Skip to content

RERA projects in Ajanti

2 projects under 2 MahaRERA registrations, registered 2022–2023. None has an extended completion date on record.

Locality
2RERA projects
2Registrations
0Completion still due2 past their completion date, 1 marked completed
—Median extension beyond promised date0% of registrations extended
0Regulatory casesnone on MahaRERA's lists
2Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20221
20231

Projects in Ajanti

2 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Armors NagarArmors Developers Private LimitedP504000513728 Jun 202331 Dec 202531 Dec 2025Promised date passed0
Vithai NagriPurushottam Wamanrao BhaimareP5040003260414 Jan 20221 Dec 2024—Completed0

Other localities in Hinganghat

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Armors Developers Private Limited1 project
  2. Purushottam Wamanrao Bhaimare1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology