8 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects522in 83 localities
Registrations534some projects hold several
Completion still due188259 past their date
Median extension4 months47% of registrations extended
Regulatory cases26on 26 projects

8 in 10 registrations run late here

534 MahaRERA registrations in Sindhudurg and the places within it

46 not yet due142 extended, not yet due259 past even the latest date87 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Sindhudurg

522 projects registered with MahaRERA in this district and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Siddhivinayak DevelopersSiddhivinayak DevelopersDue Dec 2027, extended 4 mo—33%
Srishti Aangan Phase 2Neeraj Mohan Desai HUFCompleted—90%
Usha Bhaskar ResidencyAbhay Sharad WalawalkarCompleted—54%
Sawantwadi EnclaveLandkraft Spaces Private LimitedCompleted——
DattaprasadVishavajit11 mo late——
VrindavanKalpak DevelopersDue Oct 2029, extended 4 mo—20%
Neelgiri HeightsAakar Builders & DevelopersCompleted, extended 1 yr—59%
Shree Mahalaxmi ResidencyManoj Vasant Mahadik5 mo late——
perto de goa phase R 1Ankit Vastu Creations Private LimitedDue Jun 2027——
Shri Datta ApartmentBahar Dasharath Bhosale2 yrs 5 mo late——
Samarth VaibhavSamarth Builders & DevelopersCompleted—55%
Rameshwar ComplexRameshwar ConstructionsDue Apr 2027, extended 4 mo—100%
Devdurg ElitesOmtech Associates8 mo late—5%
Omkar HomesSantosh Gopal Kode2 yrs 6 mo late——
Axis Lake CityGirirajji Infrastructure Private Limited1 yr 7 mo late——
Shridhar ApartmentVijay Shridhar TawdeCompleted——
EkdantparkShree Mahalakshmi Buildcon LLPDue Oct 2029, extended 4 mo—17%
Manish ResidencyArun Maruti RawoolCompleted—62%
Vedant Shopping MarketSantosh Govind Walavalkar1 yr 5 mo late——
Jaitapkarwadi Phase IIIPrakash Rajaram JaitapkarDue Oct 2029, extended 4 mo——
Shri Prasad ResidencyMrs Sunita Rajendra PatilCompleted——
Bhumaiyya ParkDattaraj Constructions2 yrs 11 mo late—32%
ATHANG HOMES Project By Morvekar RealtorsChandrashekhar Suryakant MorvekarCompleted—79%
Shree ResidencyManoj Vasant MahadikCompleted——
Green ValleyAjinkya ConstructionCompleted——
Sindhudurg market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Ajinkya Construction8 projects
  2. Sukhmani Constructions6 projects
  3. Ajinkkya Construction5 projects
  4. Nirmitee Builders & Developers5 projects
  5. Ranco Realty Pvt Ltd5 projects
  6. Benjamin Manwel Dsouza4 projects
  7. Chandrashekhar Suryakant Morvekar4 projects
  8. Consortexe Properties Pvt Ltd4 projects
  9. Manoj Vasant Mahadik4 projects
  10. Abhay Sharad Walawalkar3 projects

Sindhudurg, in questions

How many projects in Sindhudurg run late?

8 in 10 MahaRERA registrations (401 of 534): their completion date was extended or has passed, data through 20 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Sindhudurg by Deedo. Medians on fewer than 3 deeds are not shown.

Data through20 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology