RERA projects in Pimpalgaon (534463)

4 projects under 5 MahaRERA registrations, registered 2020–2024. None has an extended completion date on record.

4RERA projects
5Registrationssome projects hold several
0Completion still due5 past their completion date, 4 marked completed
—Median extension beyond promised date0% of registrations extended
0Regulatory casesnone on MahaRERA's lists
0Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20203
20210
20221
20230
20241

Projects in Pimpalgaon (534463)

4 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Sai NagarNiraj Lohakare, Sanjay Sharma, Sunil Langade, Vikram Taori And Pradeep NahaleP5040006652311 Jun 202431 Mar 2026—Completed0
Mauli parkVilas Narayanrao NewareP504000323734 Jan 202230 Aug 2024—Promised date passed0
Mahakali NagariKrishnagiri DevelopersP50400024659, P5040002485726 Feb 202030 Mar 2023—Completed0
Mahakali Nagri-7Atul Namdeo WandileP5040002462724 Feb 202030 Mar 2023—Completed0

Other localities in Hinganghat

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Atul Namdeo Wandile1 project
  2. Krishnagiri Developers1 project
  3. Niraj Lohakare, Sanjay Sharma, Sunil Langade, Vikram Taori And Pradeep Nahale1 project
  4. Vilas Narayanrao Neware1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology