Skip to content
Deedo home
Menu

RERA projects in Sindi Turf Hindnagar (Ct)

8 projects under 8 MahaRERA registrations, registered 2019–2023. None has an extended completion date on record.

Locality
8RERA projects
8Registrations
1Completion still due7 past their completion date, 1 marked completed
—Median extension beyond promised date0% of registrations extended
0Regulatory casesnone on MahaRERA's lists
1Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20191
20204
20212
20220
20231

Projects in Sindi Turf Hindnagar (Ct)

8 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Majestic HeightsEz DevelopersP5040005413529 Dec 202331 Dec 2026—Not yet due0
Shri Baba Aashirwad NagariMahesh Shankarrao GulhaneP5040003081714 Sep 202131 Mar 2023—Completed0
Aai Krupa NagariMahesh Shankarrao GulhaneP504000288335 Apr 202130 Sep 2023—Promised date passed0
Aai NagariManoj Vora, Anju Tiwari & Ujwala PurohitP5040002713319 Nov 202030 Sep 2022—Promised date passed0
Aai NagariDeepak Gangadhar MandokarP5040002438410 Feb 202030 Mar 2023—Promised date passed0
Aai NagariKrishnagiri DevelopersP504000243255 Feb 202030 Mar 2023—Promised date passed0
Aai nagariMahesh Shankarrao GulhaneP504000238166 Jan 202030 Mar 2023—Promised date passed0
Maa Mahalaxmi ResidencyMaa Vaishnavi InfraP504000207749 May 201930 Dec 2023—Promised date passed0

Other localities in Wardha

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Mahesh Shankarrao Gulhane3 projects
  2. Deepak Gangadhar Mandokar1 project
  3. Ez Developers1 project
  4. Krishnagiri Developers1 project
  5. Maa Vaishnavi Infra1 project
  6. Manoj Vora, Anju Tiwari & Ujwala Purohit1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology