RERA projects in Samudrapur
4 projects under 4 MahaRERA registrations, registered 2022–2023. 33% have a completion date extended beyond the one promised.
Taluka
4RERA projects
4Registrations
1Completion still due2 past their completion date
12 monthsMedian extension beyond promised date33% of registrations extended
0Regulatory casesnone on MahaRERA's lists
0Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2022 | 2 |
| 2023 | 1 |
Projects in Samudrapur
4 projects registered with MahaRERA in this taluka and the places within it.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Mauli ParkRupali Pravin Ghurde | P50400051014 | 19 May 2023 | 30 Apr 2027 | — | Not yet due | 0 |
| Jaihind NagarBabarao Jambhulkar And Uttara Jambhulkar | P50400034880 | 28 Apr 2022 | 31 Mar 2024 | 30 Mar 2025 | Extended 12 mo | 0 |
| Shrikrupa ComplexRajesh Rameshraw Dagwar | P50400033214 | 9 Feb 2022 | 31 Mar 2023 | — | Promised date passed | 0 |
| Daimond Galaxy Complex | P50400017658 | — | — | — | — | 0 |
Other talukas in Wardha
Most active promoters
By projects registered here, as named on MahaRERA.
- Babarao Jambhulkar And Uttara Jambhulkar1 project
- Rajesh Rameshraw Dagwar1 project
- Rupali Pravin Ghurde1 project
Data through8 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology