Ganesh Nagar Part - 4
Deedo IDDP-WAR-ZGXYMahaRERA shows it completed; no MahaRERA orders on record; 20% of its units are booked.
Deoli (M Cl), Wardha 442101 · by Pratima Diliprao Shankarpale
Buying a flat here?
See every deed registered on it.
MahaRERA shows it completed
- This projectRegistered 6 Mar 2023, completion promised 31 Mar 2025.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
2 buildings
Open a building to see every flat, floor by floor.
- 7sSize not on record0% booked
- Survey No. 194/3, Mauja : Deoli , Tah. Deoli & Dist., Wardha.Size not on record20% booked
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP50400049993
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P50400049993 | 6 Mar 2023 | 31 Mar 2025 | 31 Mar 2025 | Pratima Diliprao Shankarpale | Project page |
Documents95
46 documents held by Deedo, 49 filings listed on MahaRERA's project page
Show all 95 documentsShow fewer documents
Other (16)
Commencement certificate (3)
Form B
- Form BDate not statedView
Form 1 (14)
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
Allotment letter
- Allotment letterDate not statedView
Title report
- Title reportDate not statedView
Layout plan (6)
Form 2
- Form 2Date not statedView
Legal
Migrated
- 1 PAN CardPratima Shankarpale _ Pan card.pdf · uploaded 15 Feb 2023View
- 1 Copy of the legal title reportFORMAT A SEARCH.pdf · uploaded 15 Feb 2023View
- 1 a Details of encumbrances concerned to FinanceDECLARATION_NO ENCUMBRANCE.pdf · uploaded 15 Feb 2023View
- 1 b Details of encumbrances concerned to LegalDECLARATION_NO ENCUMBRANCE.pdf · uploaded 15 Feb 2023View
- 1 Copy of Layout Approval (in case of layout)SANCTIONED MAP.pdf · uploaded 15 Feb 2023View
- 1 Building Plan Approval / NA Order for plotted developmentNA ORDER PART 1.pdf · uploaded 15 Feb 2023View
- 2 Building Plan Approval / NA Order for plotted developmentNA ORDER PART 2.pdf · uploaded 15 Feb 2023View
- 1 Commencement Certificates / NA Order for plotted developmentNA ORDER PART 1.pdf · uploaded 15 Feb 2023View
- 2 Commencement Certificates / NA Order for plotted developmentNA ORDER PART 2.pdf · uploaded 15 Feb 2023View
- 1 Declaration about Commencement CertificateFORMAT-D.pdf · uploaded 15 Feb 2023View
- 1 Declaration in FORM BFORM B.pdf · uploaded 15 Feb 2023View
- 1 CERSAI detailsDECLARATION _CERSAI.pdf · uploaded 15 Feb 2023View
- 2 CERSAI detailsCERSAI_Search_Report_200260451027_For_Asset_Based_Search_15_02_2023_19_33_18_368.pdf · uploaded 15 Feb 2023View
- 1 Disclosure of sold/ booked inventoryBOOK SOLD INVENTORY.pdf · uploaded 15 Feb 2023View
- 1 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest.pdf · uploaded 15 Feb 2023View
- 1 Proforma of Agreement for salePROFORMA OF AGREEMENT TO SALE_PART 1.pdf · uploaded 15 Feb 2023View
- 2 Proforma of Agreement for salePROFORMA OF AGREEMENT TO SALE_PART 2.pdf · uploaded 15 Feb 2023View
- 1 Proforma of Allotment letterALLOTMENT LETTER.pdf · uploaded 15 Feb 2023View
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameDECLARATION_SEPERATE BANK ACCOUNT.pdf · uploaded 15 Feb 2023View
- 1 Deviation Report with respect to Allotment letterDECLARATION_ Deviation proforma of allotment letter.pdf · uploaded 15 Feb 2023View
- 1 Deviation Report with respect to model copy of AgreementDECLARATION_ Deviation of agreement to sale.pdf · uploaded 15 Feb 2023View
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 24 Feb 2023View
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentCompletion certificate_ Pratima.pdf · uploaded 2 Feb 2024View
- 1 Architect’s Certificate on Completion of Project (Form 4)Form 4_Pratima.pdf · uploaded 2 Feb 2024View
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 15 Feb 2024View
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 15 Feb 2024View
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A.pdf · uploaded 15 Feb 2024View
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 15 Feb 2024View
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5.pdf · uploaded 15 Feb 2024View
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_30-06-2023.pdf · uploaded 26 Mar 2024View
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_ 30-09-2023.pdf · uploaded 26 Mar 2024View
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_31-12-2023.pdf · uploaded 26 Mar 2024View
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2_30-06-2023.pdf · uploaded 26 Mar 2024View
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2_30-09-2023.pdf · uploaded 26 Mar 2024View
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2_31-12-2023.pdf · uploaded 26 Mar 2024View
- 2 Disclosure of sold/ booked inventoryBook Sold inventory_31-03-2023.pdf · uploaded 26 Mar 2024View
- 3 Disclosure of sold/ booked inventoryBook sold inventory_30-06-2023.pdf · uploaded 26 Mar 2024View
- 4 Disclosure of sold/ booked inventoryBook sold inventory_30-09-2023.pdf · uploaded 26 Mar 2024View
- 5 Disclosure of sold/ booked inventoryBook sold inventory_ 31-12-2023.pdf · uploaded 26 Mar 2024View
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3_30-06-2023.pdf · uploaded 26 Mar 2024View
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3_30-09-2023.pdf · uploaded 26 Mar 2024View
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3_31-12-2023.pdf · uploaded 26 Mar 2024View
Technical
Technical (Architect)
- DocumentForm 1_31-12-2023.pdf · uploaded 26 Mar 2024View
Technical (Engineer)
- DocumentForm 2_31-12-2023.pdf · uploaded 26 Mar 2024View
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 194/3
As registered with MahaRERA and published on its project page
- Project type
- Plotted
- Status on MahaRERA
- Certificate Signed
- Address
- 194/3, Survey No 194/3 Mauja Deoli, Wardha, Survey No 194/3 Mauja Deoli, WardhaPIN 442101
- Village
- Deoli (M Cl), Deoli taluka
- Land area for this project
- 13,409 sq m (1,44,333 sq ft)
- Permissible built-up area
- 13,409 sq m (1,44,333 sq ft)
- Sanctioned built-up area
- 0 sq m (0 sq ft)
- Recreational open space
- 2,315 sq m (24,922 sq ft)
- Designated bank account
- 171
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
194/3
Boundaries
- North
- Pratima Shankarpale Agri Land
- South
- Golhar Agri Land
- East
- Mamta P Patil Agri Land
- West
- Dekate Agri Land
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Niranjan Kande | — |
| Chartered accountant | Darshan Wakhariya | — |
| Engineer | Niranjan Kande | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Deoli (M Cl)
- Vaibhav Nagar 2RERA PP1340002501185
- Vaibhav Nagar - 1RERA PP1340002501102
- Mahesh NagarRERA P50400056379
- Mauli ParkRERA P50400049903
- Ganesh Nagar Part 2RERA P50400032052
- Mahalaxmi TownRERA P50400031865
- Narendra NagarRERA P50400031902
- Chhoriya Future City - Deoli Wardha PlottingRERA P50400031119
All 14 projects in Deoli (M Cl) · Compare Ganesh Nagar Part - 4 with another project