RERA projects in Barshi (M Cl)
6 projects under 6 MahaRERA registrations, registered 2017–2026. 17% have a completion date extended beyond the one promised.
6RERA projects
6Registrations
1Completion still due5 past their completion date
48 monthsMedian extension beyond promised date17% of registrations extended
0Regulatory casesnone on MahaRERA's lists
1Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 1 |
| 2018 | 2 |
| 2019 | 0 |
| 2020 | 1 |
| 2021 | 0 |
| 2022 | 0 |
| 2023 | 0 |
| 2024 | 0 |
| 2025 | 1 |
| 2026 | 1 |
Projects in Barshi (M Cl)
6 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Royal Residency Building No 4Shubhankar Developers | PR1320002600339 | 5 May 2026 | 31 Dec 2027 | — | Not yet due | 0 |
| Samruddhi ApartmentAshwa Vishwa Builders Private Limited | P52600080239 | 13 May 2025 | 30 Jun 2026 | — | Promised date passed | 0 |
| Jagnnath Puram Phase IISahayog Developers | P52600027285 | 1 Dec 2020 | 30 Sep 2024 | — | Promised date passed | 0 |
| Royal ResidencyShubhankar Developers | P52600014907 | 11 Jan 2018 | 30 Dec 2022 | — | Promised date passed | 0 |
| Shivsmruti ResidencyBhairavnath Developers | P52600014884 | 9 Jan 2018 | 5 Jul 2021 | — | Promised date passed | 0 |
| TathastuTathastu Developers | P52600006211 | 14 Aug 2017 | 31 Dec 2018 | 30 Dec 2022 | Extended 48 mo | 0 |
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology