RERA projects in Pipri (Ct)
13 projects under 13 MahaRERA registrations, registered 2020–2025. 15% have a completion date extended beyond the one promised.
Locality
13RERA projects
13Registrations
2Completion still due11 past their completion date, 7 marked completed
24 monthsMedian extension beyond promised date15% of registrations extended
0Regulatory casesnone on MahaRERA's lists
10Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2020 | 1 |
| 2021 | 3 |
| 2022 | 3 |
| 2023 | 5 |
| 2024 | 0 |
| 2025 | 1 |
Projects in Pipri (Ct)
13 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Maa Vaishnavi Nagari 9- Wing IIINiklesh Deshmukh, Sangita Rithe, Priyanka Deshmukh, Vandana Deshmukh(Part. Maa Vaishnavi Buil.&Dev.) | P50400079698 | 20 Mar 2025 | 31 Dec 2028 | — | Not yet due | 0 |
| Gayatri ParkPavan S Vidhwani, Pradip V Giradkar, Shankarrao Champatrao Yeulkar, Vrushabh Anantrao Thakre | P50400054161 | 29 Dec 2023 | 31 Mar 2026 | — | Completed | 0 |
| New Mauli ParkSunil Purushottam Dhoble | P50400049645 | 22 Feb 2023 | 30 Jun 2024 | — | Promised date passed | 0 |
| Balaji Pride Commercial Cum Residential Complex on Plot no A and B in Sr No 39/3, 41/1-2,42/1-2Balaji Buildcon | P50400049090 | 30 Jan 2023 | 31 Mar 2024 | — | Promised date passed | 0 |
| Gurukrupa Nagari- Residential Layout Plan in Survey No 66/4/1AShree Krushnagiri Hospitality & Infra | P50400048619 | 10 Jan 2023 | 31 Mar 2024 | — | Completed | 0 |
| Gurukrupa Nagari - Residential Layout Plan in Survey No.66/4/1KMahesh Shankarrao Gulhane | P50400048459 | 3 Jan 2023 | 31 Mar 2024 | — | Completed | 0 |
| Sahas Paradise proposed Apartment on Plot 8 and 9 In Sr No 39/1SAHAS LAND AND INFRA DEVELOPERS PRIVATEl LIMITED | P50400047417 | 27 Oct 2022 | 31 Mar 2025 | — | Completed | 0 |
| Maa Vaishnavi Nagari 9 Wing 2Rajkumar Deshmukh Sangita Rithe (Partner Maa Vaishnavi Builders and Developers) | P50400046999 | 26 Sep 2022 | 31 Mar 2026 | — | Completed | 0 |
| Manmode Town Unit 1Sanjay Manmode And Mohan Manmode | P50400045574 | 24 May 2022 | 31 Mar 2025 | — | Promised date passed | 0 |
| Pratapgad ApartmentPioneer Builders | P50400031868 | 22 Nov 2021 | 31 Dec 2024 | — | Promised date passed | 0 |
| Bhaskar NagariBhushan Orke, Roshan Orke, Ashish Orke, Rekha Orke, Jyoti Bhele | P50400030280 | 15 Aug 2021 | 31 Mar 2024 | 30 Mar 2025 | Completed | 0 |
| Chalakh ArcadePandurang Govindrao Chalakh | P50400029388 | 29 May 2021 | 31 Mar 2023 | 31 Mar 2026 | Extended 36 mo | 0 |
| Maa Vaishnavi Nagari - 9Rajkumar Deshmukh Sangita Rithe (Partner Maa Vaishnavi Builders and Developers) | P50400024971 | 12 Mar 2020 | 30 Mar 2030 | — | Completed | 0 |
Other localities in Wardha
Most active promoters
By projects registered here, as named on MahaRERA.
- Rajkumar Deshmukh Sangita Rithe (Partner Maa Vaishnavi Builders and Developers)2 projects
- Balaji Buildcon1 project
- Bhushan Orke, Roshan Orke, Ashish Orke, Rekha Orke, Jyoti Bhele1 project
- Mahesh Shankarrao Gulhane1 project
- Niklesh Deshmukh, Sangita Rithe, Priyanka Deshmukh, Vandana Deshmukh(Part. Maa Vaishnavi Buil.&Dev.)1 project
- Pandurang Govindrao Chalakh1 project
- Pavan S Vidhwani, Pradip V Giradkar, Shankarrao Champatrao Yeulkar, Vrushabh Anantrao Thakre1 project
- Pioneer Builders1 project
- SAHAS LAND AND INFRA DEVELOPERS PRIVATEl LIMITED1 project
- Sanjay Manmode And Mohan Manmode1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology