Deedo IDDL-WAR-WARDHA5 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects284in 63 localities
Registrations292some projects hold several
Completion still due46206 past their date
Median extension5 months17% of registrations extended
Regulatory cases13on 13 projects
5 in 10 registrations run late here
292 MahaRERA registrations in Wardha and the places within it
91 completed20 not yet due24 extended, not yet due117 past even the latest date40 no date on record
Extended registrations moved their completion date by a median of 5 months.
Projects in Wardha
284 projects registered with MahaRERA in this district and the places within it.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Vibhavari EnclaveMangesh Vinodrao Satpute | Due Jul 2030, extended 4 mo | — | — |
| Gajanan Leela 7Kapital Homes | Due Jul 2030, extended 4 mo | — | — |
| Keystone Elevate-Tower C1Keystone Communities LLP | Due Apr 2033, extended 4 mo | — | — |
| City CenterGungara Balaji Venture | Due Jul 2027, extended 4 mo | — | — |
| Dhp TownDhp Infraventures | Due Apr 2033, extended 4 mo | — | — |
| Dattadham Part 4Haribhau Wasudeorao Wazurkar | Due Jul 2028, extended 4 mo | — | — |
| Maa Vaishnavi Nagari 9- Wing IIINiklesh Deshmukh, Sangita Rithe, Priyanka Deshmukh, Vandana Deshmukh(Part. Maa Vaishnavi Buil.&Dev.) | Due Apr 2029, extended 4 mo | — | — |
| Keystone Elevate-Tower A2Keystone Communities LLP | Due Apr 2033, extended 4 mo | — | — |
| Keystone Elevate-CommercialKeystone Communities LLP | Due Apr 2033, extended 4 mo | — | — |
| Keystone Elevate-Tower B1Keystone Communities LLP | Due Apr 2033, extended 4 mo | — | — |
| Omkar NagarA. V. Infratech | Due Jul 2034, extended 4 mo | — | — |
| Akshardham Phase - 2Govindam Infra | Due Oct 2028, extended 4 mo | — | — |
| Keystone Elevate-Tower A1Keystone Communities LLP | Due Apr 2033, extended 4 mo | — | 3% |
| Ayodhya CityYogesh Laxmikant Gawande | Due Mar 2027, extended 2 yrs | — | — |
| Anand Sagar City - Part 7Mahajan Land Developers | 1 yr 11 mo late | — | — |
| Vidya NagriPramod Wamanrao Kolhe | Due Jul 2027, extended 4 mo | — | — |
| Armors NagarArmors Developers Private Limited | 11 mo late | — | — |
| Laxmi NagarPratik Anil Meghe | 2 yrs 8 mo late | — | — |
| Shree Gungara Balaji ParkShree Gungara Balaji Park | 8 mo late | — | — |
| Mauli ParkSnehal Bhaiyajji Pisudde | 7 mo late | — | — |
| Ayodhya City-Residential Layout Plan in Survey No-107/2Mahesh Shankarrao Gulhane | Due Mar 2027, extended 3 yrs | — | — |
| Matrubhumi NagarSachin Suryabhan Moon | Due Apr 2027, extended 4 mo | — | — |
| Vastuvishwa Apartments - Samta NagarSaju Anapara Joseph Verghese | 2 yrs late | — | — |
| Mauli parkVilas Narayanrao Neware | 2 yrs 3 mo late | — | — |
| Shree Krishna NagarArth Land Developers | 2 yrs 3 mo late | — | — |
Localities in Wardha
- Hinganghat25 projects
- Wardha (M Cl)22 projects
- Wardha15 projects
- Deoli (M Cl)14 projects
- Pipri (Ct)13 projects
- Sawangi (Meghe) (Ct)13 projects
- Umari (Meghe)13 projects
- Masala (Ct)12 projects
- Nalwadi10 projects
- Pavnar9 projects
- Seloo8 projects
- Sindi Turf Hindnagar (Ct)8 projects
All 63 localities
- Palakwadi (Wardha)6
- Seloo6
- Sindi Kh.5
- Borgaon (Meghe) (Ct)4
- Chichala4
- Inzapur4
- Pimpalgaon (534386)4
- Pimpalgaon (534463)4
- Sekapur4
- Sewagram4
- Sindi (M Cl)4
- Aalodi3
- Karla3
- Ajanti2
- Arvi2
- Bhiwapur (534083)2
- Deoli2
- Junona2
- Karanja2
- Kelzar2
- Nachangaon2
- Nagthana2
- Rimdoh2
- Satoda2
- Shahalangadi2
- Anji (Mothi)1
- Barbadi1
- Bhaipur1
- Bori1
- Chandani (533686)1
- Chitoda1
- Daroda1
- Dattapur (534082)1
- Dhochi1
- Hamdapur1
- Hinganghat (M Cl)1
- Hingni1
- Jamb1
- Morangana1
- Nandgaon (534355)1
- Palasgaon1
- Pulgaon (M Cl)1
- Renkapur1
- Samudrapur1
- Samudrapur1
- Sawali Kh1
- Seldoh1
- Selukate1
- Talegaon1
- Talegaon (534121)1
- Waigaon (Ni)1
Other districts
Most active promoters
- Mahesh Shankarrao Gulhane10 projects
- Krishnagiri Developers7 projects
- Mahajan Land Developers6 projects
- Sanjay Tejmal Ostwal6 projects
- Atul Namdeo Wandile5 projects
- Keystone Communities Llp5 projects
- Vastu Land Developers & Builders5 projects
- Haribhau Wasudeorao Wazurkar4 projects
- Shourya Builders And Developers4 projects
- Ashish Sharadkumar Tiwari3 projects
Wardha, in questions
How many projects in Wardha run late?
5 in 10 MahaRERA registrations (141 of 292): their completion date was extended or has passed, data through 21 Oct 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Wardha by Deedo. Medians on fewer than 3 deeds are not shown.
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology