RERA projects in Seloo
25 projects under 25 MahaRERA registrations, registered 2018–2023. 24% have a completion date extended beyond the one promised.
25RERA projects
25Registrations
4Completion still due13 past their completion date, 6 marked completed
28 monthsMedian extension beyond promised date24% of registrations extended
0Regulatory casesnone on MahaRERA's lists
0Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2018 | 2 |
| 2019 | 0 |
| 2020 | 6 |
| 2021 | 3 |
| 2022 | 3 |
| 2023 | 3 |
Projects in Seloo
25 projects registered with MahaRERA in this taluka and the places within it.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Vidya NagriPramod Wamanrao Kolhe | P50400052189 | 27 Jul 2023 | 31 Mar 2027 | — | Not yet due | 0 |
| Mauli ParkSunil Purushottam Dhoble | P50400049727 | 22 Feb 2023 | 30 Jun 2024 | — | Promised date passed | 0 |
| Raavee Ki NagariRajesh Motilal Jaiswal | P50400048698 | 12 Jan 2023 | 31 Dec 2025 | — | Completed | 0 |
| Sakhuaai DevelopersAjay P. Deshmukh, Rupali J. Khodake | P50400046793 | 10 Sep 2022 | 31 Dec 2023 | 30 Dec 2024 | Completed | 0 |
| Matrubhumi NagarSachin Suryabhan Moon | P50400046203 | 20 Jun 2022 | 31 Dec 2026 | — | Not yet due | 0 |
| Ganesh Nagar-2Sanjay Tejmal Ostwal | P50400045711 | 6 Jun 2022 | 30 Apr 2025 | — | Promised date passed | 0 |
| Ganesh NagarSanjay Tejmal Ostwal | P50400031857 | 22 Nov 2021 | 31 Aug 2023 | — | Completed | 0 |
| Kirange NagariVishvanath Rama Kirange | P50400030896 | 20 Sep 2021 | 31 Dec 2022 | — | Completed | 0 |
| Shree Krishna NagarArth Land Developers | P50400030845 | 20 Sep 2021 | 15 Aug 2024 | — | Promised date passed | 0 |
| Shree Hariram NagarSaiparth Group | P50400025705 | 3 Jul 2020 | 30 Dec 2021 | — | Completed | 0 |
| Shiv Sandesh ColonyShiv Sandesh Colony | P50400025394 | 21 May 2020 | 30 Sep 2022 | — | Completed | 0 |
| Mauli Park - 3Shrikant Vasant Korde | P50400025156 | 19 Mar 2020 | 30 Mar 2022 | — | Promised date passed | 0 |
| Ambika 1Ashok Nathuram Joshi | P50400024198 | 27 Jan 2020 | 30 Dec 2022 | 12 Sep 2023 | Extended 9 mo | 0 |
| Ambika2Ramesh Badriprsad Agrawal | P50400024199 | 27 Jan 2020 | 30 Dec 2022 | — | Promised date passed | 0 |
| Ladole LayoutAishwarya S Ladole and Viraj S Ladole | P50400023916 | 14 Jan 2020 | 30 Oct 2022 | 31 Dec 2027 | Extended 62 mo | 0 |
| Sai NagariSai Infratech | P50400017676 | 4 Sep 2018 | 30 Sep 2020 | — | Promised date passed | 0 |
| Midas Natures NestMidas Dream Built Pvt Ltd | P50400015692 | 16 Mar 2018 | 30 Jun 2023 | 31 Mar 2027 | Extended 45 mo | 0 |
| Dehu Aalandi Park | P50400045563 | — | — | — | — | 0 |
| Kesariya Nagari | P50400034599 | — | — | — | — | 0 |
| Kings Village | P50400006520 | — | — | — | — | 0 |
| Mauli Town | P50400025524 | — | — | — | — | 0 |
| Sai Nagar | P50400025429 | — | — | — | — | 0 |
| Shree Gungara Balaji Park | P50400031658 | — | — | — | — | 0 |
| Shree Hari Nagar | P50400027032 | — | — | — | — | 0 |
| Shriram Nagar | P50400025479 | — | — | — | — | 0 |
Other talukas in Wardha
- Wardha161 projects
- Hinganghat45 projects
- Deoli19 projects
- Arvi5 projects
- Samudrapur4 projects
Most active promoters
By projects registered here, as named on MahaRERA.
- Sanjay Tejmal Ostwal2 projects
- Aishwarya S Ladole and Viraj S Ladole1 project
- Ajay P. Deshmukh, Rupali J. Khodake1 project
- Arth Land Developers1 project
- Ashok Nathuram Joshi1 project
- Midas Dream Built Pvt Ltd1 project
- Pramod Wamanrao Kolhe1 project
- Rajesh Motilal Jaiswal1 project
- Ramesh Badriprsad Agrawal1 project
- Sachin Suryabhan Moon1 project
Data through8 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology