6 projects under 6 MahaRERA registrations, registered 2017–2024. 17% have a completion date extended beyond the one promised.

6RERA projects
6Registrations
4Completion still due2 past their completion date
47 monthsMedian extension beyond promised date17% of registrations extended
1Regulatory caseson 1 project
0Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20173
20180
20190
20201
20210
20220
20230
20242

Projects in Sangole (M Cl)

6 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Gawade HeightsSwati Ajitkumar GawadeP5260007777629 Oct 202431 Dec 2028—Not yet due0
Silver ParkV.a. DevelopersP5260005544722 Mar 202431 Dec 2026—Not yet due0
ShivalayaMillenium EnterprisesP5260002700710 Nov 202010 Feb 202331 Dec 2026Extended 46 mo0
Siddhivinayak HightsSai DevelopersP526000144995 Dec 201730 Jun 2018—Promised date passed0
Manjul PlazaAslam Babalal MujawarP5260001375325 Oct 201731 Dec 2026—Not yet due0
Dream CityFuture Housing CorporationP526000038736 Aug 201730 Dec 2021—Promised date passed1

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Aslam Babalal Mujawar1 project
  2. Future Housing Corporation1 project
  3. Millenium Enterprises1 project
  4. Sai Developers1 project
  5. Swati Ajitkumar Gawade1 project
  6. V.a. Developers1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology