Skip to content
Plotted · 1 building · 111 unitsRERA P50400049903

Mauli Park

Deedo IDDP-WAR-6SHJ

Completion was pushed back 4 months to Aug 2026, and that date has passed too; no MahaRERA orders on record; 17% of its units are booked.

Deoli (M Cl), Wardha 442101 · by Snehal Bhaiyajji Pisudde

Delivery7 mo latePromised Apr 2026 · revised Aug 2026 · that date has passed tooRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales17% booked19 of 111 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months to Aug 2026, and that date has passed too

  • This projectRegistered 6 Mar 2023, completion promised 30 Apr 2026, revised to 30 Aug 2026, and still not shown completed today.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP50400049903
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P504000499036 Mar 202330 Apr 202630 Aug 2026Snehal Bhaiyajji PisuddeProject page
Documents63

25 documents held by Deedo, 38 filings listed on MahaRERA's project page

Registration certificate

Other (8)

  • OtherDate not statedView
  • OtherDate not statedView
  • OtherDate not statedView
  • OtherDate not statedView
  • OtherDate not statedView
  • OtherDate not statedView
  • OtherDate not statedView
Show all 63 documentsShow fewer documents

Other (8)

  • OtherDate not statedView

Commencement certificate (2)

  • Commencement certificateDate not statedView
  • Commencement certificateDate not statedView

Title report

  • Title reportDate not statedView

Encumbrance details (2)

  • Encumbrance detailsDate not statedView
  • Encumbrance detailsDate not statedView

Layout plan (2)

  • Layout planDate not statedView
  • Layout planDate not statedView

Form 1 (6)

  • Form 1Date not statedView
  • Form 1Date not statedView
  • Form 1Date not statedView
  • Form 1Date not statedView
  • Form 1Date not statedView
  • Form 1Date not statedView

Allotment letter

  • Allotment letterDate not statedView

Form 2

  • Form 2Date not statedView

Form B

  • Form BDate not statedView

Legal

  • Declaration Form Bdeoli form b.pdf · uploaded 12 Dec 2022View
  • Legal Title reportdeoli search.pdf · uploaded 12 Dec 2022View

Migrated

  • 1 PAN Cardgopipan.pdf · uploaded 12 Dec 2022Source
  • 1 Copy of the legal title reportdeoli search.pdf · uploaded 12 Dec 2022View
  • 1 a Details of encumbrances concerned to Financedeoli encumbrance.pdf · uploaded 12 Dec 2022Source
  • 1 b Details of encumbrances concerned to Legaldeoli encumbrance.pdf · uploaded 12 Dec 2022Source
  • 1 Declaration in FORM Bdeoli form b.pdf · uploaded 12 Dec 2022View
  • 1 CERSAI detailscersai deoli 3.pdf · uploaded 12 Dec 2022View
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)deoliCA_compressed.pdf · uploaded 12 Dec 2022View
  • 1 Proforma of Allotment letterallotment.pdf · uploaded 12 Dec 2022View
  • 1 Proforma of Agreement for salerera agreement.pdf · uploaded 12 Dec 2022View
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the samenew bank declaration.pdf · uploaded 12 Dec 2022View
  • 1 Deviation Report with respect to Allotment letterdeoli deviation allotment.pdf · uploaded 12 Dec 2022View
  • 1 Deviation Report with respect to model copy of Agreementdeoli deviation agreement.pdf · uploaded 12 Dec 2022View
  • 1 Disclosure of Interest in Other Real Estate Organizationsotherprojects.pdf · uploaded 30 Dec 2022View
  • 2 a Details of encumbrances concerned to Financenew encumberance.pdf · uploaded 24 Jan 2023Source
  • 2 b Details of encumbrances concerned to Legalnew encumberance.pdf · uploaded 24 Jan 2023View
  • 1 Copy of Layout Approval (in case of layout)PLAN705PART1.pdf · uploaded 24 Jan 2023View
  • 1 Building Plan Approval / NA Order for plotted development705 p MC.pdf · uploaded 24 Jan 2023View
  • 1 Commencement Certificates / NA Order for plotted development705 p MC.pdf · uploaded 15 Feb 2023View
  • 1 Declaration about Commencement Certificatecc declaration 705.pdf · uploaded 1 Mar 2023View
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1.pdf · uploaded 7 Nov 2023Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 1.pdf · uploaded 7 Nov 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)FORM 2A.pdf · uploaded 7 Nov 2023View
  • 1 Status of Conveyance705 NA ORDDER.pdf · uploaded 7 Nov 2023View
  • 2 Status of ConveyanceNA FINAL.pdf · uploaded 7 Nov 2023View
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 A.pdf · uploaded 17 Nov 2023View
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 B.pdf · uploaded 17 Nov 2023Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 C.pdf · uploaded 17 Nov 2023View
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 0.pdf · uploaded 17 Nov 2023View
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 3.pdf · uploaded 17 Nov 2023View
  • 1 Disclosure of sold/ booked inventorySOLD BOOKED 1.pdf · uploaded 18 Nov 2023View
  • 2 Disclosure of sold/ booked inventorySOLD BOOKED 2.pdf · uploaded 18 Nov 2023View
  • 3 Disclosure of sold/ booked inventorySOLD BOOKED 3.pdf · uploaded 18 Nov 2023View

Technical

  • DocumentPLAN705PART1.pdf · uploaded 24 Jan 2023View
  • Document705 p MC.pdf · uploaded 24 Jan 2023View

Technical (Architect)

  • DocumentFORM 1 C.pdf · uploaded 17 Nov 2023View

Technical (Engineer)

  • DocumentFORM 2 3.pdf · uploaded 17 Nov 2023View

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 705 PART 1

As registered with MahaRERA and published on its project page

Project type
Plotted
Status on MahaRERA
Certificate Signed
Address
705 -PART 1, Layout on SURVEY NO. 705, DEOLIPIN 442101
Village
Deoli (M Cl), Deoli taluka
Land area for this project
11,932 sq m (1,28,433 sq ft)
Permissible built-up area
0 sq m (0 sq ft)
Sanctioned built-up area
0 sq m (0 sq ft)
Recreational open space
1,864 sq m (20,066 sq ft)
Designated bank account
76
Developed in phases
No

Survey, CTS, gat or plot numbers

705 PART 1

Land as published on MahaRERA's project page

705 -PART 1

Boundaries

North
Survey No 707
South
Survey No 713
East
Survey No 704 985
West
Remaining Part Of Survey No 705

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectKaustubh Waghmare—
Chartered accountantpallavi kaswa—
EngineerYash deshpande—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology