8 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects873in 51 localities
Registrations885some projects hold several
Completion still due298492 past their date
Median extension4 months41% of registrations extended
Regulatory cases35on 35 projects

8 in 10 registrations run late here

885 MahaRERA registrations in Kolhapur and the places within it

87 not yet due211 extended, not yet due492 past even the latest date95 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Kolhapur

873 projects registered with MahaRERA in this district and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Vrindavan HeightsMahalaxmi BuildconDue Apr 2029, extended 4 mo——
Arnika Business BayParikh Sygmia VenturesDue Feb 2029, extended 4 mo——
Mg Market Block AMg DevelopersDue Apr 2031, extended 4 mo——
Sharad Pride 41Pratik InfraDue Aug 2030, extended 4 mo——
Shri Ram ResidencyShri Mangaraya DevelopersDue Apr 2028, extended 4 mo——
Green CountyMirajkar Nichite Builders And Developers Private LimitedDue Mar 2029——
Samarth ResidencyS P AssociatesDue Apr 2031, extended 4 mo——
The BalsamJotiraditya BuildersDue Apr 2031, extended 4 mo——
Loknagari Karande MalaVikesh Abhaykumar OswalDue Jul 2030, extended 4 mo——
Samarth Krupa ResidencySwamisamarthbuildonDue May 2030, extended 4 mo——
Nimbalkar HeritageMorbale Infra Project Private LimitedDue Apr 2030, extended 4 mo——
Vasant Villas ResidencyShree Datta DevelopersDue Apr 2030, extended 4 mo——
Anant Pride Phase IIIAnant Estate DevelopersDue Apr 2031, extended 4 mo——
Sequoia RiseDevika ConstructionDue Apr 2033, extended 4 mo——
Vihanga ResidencyIndo Buildcon DevelopersDue Apr 2031, extended 4 mo——
Palace GrandeurMangal RealtyDue Apr 2030, extended 4 mo——
Meen Kiran ResidencyBhumi BuildersDue Apr 2031, extended 4 mo——
Goldenn ProsperaCskcon Private LimitedDue Apr 2029, extended 4 mo——
Digvijay HeightsDigvijay Associates Builders Developers & EarthmoversDue Jul 2031, extended 4 mo——
Veerashri HeightsViraj Sunilkumar SarnaikDue Apr 2030, extended 4 mo——
Lords HighlandBalraj Digambar JadhavDue Sep 2028, extended 4 mo——
33 West AvenueAtk InfraDue Apr 2031, extended 4 mo——
Brahmandnayak SankulLandmark DevelopersDue Apr 2031, extended 4 mo——
CellestiaBalaji InfraDue Dec 2029, extended 4 mo——
Ideal Aero PlazaIdeal DevelopersDue Apr 2028, extended 4 mo——
Kolhapur market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Deshpande Infra7 projects
  2. Pune Housing and Area Development Board Pune7 projects
  3. Randive Builders And Developers7 projects
  4. Bhaskar Ramgonda Patil6 projects
  5. Pune Hsg. & Area Devp. Board6 projects
  6. Sd Associates5 projects
  7. Shendre And Associates5 projects
  8. The Ideal Construction5 projects
  9. Bedekar Lifespaces Llp4 projects
  10. Fortune Developers4 projects

Kolhapur, in questions

How many projects in Kolhapur run late?

8 in 10 MahaRERA registrations (703 of 885): their completion date was extended or has passed, data through 23 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Kolhapur by Deedo. Medians on fewer than 3 deeds are not shown.

Data through23 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology