Shivalaya

Certificate Signed

Sangole (M Cl), Solapur 413307 |Promoter: Millenium Enterprises

Residential / Group HousingRERAP52600027007
10 Nov 2020Registered with MahaRERA
10 Feb 2023Promised completion
31 Dec 2026Revised completionPushed back 3 years and 10 months
1Building
46Units registered23 booked (50%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Buildings
1
Unit types
1BHK, 2BHK, Shop46 units in all
Address
2922/6, Mangalwedha- Solapur Road, DegaonPIN 413307
Designated bank account
87
Developed in phases
No

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 3 years and 10 months

Registered
10 Nov 2020
Promised
10 Feb 2023
Revised
31 Dec 2026

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5260002700710 Nov 202010 Feb 202331 Dec 2026Millenium EnterprisesProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Building 1546

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

23 of 46 units booked (50%), as the promoter reported to MahaRERA

1BHK · 28 units2BHK · 8 unitsShop · 10 units
TypeCarpet areaUnitsBooked
1BHK42.72 sq m · 460 sq ft41
1BHK45.36 sq m · 488 sq ft40
1BHK46.2 sq m · 497 sq ft41
1BHK46.65 sq m · 502 sq ft43
1BHK46.77 sq m · 503 sq ft87
1BHK46.93 sq m · 505 sq ft44
2BHK63.5 sq m · 684 sq ft20
2BHK63.86 sq m · 687 sq ft21
Show all 15 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
2BHK65.21 sq m · 702 sq ft20
2BHK66.39 sq m · 715 sq ft21
Shop8.06 sq m · 87 sq ft21
Shop8.89 sq m · 96 sq ft21
Shop10.42 sq m · 112 sq ft21
Shop10.54 sq m · 113 sq ft21
Shop12.16 sq m · 131 sq ft21

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

2 documents held by Deedo, 111 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Finance

  • PAN CardCompany Pan Card.pdf · uploaded 4 Jul 2020Source

Legal

  • Legal Title reportTitle Search sangala_compressed (1)-1-3.pdf · uploaded 7 Nov 2020Source
  • Legal Title reportTitle Search sangala_compressed (1)-4-5.pdf · uploaded 7 Nov 2020Source
  • Declaration Form BForm B Ankush.pdf · uploaded 7 Nov 2020Source
  • Declaration Form BForm B Shubhangi.pdf · uploaded 7 Nov 2020Source
  • Declaration Form BForm B Vandana.pdf · uploaded 7 Nov 2020Source
Show all 113 documentsShow fewer documents

Legal

  • Declaration Form Bstamp.pdf · uploaded 30 Dec 2024Source
  • Declaration Form Bstamp.pdf · uploaded 21 Jan 2025Source

Migrated

  • 1 PAN CardCompany Pan Card.pdf · uploaded 4 Jul 2020Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement.pdf · uploaded 4 Jul 2020Source
  • 1 Details of encumbrancesShivalaya-Non-Encumrance.pdf · uploaded 6 Jul 2020Source
  • 1 Proforma of Allotment letterDraft Agreement for Sale.pdf · uploaded 6 Jul 2020Source
  • 1 Copy of Layout Approval (in case of layout)Layout Plan.PDF · uploaded 23 Jul 2020Source
  • 1 Building Plan Approval / NA Order for plotted developmentBuilding Plan.PDF · uploaded 23 Jul 2020Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 12 Aug 2020Source
  • 1 Copy of the legal title reportTitle Search sangala_compressed (1)-1-3.pdf · uploaded 7 Nov 2020Source
  • 2 Copy of the legal title reportTitle Search sangala_compressed (1)-4-5.pdf · uploaded 7 Nov 2020Source
  • 1 Declaration in FORM BForm B Ankush.pdf · uploaded 7 Nov 2020Source
  • 2 Declaration in FORM BForm B Shubhangi.pdf · uploaded 7 Nov 2020Source
  • 3 Declaration in FORM BForm B Vandana.pdf · uploaded 7 Nov 2020Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Signed form 3_compressed.pdf · uploaded 30 Jan 2021Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Rera certificate_compressed.pdf · uploaded 14 Aug 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Signed Form 5.pdf · uploaded 30 Jun 2022Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Engineer certificate 20-21.pdf · uploaded 8 Aug 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Engineer certificate 21-22.pdf · uploaded 8 Aug 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Engineer certificate 22-23.pdf · uploaded 8 Aug 2023Source
  • 1 Disclosure of sold/ booked inventorysold.pdf · uploaded 8 Aug 2023Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect certificate.pdf · uploaded 6 Sep 2023Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)RERA Engineer's certificate.pdf · uploaded 6 Sep 2023Source
  • 1 Disclosure of sold/ booked inventorysold inver 12-24.pdf · uploaded 5 Dec 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)2021-22.pdf · uploaded 5 Dec 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)2022-23.pdf · uploaded 5 Dec 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)FORM 2A 23-24.pdf · uploaded 5 Dec 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)2023-24.pdf · uploaded 5 Dec 2024Source
  • 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architech_Part10.pdf · uploaded 6 Dec 2024Source
  • 13 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architech_Part13.pdf · uploaded 6 Dec 2024Source
  • 12 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architech_Part12.pdf · uploaded 6 Dec 2024Source
  • 11 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architech_Part11.pdf · uploaded 6 Dec 2024Source
  • 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architech_Part9.pdf · uploaded 6 Dec 2024Source
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architech_Part8.pdf · uploaded 6 Dec 2024Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architech_Part7.pdf · uploaded 6 Dec 2024Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architech_Part6.pdf · uploaded 6 Dec 2024Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architech_Part5.pdf · uploaded 6 Dec 2024Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architech_Part4.pdf · uploaded 6 Dec 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architech_Part3.pdf · uploaded 6 Dec 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architech_Part2.pdf · uploaded 6 Dec 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architech_Part1.pdf · uploaded 6 Dec 2024Source
  • 10 CA Certificate on Project Cost & Fund withdrawal (Form 3)9 Q3-23 - converted.pdf · uploaded 6 Dec 2024Source
  • 14 CA Certificate on Project Cost & Fund withdrawal (Form 3)13 Q4-23 - converted.pdf · uploaded 6 Dec 2024Source
  • 13 CA Certificate on Project Cost & Fund withdrawal (Form 3)12 Q3-24 - converted.pdf · uploaded 6 Dec 2024Source
  • 12 CA Certificate on Project Cost & Fund withdrawal (Form 3)11 Q2-24 - converted.pdf · uploaded 6 Dec 2024Source
  • 11 CA Certificate on Project Cost & Fund withdrawal (Form 3)10 Q1- 24 - converted.pdf · uploaded 6 Dec 2024Source
  • 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)8 Q2-23 - converted.pdf · uploaded 6 Dec 2024Source
  • 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)8 Q2-23 - converted.pdf · uploaded 6 Dec 2024Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)6 Q4-22 - converted.pdf · uploaded 6 Dec 2024Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)5 Q3-22 - converted.pdf · uploaded 6 Dec 2024Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)4 Q2-22 - converted.pdf · uploaded 6 Dec 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)3 Q1- 22 - converted.pdf · uploaded 6 Dec 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)2 Q4-21 - converted.pdf · uploaded 6 Dec 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)1 Q3-21 - converted.pdf · uploaded 6 Dec 2024Source
  • 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)7 Q1-23 - converted.pdf · uploaded 6 Dec 2024Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)7 Engineers Cert.pdf · uploaded 6 Dec 2024Source
  • 13 Engineer’s Certificate on Cost Incurred on Project (Form 2)13 Engineers Cert.pdf · uploaded 6 Dec 2024Source
  • 12 Engineer’s Certificate on Cost Incurred on Project (Form 2)12 Engineers Cert.pdf · uploaded 6 Dec 2024Source
  • 11 Engineer’s Certificate on Cost Incurred on Project (Form 2)11 Engineers Cert.pdf · uploaded 6 Dec 2024Source
  • 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)10 Engineers Cert.pdf · uploaded 6 Dec 2024Source
  • 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)9 Engineers Cert.pdf · uploaded 6 Dec 2024Source
  • 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)8 Engineers Cert.pdf · uploaded 6 Dec 2024Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)6 Engineers Cert.pdf · uploaded 6 Dec 2024Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)5 Engineers Cert.pdf · uploaded 6 Dec 2024Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)4 Engineers Cert.pdf · uploaded 6 Dec 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)3 Engineers Cert.pdf · uploaded 6 Dec 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)2 Engineers Cert.pdf · uploaded 6 Dec 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)1 Engineers Cert.pdf · uploaded 6 Dec 2024Source
  • 2 Declaration in FORM Bstamp.pdf · uploaded 30 Dec 2024Source
  • 14 Architect’s Certificate of Percentage of Completion of Work (Form 1)Arch 14.pdf · uploaded 30 Dec 2024Source
  • 14 Engineer’s Certificate on Cost Incurred on Project (Form 2)RERA_Engineer 14.pdf · uploaded 30 Dec 2024Source
  • 1 Declaration in FORM Bstamp.pdf · uploaded 21 Jan 2025Source
  • 1 Declaration about Commencement Certificatecc dec - converted.pdf · uploaded 21 Jan 2025Source

Technical

  • DocumentLayout Plan.PDF · uploaded 23 Jul 2020Source
  • DocumentBuilding Plan.PDF · uploaded 23 Jul 2020Source

Technical (Architect)

  • DocumentArchitect certificate.pdf · uploaded 6 Sep 2023Source
  • DocumentArchitech_Part1.pdf · uploaded 6 Dec 2024Source
  • DocumentArchitech_Part2.pdf · uploaded 6 Dec 2024Source
  • DocumentArchitech_Part3.pdf · uploaded 6 Dec 2024Source
  • DocumentArchitech_Part4.pdf · uploaded 6 Dec 2024Source
  • DocumentArchitech_Part5.pdf · uploaded 6 Dec 2024Source
  • DocumentArchitech_Part6.pdf · uploaded 6 Dec 2024Source
  • DocumentArchitech_Part7.pdf · uploaded 6 Dec 2024Source
  • DocumentArchitech_Part8.pdf · uploaded 6 Dec 2024Source
  • DocumentArchitech_Part9.pdf · uploaded 6 Dec 2024Source
  • DocumentArchitech_Part10.pdf · uploaded 6 Dec 2024Source
  • DocumentArchitech_Part11.pdf · uploaded 6 Dec 2024Source
  • DocumentArchitech_Part12.pdf · uploaded 6 Dec 2024Source
  • DocumentArchitech_Part13.pdf · uploaded 6 Dec 2024Source
  • DocumentArch 14.pdf · uploaded 30 Dec 2024Source

Technical (Engineer)

  • DocumentRERA Engineer's certificate.pdf · uploaded 6 Sep 2023Source
  • Document1 Engineers Cert.pdf · uploaded 6 Dec 2024Source
  • Document2 Engineers Cert.pdf · uploaded 6 Dec 2024Source
  • Document3 Engineers Cert.pdf · uploaded 6 Dec 2024Source
  • Document4 Engineers Cert.pdf · uploaded 6 Dec 2024Source
  • Document5 Engineers Cert.pdf · uploaded 6 Dec 2024Source
  • Document6 Engineers Cert.pdf · uploaded 6 Dec 2024Source
  • Document7 Engineers Cert.pdf · uploaded 6 Dec 2024Source
  • Document8 Engineers Cert.pdf · uploaded 6 Dec 2024Source
  • Document9 Engineers Cert.pdf · uploaded 6 Dec 2024Source
  • Document10 Engineers Cert.pdf · uploaded 6 Dec 2024Source
  • Document11 Engineers Cert.pdf · uploaded 6 Dec 2024Source
  • Document12 Engineers Cert.pdf · uploaded 6 Dec 2024Source
  • Document13 Engineers Cert.pdf · uploaded 6 Dec 2024Source
  • DocumentRERA_Engineer 14.pdf · uploaded 30 Dec 2024Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Sangole (M Cl), Sangole taluka

Survey, CTS, gat or plot numbers

2922/6

Boundaries

North
Bansode Plot
South
Deshpande Plot
East
Road
West
Kasabe Plot

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectSachin Waingade—
Chartered accountantCA Aditya Patil—
EngineerMilind Ankalgi—

Source: MahaRERA project page. Contact details are not shown.