RERA projects in Sindi (M Cl)
4 projects under 4 MahaRERA registrations, registered 2020–2020. 25% have a completion date extended beyond the one promised.
Locality
4RERA projects
4Registrations
0Completion still due4 past their completion date, 2 marked completed
8 monthsMedian extension beyond promised date25% of registrations extended
0Regulatory casesnone on MahaRERA's lists
0Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2020 | 4 |
Projects in Sindi (M Cl)
4 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Shree Hariram NagarSaiparth Group | P50400025705 | 3 Jul 2020 | 30 Dec 2021 | — | Completed | 0 |
| Shiv Sandesh ColonyShiv Sandesh Colony | P50400025394 | 21 May 2020 | 30 Sep 2022 | — | Completed | 0 |
| Ambika 1Ashok Nathuram Joshi | P50400024198 | 27 Jan 2020 | 30 Dec 2022 | 12 Sep 2023 | Extended 9 mo | 0 |
| Ambika2Ramesh Badriprsad Agrawal | P50400024199 | 27 Jan 2020 | 30 Dec 2022 | — | Promised date passed | 0 |
Other localities in Seloo
Most active promoters
By projects registered here, as named on MahaRERA.
- Ashok Nathuram Joshi1 project
- Ramesh Badriprsad Agrawal1 project
- Saiparth Group1 project
- Shiv Sandesh Colony1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology