10 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects2
Registrations2
Completion still due11 past their date
Median extension7 months100% of registrations extended
Regulatory cases0none on MahaRERA's lists

10 in 10 registrations run late here

2 MahaRERA registrations in Gargoti

1 extended, not yet due1 past even the latest date

Extended registrations moved their completion date by a median of 7 months.

Projects in Gargoti

2 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
RaigadRukmini Enterprises1 yr 11 mo late——
Shrihari EnclaveNandkumar Dasharath MaliDue Nov 2027, extended 4 mo—14%
Gargoti market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Nandkumar Dasharath Mali1 project
  2. Rukmini Enterprises1 project

Gargoti, in questions

How many projects in Gargoti run late?

10 in 10 MahaRERA registrations (2 of 2): their completion date was extended or has passed, data through 21 Oct 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Gargoti by Deedo. Medians on fewer than 3 deeds are not shown.

Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology