RERA projects in Solapur
543 projects under 553 MahaRERA registrations across 36 localities, registered 2017–2026. 12% have a completion date extended beyond the one promised.
543RERA projectsin 36 localities
553Registrationssome projects hold several
162Completion still due330 past their completion date
24 monthsMedian extension beyond promised date12% of registrations extended
29Regulatory caseson 29 projects
65Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 127 |
| 2018 | 25 |
| 2019 | 34 |
| 2020 | 37 |
| 2021 | 59 |
| 2022 | 59 |
| 2023 | 60 |
| 2024 | 36 |
| 2025 | 41 |
| 2026 | 14 |
Localities in Solapur
By number of registered projects. Talukas and localities as MahaRERA names them.
Solapur (M Corp.)328 projectsSolapur North38 projectsPandharpur29 projectsIsbavi23 projectsBarshi21 projectsBarshi10 projectsPandharpur7 projectsTembhurni7 projectsBarshi (M Cl)6 projectsKarmala (Rural)6 projectsSangole (M Cl)6 projectsWakhari5 projects
All 36 localities
- Solapur (M Corp.)328
- Solapur North38
- Pandharpur29
- Isbavi23
- Barshi21
- Barshi10
- Pandharpur7
- Tembhurni7
- Barshi (M Cl)6
- Karmala (Rural)6
- Sangole (M Cl)6
- Wakhari5
- Kurdu2
- Majrewadi2
- Malshiras2
- Mohol2
- Solapur South2
- Takli2
- Akkalkot (M Cl)1
- Akkalkot (Rural)1
- Boramani1
- Indiranagar (N.V.)1
- Jeur1
- Kandar1
- Karmala (Mci)1
- Kasbe Solapur1
- Kasegaon1
- Kurduwadi1
- Madha1
- Mangalvedhe (M Cl)1
- Modnimb1
- Neharu Nagar1
- Sangole1
- Vairag1
- Velapur1
- Wangi1
Projects in Solapur
543 projects registered with MahaRERA in this district and the places within it.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Martand EnclaveRajmudra Buildcon | PR1321012601776 | 3 Sep 2026 | 31 May 2028 | — | Not yet due | 0 |
| Aarambha ResidencyAarambha Residency | PR1320002601702 | 31 Aug 2026 | 31 Jul 2029 | — | Not yet due | 0 |
| Hexa-Vip PrimeHexaforce Construction LLP | PC1320002601589 | 19 Aug 2026 | 31 Dec 2030 | — | Not yet due | 0 |
| Star AveneuShri Samarth Associates | PM1320002601362 | 30 Jul 2026 | 30 Dec 2030 | — | Not yet due | 0 |
| Harisamarth ResidencyShri Samarth Associates | PM1320002600750 | 12 Jun 2026 | 28 Dec 2028 | — | Not yet due | 0 |
| Shinde ArcadeShinde And Kulkarni Associates | PM1320002600690 | 8 Jun 2026 | 31 Dec 2030 | — | Not yet due | 0 |
| Flora ParkImage Space Incorporated | PM1320002600662 | 4 Jun 2026 | 30 May 2032 | — | Not yet due | 0 |
| Royal Imperial TowerRoyal Buildcon & Associates | PR1320002600605 | 1 Jun 2026 | 30 Apr 2029 | — | Not yet due | 0 |
| Royal Residency Building No 4Shubhankar Developers | PR1320002600339 | 5 May 2026 | 31 Dec 2027 | — | Not yet due | 0 |
| Blossom ParkA J Buildcon | PM1320002502519 | 26 Feb 2026 | 31 Mar 2029 | — | Not yet due | 0 |
| Rita EmpireSwaraj Builders and Developers | PR1320002502449 | 23 Feb 2026 | 31 Dec 2030 | — | Not yet due | 0 |
| Vijays The PrestigeGavasane And Khed Builders | P52600081091 | 5 Feb 2026 | 31 Aug 2029 | — | Not yet due | 0 |
| Golden SkylineSavalkar And Sontakale Group | PR1321012502057 | 12 Jan 2026 | 31 Mar 2029 | — | Not yet due | 0 |
| Tirupati HarishaTirupati Construction Pramoters And Developers | PR1320002501713 | 8 Dec 2025 | 31 Dec 2028 | — | Not yet due | 0 |
| Vijayraj VishvaAruna Realtors | PR1320002501716 | 8 Dec 2025 | 31 Dec 2032 | — | Not yet due | 0 |
| Dhanshree ParkKazi Builders | P52600081055 | 2 Dec 2025 | 31 Mar 2028 | — | Not yet due | 0 |
| Tirupati Puram IITirupati Construction Pramoters And Developers | PR1320002501514 | 19 Nov 2025 | 29 Dec 2030 | — | Not yet due | 0 |
| Sai Samarth ResidencyAtul Jagdish Deshpande | PR1320002501332 | 24 Oct 2025 | 21 Nov 2030 | — | Not yet due | 0 |
| Rakhi TowerShiva Construction | PR1320002501254 | 16 Oct 2025 | 31 Dec 2028 | — | Not yet due | 0 |
| Kandres Residency A5 BuildingKandre Developer | PM1320002501051 | 1 Oct 2025 | 31 Dec 2027 | — | Not yet due | 0 |
| Yarawa ResidencyYarawa Buildcon LLP | PR1320002501084 | 1 Oct 2025 | 31 Mar 2029 | — | Not yet due | 0 |
| Royal PragatiRoyal Buildcon & Associates | PR1320002500911 | 23 Sep 2025 | 31 Mar 2027 | — | Not yet due | 0 |
| Jijau ResidencyRachana Developers | PR1320002500779 | 15 Sep 2025 | 1 Sep 2029 | — | Not yet due | 0 |
| Mahanandi HeightsSneharika Vijayshree Developers | PR1320002500698 | 3 Sep 2025 | 31 Dec 2030 | — | Not yet due | 0 |
| Samarth PrasadJjrv Infra Private Limited | PM1320002500526 | 11 Aug 2025 | 1 Aug 2030 | — | Not yet due | 0 |
| Shrikhande PrideB. S. L. Developers | P52600080909 | 11 Aug 2025 | 31 Dec 2027 | — | Not yet due | 0 |
| Vijayraj SamruddhiOm Realtors | P52600080895 | 1 Aug 2025 | 30 Apr 2030 | — | Not yet due | 0 |
| Mahesh ComplexShri Chaitanya Adhyatmik Trust | PC1320002500410 | 29 Jul 2025 | 31 Mar 2030 | — | Not yet due | 0 |
| Anantkoti SkyvillaAnantkoti Buildcon | PM1320002500349 | 23 Jul 2025 | 1 Jun 2029 | — | Not yet due | 0 |
| Manmeet MandarSolapur Infracons Private Limited | PR1320002500351 | 23 Jul 2025 | 31 Mar 2030 | — | Not yet due | 0 |
| Deepgiri HeightsSachin Purushottam Kulkarni | P52600080850 | 21 Jul 2025 | 31 Dec 2027 | — | Not yet due | 0 |
| Mithila Golden HeightsAim Properties | P52600080754 | 3 Jul 2025 | 31 Dec 2027 | — | Not yet due | 0 |
| Godavari HeightsGayatri Developers | P52600080728 | 30 Jun 2025 | 31 Dec 2026 | — | Not yet due | 0 |
| Raghuraj PrideVasturaj Builders And Developers | P52600080721 | 27 Jun 2025 | 31 Aug 2027 | — | Not yet due | 0 |
| Shantais ParadiseShri Samarth Construction | P52600080531 | 16 Jun 2025 | 31 Dec 2027 | — | Not yet due | 0 |
| SnehsrusthiGayatri Developers | P52600080539 | 16 Jun 2025 | 31 Dec 2026 | — | Not yet due | 0 |
| Kimaya Swapanapurti Phase 2Alacrity Constructions Pvt Ltd | P52600080497 | 11 Jun 2025 | 31 Dec 2030 | — | Not yet due | 0 |
| Mahavir HeightsArihant Venkateshwara Infra | P52600080499 | 11 Jun 2025 | 31 Dec 2027 | — | Not yet due | 0 |
| Samruddhi ApartmentAshwa Vishwa Builders Private Limited | P52600080239 | 13 May 2025 | 30 Jun 2026 | — | Promised date passed | 0 |
| Skyline SpringsSkyline builders & Developers | P52600080202 | 6 May 2025 | 1 Jan 2027 | — | Not yet due | 0 |
| Shivyogi ResidencyMohan Hiromal Sachdev | P52600080032 | 18 Apr 2025 | 31 Dec 2028 | — | Not yet due | 0 |
| Kimaya SwapanashrusthiKimaya Constructions Pvt Ltd | P52600079814 | 27 Mar 2025 | 31 Mar 2030 | — | Not yet due | 0 |
| Unique ResidencyUnique Developers | P52600079735 | 24 Mar 2025 | 31 Dec 2028 | — | Not yet due | 0 |
| Gulmohar ResidencyGulmohar Residency | P52600079681 | 20 Mar 2025 | 31 Dec 2028 | — | Not yet due | 0 |
| Madhusudan HeightsSuyash Developers | P52600079644 | 17 Mar 2025 | 31 Dec 2027 | — | Not yet due | 0 |
| Maner ComplexJahir Jamal Maner | P52600079428 | 6 Mar 2025 | 31 Dec 2030 | — | Not yet due | 0 |
| Dwarkadhish EnclaveVaishnavi Construction | P52600079368 | 3 Mar 2025 | 31 Dec 2026 | — | Not yet due | 0 |
| Shri Pralhad Smurti ResidencyVijayratna Developers | P52600079243 | 18 Feb 2025 | 31 Dec 2026 | — | Not yet due | 0 |
| K-S BougainvilleaKaranje-Surana Constructions Pvt. Ltd. | P52600079195 | 14 Feb 2025 | 31 Dec 2029 | — | Not yet due | 0 |
| KrishnalayamDiddi Infracons | P52600079151 | 10 Feb 2025 | 31 Aug 2027 | — | Not yet due | 0 |
| Royal SynergyShree Jagdamb Developers | P52600079157 | 10 Feb 2025 | 31 Dec 2029 | — | Not yet due | 0 |
| Royal HeritageMahadev Iranna Akalwadi | P52600079058 | 3 Feb 2025 | 31 Mar 2027 | — | Not yet due | 0 |
| Lotus ApartmentLotus Apartment | P52600078904 | 20 Jan 2025 | 31 Mar 2025 | — | Promised date passed | 0 |
| Laxmi ResidencyLaxmikant Infra | P52600078797 | 13 Jan 2025 | 31 Dec 2027 | — | Not yet due | 0 |
| Radha Damodar SankulShashikant Marutirao Jiddimani | P52600078619 | 27 Dec 2024 | 30 Dec 2030 | — | Not yet due | 0 |
| Bahava ApartmentTauseef Jaweed Shaikh & Jaweed Gulam Shaikh | P52600078480 | 17 Dec 2024 | 31 Dec 2027 | — | Not yet due | 0 |
| Daksh ResidencyBhagyoday Builders | P52600078465 | 12 Dec 2024 | 31 Dec 2027 | — | Not yet due | 0 |
| Shivtej PlazaSomanath Jagnnath Nikam | P52600078451 | 12 Dec 2024 | 31 Dec 2026 | — | Not yet due | 0 |
| Paras Business ParkPriyadarshani Corporation | P52600077981 | 14 Nov 2024 | 30 Dec 2030 | — | Not yet due | 0 |
| Kaizen EmeraldSwapnil Nalin Kothadia | P52600077841 | 7 Nov 2024 | 31 Dec 2027 | — | Not yet due | 0 |
| Gawade HeightsSwati Ajitkumar Gawade | P52600077776 | 29 Oct 2024 | 31 Dec 2028 | — | Not yet due | 0 |
| B9 LifestyleDinesh Khushiram Agrawal | P52600077188 | 29 Jul 2024 | 31 Dec 2027 | — | Not yet due | 0 |
| Aakruti HeritageAakruti Developers | P52600076988 | 10 Jul 2024 | 1 Nov 2027 | — | Not yet due | 0 |
| Construction of 224 LIG Residential T/S on Land Bearing Survey No 25A/1 Pandharpur Dist SolapurPune Housing and Area Development Board Pune | P52600076940 | 9 Jul 2024 | 31 Dec 2032 | — | Not yet due | 0 |
| Vasant ViharV.a. Developers | P52600076930 | 9 Jul 2024 | 31 Mar 2027 | — | Not yet due | 0 |
| Infinity EnclaveInfinity Reality | P52600076866 | 3 Jul 2024 | 31 May 2027 | — | Not yet due | 0 |
| Somnath HeightsSandeep Shivrudra Mokashi | P52600076764 | 28 Jun 2024 | 31 Dec 2026 | — | Not yet due | 0 |
| Niyojit Shri Somvanshiya Sahastrarjun Kshatriya Samaj Mahalaxmi Grih Nirman SansthaAnukarati Homes Private Limited | P52600076701 | 21 Jun 2024 | 31 Dec 2026 | — | Not yet due | 0 |
| Flora KalpanaImage Space Incorporated | P52600076653 | 20 Jun 2024 | 30 Apr 2027 | — | Not yet due | 0 |
| Pushpakunj ParkManali Realty | P52600076604 | 18 Jun 2024 | 31 Dec 2028 | — | Not yet due | 0 |
| Construction of Composite Housing Scheme of 126 T/s EWS and 112 T/s LIGPune Housing and Area Development Board Pune | P52600056169 | 16 May 2024 | 31 Dec 2032 | — | Not yet due | 0 |
| Centre CourtMaheshwari Developers | P52600056113 | 11 May 2024 | 31 Mar 2028 | — | Not yet due | 0 |
| Green OneMohammed Jaweed Nasiruddin Lunje | P52600055842 | 23 Apr 2024 | 31 Mar 2025 | — | Promised date passed | 0 |
| Tirupati PuramTirupati Construction Pramoters And Developers | P52600055784 | 16 Apr 2024 | 4 Oct 2029 | — | Not yet due | 0 |
| AkshataKisan Constructions Pvt Ltd | P52600055591 | 4 Apr 2024 | 31 Mar 2026 | — | Promised date passed | 0 |
| Necklace PrideMukhtiyar Shahadat Maindargi | P52600055508 | 2 Apr 2024 | 31 Dec 2027 | — | Not yet due | 0 |
| Patel PlazaEhsan Construction | P52600055472 | 2 Apr 2024 | 31 Dec 2025 | — | Promised date passed | 0 |
| Samarth ResidencyAbhaykumar Malharao Edke | P52600055390 | 22 Mar 2024 | 31 Dec 2027 | — | Not yet due | 0 |
| Silver ParkV.a. Developers | P52600055447 | 22 Mar 2024 | 31 Dec 2026 | — | Not yet due | 0 |
| Nilayam HeightsSachin Purushottam Kulkarni | P52600055316 | 14 Mar 2024 | 31 Dec 2026 | — | Not yet due | 0 |
| Samruddhi HeightsPragati Associates | P52600055310 | 14 Mar 2024 | 30 Apr 2028 | — | Not yet due | 0 |
| Khushi HeritageKhushi Buildcon | P52600055164 | 4 Mar 2024 | 31 Aug 2026 | — | Promised date passed | 0 |
| Manmeet AbhilashaSolapur Multicons LLP | P52600055081 | 29 Feb 2024 | 31 Mar 2027 | — | Not yet due | 0 |
| Prajay HeightsJaykant Construction | P52600055040 | 26 Feb 2024 | 14 Mar 2027 | — | Not yet due | 0 |
| Adinath ApartmentArchit Developers | P52600054855 | 15 Feb 2024 | 31 Dec 2026 | — | Not yet due | 0 |
| Four SeasonsT6 Realty Pvt Ltd | P52600054726 | 6 Feb 2024 | 31 Dec 2025 | — | Promised date passed | 0 |
| Paras ParadiseAnantkoti Developers | P52600054638 | 2 Feb 2024 | 31 Mar 2027 | — | Not yet due | 0 |
| Sai IconBjr Contructions Private Limited | P52600054657 | 2 Feb 2024 | 31 Oct 2027 | — | Not yet due | 0 |
| Rushi RichMeghshyam Mallikarjun Yemul | P52600054282 | 15 Jan 2024 | 31 Dec 2027 | — | Not yet due | 0 |
| Tirumala ParadiseSachin Vitthal Ghanate | P52600054305 | 15 Jan 2024 | 31 Dec 2026 | — | Not yet due | 0 |
| Vivek HeightsAzam Ismail Saifan | P52600054030 | 19 Dec 2023 | 31 Dec 2026 | — | Not yet due | 0 |
| Kamtam Icon Wing BVishwa Developers | P52600053917 | 11 Dec 2023 | 31 Mar 2027 | — | Not yet due | 0 |
| Swami Samarth RegencyShri Swami Samarth Developers | P52600053627 | 21 Nov 2023 | 31 Dec 2026 | — | Not yet due | 0 |
| Platinum MallM/S Ganesh Ramchandra Apte | P52600053600 | 10 Nov 2023 | 31 Dec 2035 | — | Not yet due | 0 |
| Royal Residency Building No 2Shubhankar Developers | P52600053463 | 6 Nov 2023 | 31 Mar 2026 | — | Promised date passed | 0 |
| Suyog Shrushti Phase 2Suyog Developers | P52600053307 | 23 Oct 2023 | 15 Mar 2026 | — | Promised date passed | 0 |
| Padmawati RejencyGurappa Mallikarjun Kapse | P52600053139 | 17 Oct 2023 | 31 Mar 2027 | — | Not yet due | 0 |
| Shree Ekdant HeightsMahesh Mahantappa Hatte | P52600053183 | 17 Oct 2023 | 31 Dec 2025 | — | Promised date passed | 0 |
| Vishwa PrideShri Samarth Associates | P52600053132 | 16 Oct 2023 | 31 Dec 2026 | — | Not yet due | 0 |
| Aviraj HeightsVidhyadhar Mallikarjun Akkalwadi | P52600052766 | 22 Sep 2023 | 31 Dec 2027 | — | Not yet due | 0 |
Other districts
- Pune13,424 projects
- Thane7,170 projects
- Mumbai Suburban6,592 projects
- Raigarh5,728 projects
- Nashik4,171 projects
- Palghar3,084 projects
- Nagpur2,793 projects
- Aurangabad1,469 projects
- Mumbai City1,380 projects
- Satara1,181 projects
- Ratnagiri1,138 projects
- Kolhapur863 projects
Most active promoters
By projects registered here, as named on MahaRERA.
- Dhariwal And Chhoriya Buildcon Pvt Ltd7 projects
- Mohsin Haroon Shaikh6 projects
- Devendra Vasudeo Sangolkar5 projects
- Image Space Incorporated5 projects
- Tirupati Construction Promoters & Developers5 projects
- Ayyub Usman Motiwala4 projects
- Gayatri Developers4 projects
- Hanmantu Komarayya Bura4 projects
- Pandhe Infracons Pvt Ltd4 projects
- Shri R N Goli Developers4 projects
Data through8 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology