RERA projects in Seldoh
1 project under 1 MahaRERA registration, registered 2020–2020. 100% have a completion date extended beyond the one promised.
Locality
1RERA projects
1Registrations
1Completion still due0 past their completion date
62 monthsMedian extension beyond promised date100% of registrations extended
0Regulatory casesnone on MahaRERA's lists
0Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2020 | 1 |
Projects in Seldoh
1 project registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Ladole LayoutAishwarya S Ladole and Viraj S Ladole | P50400023916 | 14 Jan 2020 | 30 Oct 2022 | 31 Dec 2027 | Extended 62 mo | 0 |
Other localities in Seloo
Most active promoters
By projects registered here, as named on MahaRERA.
- Aishwarya S Ladole and Viraj S Ladole1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology