Skip to content

RERA projects in Solapur South

4 projects under 5 MahaRERA registrations, registered 2018–2022. None has an extended completion date on record.

Taluka
4RERA projects
5Registrationssome projects hold several
2Completion still due3 past their completion date
—Median extension beyond promised date0% of registrations extended
0Regulatory casesnone on MahaRERA's lists
881Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20182
20191
20200
20211
20221

Projects in Solapur South

4 projects registered with MahaRERA in this taluka and the places within it.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Nirmiti LandmarkNirmiti DevelopersP5260003280229 Jan 202211 Nov 202711 Nov 2027Not yet due0
Galaxy 52Swapnil Suhas RautP5260003137023 Oct 202130 Dec 202530 Dec 2025Promised date passed0
Suyog ShrushtiSuyog DevelopersP5260002113210 Jun 20191 Mar 20201 Mar 2020Promised date passed0
Ray Nagar Housing ProjectVasant Vihar Realty Pvt LtdP52600017938, P5260001795627 Sep 201831 Dec 202731 Dec 2027Not yet due0

Other talukas in Solapur

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Nirmiti Developers1 project
  2. Suyog Developers1 project
  3. Swapnil Suhas Raut1 project
  4. Vasant Vihar Realty Pvt Ltd1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology