RERA projects in Bori

1 project under 1 MahaRERA registration, registered 2018–2018. 100% have a completion date extended beyond the one promised.

Locality
1RERA projects
1Registrations
1Completion still due0 past their completion date
45 monthsMedian extension beyond promised date100% of registrations extended
0Regulatory casesnone on MahaRERA's lists
0Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20181

Projects in Bori

1 project registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Midas Natures NestMidas Dream Built Pvt LtdP5040001569216 Mar 201830 Jun 202331 Mar 2027Extended 45 mo0

Other localities in Seloo

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Midas Dream Built Pvt Ltd1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology