Kolhapur
Deedo IDDL-KOL-KOLHAPUR8 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects873in 51 localities
Registrations885some projects hold several
Completion still due298492 past their date
Median extension4 months41% of registrations extended
Regulatory cases35on 35 projects
8 in 10 registrations run late here
885 MahaRERA registrations in Kolhapur and the places within it
87 not yet due211 extended, not yet due492 past even the latest date95 no date on record
Extended registrations moved their completion date by a median of 4 months.
Projects in Kolhapur
873 projects registered with MahaRERA in this district and the places within it.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Vrindavan HeightsMahalaxmi Buildcon | Due Apr 2029, extended 4 mo | — | — |
| Arnika Business BayParikh Sygmia Ventures | Due Feb 2029, extended 4 mo | — | — |
| Mg Market Block AMg Developers | Due Apr 2031, extended 4 mo | — | — |
| Sharad Pride 41Pratik Infra | Due Aug 2030, extended 4 mo | — | — |
| Shri Ram ResidencyShri Mangaraya Developers | Due Apr 2028, extended 4 mo | — | — |
| Green CountyMirajkar Nichite Builders And Developers Private Limited | Due Mar 2029 | — | — |
| Samarth ResidencyS P Associates | Due Apr 2031, extended 4 mo | — | — |
| The BalsamJotiraditya Builders | Due Apr 2031, extended 4 mo | — | — |
| Loknagari Karande MalaVikesh Abhaykumar Oswal | Due Jul 2030, extended 4 mo | — | — |
| Samarth Krupa ResidencySwamisamarthbuildon | Due May 2030, extended 4 mo | — | — |
| Nimbalkar HeritageMorbale Infra Project Private Limited | Due Apr 2030, extended 4 mo | — | — |
| Vasant Villas ResidencyShree Datta Developers | Due Apr 2030, extended 4 mo | — | — |
| Anant Pride Phase IIIAnant Estate Developers | Due Apr 2031, extended 4 mo | — | — |
| Sequoia RiseDevika Construction | Due Apr 2033, extended 4 mo | — | — |
| Vihanga ResidencyIndo Buildcon Developers | Due Apr 2031, extended 4 mo | — | — |
| Palace GrandeurMangal Realty | Due Apr 2030, extended 4 mo | — | — |
| Meen Kiran ResidencyBhumi Builders | Due Apr 2031, extended 4 mo | — | — |
| Goldenn ProsperaCskcon Private Limited | Due Apr 2029, extended 4 mo | — | — |
| Digvijay HeightsDigvijay Associates Builders Developers & Earthmovers | Due Jul 2031, extended 4 mo | — | — |
| Veerashri HeightsViraj Sunilkumar Sarnaik | Due Apr 2030, extended 4 mo | — | — |
| Lords HighlandBalraj Digambar Jadhav | Due Sep 2028, extended 4 mo | — | — |
| 33 West AvenueAtk Infra | Due Apr 2031, extended 4 mo | — | — |
| Brahmandnayak SankulLandmark Developers | Due Apr 2031, extended 4 mo | — | — |
| CellestiaBalaji Infra | Due Dec 2029, extended 4 mo | — | — |
| Ideal Aero PlazaIdeal Developers | Due Apr 2028, extended 4 mo | — | — |
Localities in Kolhapur
- Kolhapur (M Corp.)455 projects
- Karvir60 projects
- Ichalkaranji (M Cl)58 projects
- Gadhinglaj40 projects
- Ujalaiwadi (Ct)27 projects
- Gadhinglaj (M Cl)23 projects
- Jaysingpur20 projects
- Karvir20 projects
- Hatkanangle17 projects
- Jaysingpur (M Cl)16 projects
- Kagal (M Cl)16 projects
- Gadhinglaj13 projects
All 51 localities
- Vadgaon Kasba (M Cl)11
- Uchgaon (Ct)7
- Balinge6
- Gijavane4
- Kagal4
- Morewadi (Ct)4
- Ajara (Ct)3
- Vadgaon Kasaba3
- Gargoti2
- Hupari (Ct)2
- Kabnur (Ct)2
- Malkapur (M Cl)2
- Pachgaon (Ct)2
- Panhala2
- Sarnobatwadi2
- Wadipir2
- Yadrav2
- Ajra1
- Bambavade1
- Bhudargad1
- Chandgad1
- Danewadi1
- Gagan Bavda1
- Hatkanangale1
- Japhale1
- Kalambe T. Thane (Ct)1
- Kandalgaon1
- Kodoli1
- Madale1
- Majale1
- Nagdevwadi1
- Nrusinhawadi1
- Panhala (M Cl)1
- Radhanagari1
- Radhanagari1
- Shirol1
- Shiroli1
- Shiye1
- Vathar Tarf Vadgaon1
Other districts
Most active promoters
- Deshpande Infra7 projects
- Pune Housing and Area Development Board Pune7 projects
- Randive Builders And Developers7 projects
- Bhaskar Ramgonda Patil6 projects
- Pune Hsg. & Area Devp. Board6 projects
- Sd Associates5 projects
- Shendre And Associates5 projects
- The Ideal Construction5 projects
- Bedekar Lifespaces Llp4 projects
- Fortune Developers4 projects
Kolhapur, in questions
How many projects in Kolhapur run late?
8 in 10 MahaRERA registrations (703 of 885): their completion date was extended or has passed, data through 23 Nov 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Kolhapur by Deedo. Medians on fewer than 3 deeds are not shown.
Data through23 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology