024Source
  • Other – TechnicalDeclaration of Non Registration Standalone Project.pdf · uploaded 8 Jan 2025Source
  • Other – TechnicalClarification on email from authority.pdf · uploaded 29 Apr 2025Source
  • Other – Technicalrera patra.pdf · uploaded 29 Apr 2025Source
  • Other – TechnicalRERA PATRA EMAIL.pdf · uploaded 29 Apr 2025Source
  • Other – TechnicalCC Email.pdf · uploaded 29 Apr 2025Source

Technical (Architect)

  • DocumentForm 1 - Architect.pdf · uploaded 25 Dec 2024Source

Technical (Engineer)

  • DocumentForm 2 - Engineer.pdf · uploaded 9 Jan 2025Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel Gut No 630/1, Plot No (43+44)

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK16 units in all
Address
Gut No 630/1, Plot No (43+44), Kasarwadi Road, Barshi - 413401, Kasarwadi Road, BarshiPIN 413401
Village
Barshi (M Cl), Barshi taluka
Land area for this project
336 sq m (3,617 sq ft)
Permissible built-up area
737 sq m (7,930 sq ft)
Sanctioned built-up area
737 sq m (7,930 sq ft)
Recreational open space
0 sq m (0 sq ft)
Designated bank account
86
Developed in phases
No

Survey, CTS, gat or plot numbers

Gut No 630/1Plot No (43+44)

Land as published on MahaRERA's project page

Gut No 630/1, Plot No (43+44), Kasarwadi Road, Barshi - 413401

Boundaries

North
Plot
South
Plot
East
Road
West
Road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking16 units

0 of 16 units booked (0%), as the promoter reported to MahaRERA

1BHK · 16 units
TypeCarpet areaUnitsBooked
1BHK37.16 sq m · 400 sq ft160

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectMahesh Nandekar—
Chartered accountantV N KAMBALE AND CO CA Vaibhav Kambale—
EngineerMahesh Nandekar—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Barshi

All 26 projects in Barshi · Compare Samruddhi Apartment with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology