Its promised completion date, Aug 2024, has passed and MahaRERA does not show it completed; no MahaRERA orders on record.

Seloo, Wardha 442104 · Promoter: Arth Land Developers

Delivery2 yrs 2 mo past duePromised Aug 2024 · no extension on record · not shown completedRegulatoryNo ordersNot in any MahaRERA list or order Deedo has read
Shree Krishna Nagar project report cardPDF: delivery, regulatory orders, people on record, every tower and the registered deals — for your bank or lawyerSee what's inside · from ₹1,499

Its promised completion date, Aug 2024, has passed and MahaRERA does not show it completed

  • This projectRegistered 20 Sep 2021, completion promised 15 Aug 2024, and still not shown completed today.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.
Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP50400030845
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5040003084520 Sep 202115 Aug 2024—Arth Land DevelopersProject page
Documents15

2 documents held by Deedo, 13 filings listed on MahaRERA's project page

Registration certificate

Other

Document library

  • Copy of the legal title reportsearch report arth developer.pdf · uploaded 4 Sep 2021Source
  • Details of encumbrancesnon encumberance certificate.pdf · uploaded 4 Sep 2021Source
  • Copy of Layout Approval (in case of layout)MAP.pdf · uploaded 4 Sep 2021Source
  • Building Plan Approval / NA Order for plotted developmentNA.PDF · uploaded 4 Sep 2021Source
  • Proforma of Allotment letterAGREEMENT AND ALLOTMENT LETTER.pdf · uploaded 4 Sep 2021Source
  • Commencement Certificates / NA Order for plotted developmentNA.PDF · uploaded 4 Sep 2021Source
Show all 15 documentsShow fewer documents

Document library

  • Declaration in FORM BFORM B.PDF · uploaded 4 Sep 2021Source
  • Declaration about Commencement CertificateForm D.pdf · uploaded 6 Sep 2021Source

Promoter documents

  • Legal Title reportsearch report arth developer.pdf · uploaded 4 Sep 2021Source
  • Declaration Form BFORM B.PDF · uploaded 4 Sep 2021Source

Technical documents

  • Layout ApprovalMAP.pdfSource
  • NA Order for Plotted DevelopmentNA.PDFSource

Proforma allotment letter

  • Proforma allotment letterAGREEMENT AND ALLOTMENT LETTER.pdfSource

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvals382

As registered with MahaRERA and published on its project page

Project type
Plotted
Status on MahaRERA
Lapsed
Address
382, Warda Road, SelooPIN 442104
Village
Seloo, Seloo taluka
Land area for this project
7,595 sq m (81,749 sq ft)
Permissible built-up area
0 sq m (0 sq ft)
Sanctioned built-up area
0 sq m (0 sq ft)
Recreational open space
1,702 sq m (18,321 sq ft)
Designated bank account
Hdfc Bank
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Survey, CTS, gat or plot numbers

382

Land as published on MahaRERA's project page

382

Boundaries

North
Survey No 376
South
Survey No 381
East
Survey No 383
West
Survey No 380

Source: registration certificates and MahaRERA's project page, as stated there.

Construction progress2 buildings and areas

Work completed, as the promoter reported it to MahaRERA (Form 1)

Building

  • ExcavationNot applicable
  • Basement (if any)Not applicable
  • Podiums (if any)Not applicable
  • PlinthNot applicable
  • Stilt FloorNot applicable
  • Slabs of Super StructureNot applicable
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
  • Sanitary Fittings within the flats / premisesNot applicable
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Common areas and amenities

  • Internal Roads & FootpathsWork START20%
  • Water SupplyNEW LAYOUT0%
  • Sewerage (Chamber, Lines, Septic Tank , STP)NEW LAYOUT0%
  • Storm Water DrainsNEW LAYOUT0%
  • Landscaping & Tree PlantingNot applicable
  • Street LightingNEW LAYOUT0%
Show all 15 activitiesShow fewer activities
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingNot applicable
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Electrical meter room, sub-station, receiving stationNot applicable
  • Aggregate area of recreational Open SpaceNEW LAYOUT0%
  • Open ParkingNot applicable

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
Architectniranjan kande—
Chartered accountantamol shegaonkar—
Engineerniranjan kande—

Source: MahaRERA project page. Contact details are not shown.