1 project under 1 MahaRERA registration, registered 2020–2020. 100% have a completion date extended beyond the one promised.

Locality
1RERA projects
1Registrations
1Completion still due0 past their completion date
4 monthsMedian extension beyond promised date100% of registrations extended
0Regulatory casesnone on MahaRERA's lists
2Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20201

Projects in Bhaipur

1 project registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
R M Dhariwal Township - Arvi Bhaipur Plotting Phase - 2Dhariwal And Chhoriya Developers LLPP504000272961 Dec 202030 Jun 203030 Oct 2030Extended 4 mo0

Other localities in Arvi

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Dhariwal And Chhoriya Developers LLP1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology