Hinganghat, Wardha
Deedo IDDL-WAR-HINGANGHAT8% of MahaRERA registrations here have pushed their completion date back.
RERA projects45
Registrations46some projects hold several
Completion still due237 past their date
Median extension12 months8% of registrations extended
Regulatory cases0none on MahaRERA's lists
6 in 10 registrations run late here
46 MahaRERA registrations in Hinganghat and the places within it
10 completed1 not yet due1 extended, not yet due27 past even the latest date7 no date on record
Extended registrations moved their completion date by a median of 12 months.
Projects in Hinganghat
45 projects registered with MahaRERA in this taluka and the places within it.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Subhash ResidencyAbhijit Subhash Bidkar and Amol Subhash Bidkar | Due Mar 2027 | — | — |
| Omkar NagarA. V. Infratech | Due Jul 2034, extended 4 mo | — | — |
| Sai NagarNiraj Lohakare, Sanjay Sharma, Sunil Langade, Vikram Taori And Pradeep Nahale | Completed | — | — |
| Armors NagarArmors Developers Private Limited | 10 mo late | — | 0% |
| Kesariya ParkRakesh Mohanrao Made | 6 mo late | — | — |
| Prashant Ingale LayoutPrashant Wasudeorao Ingale | Completed | — | — |
| Baramati CityMaa Rani Hospitality and Infra | 2 yrs 7 mo late | — | — |
| Shiv Nagari Motghare LayoutPandurang Kisan Motghare | 1 yr 6 mo late | — | — |
| Baramati CityMaa Rani Hospitality and Infra | 2 yrs 7 mo late | — | — |
| Vaishnodevi NagariSunanda Prabhakar Durbude | 1 yr 6 mo late | — | — |
| Ganesh Nagar - 2Sanjay Tejmal Ostwal | 1 yr 6 mo late | — | — |
| baramati cityMahesh Shankarrao Gulhane | 2 yrs 7 mo late | — | — |
| Baramati CityMahesh Shankarrao Gulhane | 2 yrs 7 mo late | — | — |
| Baramati CityMahesh Shankarrao Gulhane | 2 yrs 7 mo late | — | — |
| Baramati CityAtul Namdeo Wandile | 2 yrs 7 mo late | — | — |
| Baramati CityAtul Namdeo Wandile | 2 yrs 7 mo late | — | — |
| Ishwar NagarMahesh Batra & 2 Others | 1 yr 7 mo late | — | — |
| Ishwar NagarKeshar Infra | 1 yr 7 mo late | — | — |
| Vithai NagriPurushottam Wamanrao Bhaimare | Completed | — | — |
| Maa Rani Nagari Part - 2Parag Bhausaheb Mudey | Completed | — | — |
| Mauli parkVilas Narayanrao Neware | 2 yrs 2 mo late | — | — |
| Maa Rani Nagari Part - 1Sharad Ramaji Vihirkar | 3 yrs 7 mo late | — | — |
| Nano ParkSunil Harpaldas Mihani | 4 yrs 1 mo late | — | — |
| Sukhmani NagarSukhmani Developers And Builders | 2 yrs 7 mo late | — | — |
| Mauli ParkSanjay Tejmal Ostwal | 3 yrs 8 mo late | — | — |
Nearby: other talukas in Wardha
Most active promoters
- Atul Namdeo Wandile5 projects
- Sanjay Tejmal Ostwal4 projects
- Krishnagiri Developers3 projects
- Mahesh Shankarrao Gulhane3 projects
- Maa Rani Hospitality and Infra2 projects
- Abhijit Subhash Bidkar and Amol Subhash Bidkar1 project
- Armors Developers Private Limited1 project
- Ashish Ganesh Akare And Atul Namdev Wandile1 project
- A. V. Infratech1 project
- Dharmaraj Domaji Rewatkar1 project
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology