RERA projects in Deoli (M Cl)
14 projects under 15 MahaRERA registrations, registered 2019–2025. None has an extended completion date on record.
Locality
14RERA projects
15Registrationssome projects hold several
3Completion still due12 past their completion date, 6 marked completed
—Median extension beyond promised date0% of registrations extended
0Regulatory casesnone on MahaRERA's lists
3Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2019 | 1 |
| 2020 | 4 |
| 2021 | 5 |
| 2022 | 0 |
| 2023 | 2 |
| 2024 | 1 |
| 2025 | 2 |
Projects in Deoli (M Cl)
14 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Vaibhav Nagar 2Vaibhav Ravi Kashikar | PP1340002501185 | 13 Oct 2025 | 31 Mar 2027 | — | Not yet due | 0 |
| Vaibhav Nagar - 1Ashish Sharadkumar Tiwari | PP1340002501102 | 6 Oct 2025 | 31 Mar 2027 | — | Not yet due | 0 |
| Mahesh NagarAshish S. Tiwari And Archana M. Taori | P50400056379 | 31 May 2024 | 31 Mar 2025 | — | Completed | 0 |
| Ganesh Nagar Part - 4Pratima Diliprao Shankarpale | P50400049993 | 6 Mar 2023 | 31 Mar 2025 | — | Promised date passed | 0 |
| Mauli ParkSnehal Bhaiyajji Pisudde | P50400049903 | 6 Mar 2023 | 30 Apr 2026 | — | Promised date passed | 0 |
| Ganesh Nagar Part 2Manish Sharadkumar Tiwari | P50400032052 | 3 Dec 2021 | 31 Dec 2023 | — | Completed | 0 |
| Mahalaxmi TownVastu Land Developers And Builders | P50400031865 | 22 Nov 2021 | 31 Dec 2024 | — | Completed | 0 |
| Narendra NagarShree Vinayaka Developers | P50400031902 | 22 Nov 2021 | 31 Mar 2022 | — | Completed | 0 |
| Chhoriya Future City - Deoli Wardha PlottingChhoriya Developers and Construction Company | P50400031119 | 5 Oct 2021 | 31 Dec 2028 | — | Not yet due | 0 |
| Subhash NagarAdarsh Umre And Darshan Umre | P50400029937 | 15 Jul 2021 | 31 Mar 2023 | — | Promised date passed | 0 |
| Keshav ParkPunjab Keshavrao Raut | P50400026766 | 22 Oct 2020 | 30 Jun 2022 | — | Promised date passed | 0 |
| Balaji Nagari 2Anil Arunrao Karotkar | P50400025934 | 31 Jul 2020 | 30 Sep 2022 | — | Promised date passed | 0 |
| Balaji NagariAnil Arunrao Karotkar | P50400025913, P50400025914 | 29 Jul 2020 | 30 Sep 2022 | — | Completed | 0 |
| Laxminarayan Nagar Part IVDilip Wasudeorao Shankarpale | P50400020415 | 9 Apr 2019 | 30 Mar 2022 | — | Promised date passed | 0 |
Other localities in Deoli
Most active promoters
By projects registered here, as named on MahaRERA.
- Anil Arunrao Karotkar2 projects
- Adarsh Umre And Darshan Umre1 project
- Ashish Sharadkumar Tiwari1 project
- Ashish S. Tiwari And Archana M. Taori1 project
- Chhoriya Developers and Construction Company1 project
- Dilip Wasudeorao Shankarpale1 project
- Manish Sharadkumar Tiwari1 project
- Pratima Diliprao Shankarpale1 project
- Punjab Keshavrao Raut1 project
- Shree Vinayaka Developers1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology