10 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects3
Registrations3
Completion still due12 past their date
Median extension4 months33% of registrations extended
Regulatory cases0none on MahaRERA's lists

10 in 10 registrations run late here

3 MahaRERA registrations in Barshi (M Cl)

1 extended, not yet due2 past even the latest date

Extended registrations moved their completion date by a median of 4 months.

Projects in Barshi (M Cl)

3 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Royal Residency Building No 4Shubhankar DevelopersDue Apr 2028, extended 4 mo——
Royal ResidencyShubhankar DevelopersCompleted—71%
Shivsmruti ResidencyBhairavnath Developers5 yrs 4 mo late——
Barshi (M Cl) market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Nearby: other municipal areas in Barshi

Most active promoters

  1. Shubhankar Developers2 projects
  2. Bhairavnath Developers1 project

Barshi (M Cl), in questions

How many projects in Barshi (M Cl) run late?

10 in 10 MahaRERA registrations (3 of 3): their completion date was extended or has passed, data through 21 Oct 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Barshi (M Cl) by Deedo. Medians on fewer than 3 deeds are not shown.

Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology